Bear Road Elementary School Additions and Renovations Tasks - - PowerPoint PPT Presentation

bear road
SMART_READER_LITE
LIVE PREVIEW

Bear Road Elementary School Additions and Renovations Tasks - - PowerPoint PPT Presentation

Bear Road Elementary School Additions and Renovations Tasks Underway Foundations for Area A addition are currently underway, backfill expected to start next week Asbestos Abatement Courtyard site work has begun Demolition in


slide-1
SLIDE 1

Bear Road Elementary School Additions and Renovations

slide-2
SLIDE 2

Tasks Underway

  • Foundations for Area A addition are

currently underway, backfill expected to start next week

  • Asbestos Abatement
  • Courtyard site work has begun
  • Demolition in various areas
  • Photos
  • Top: Courtyard site work
  • Bottom: Foundations in Area A
slide-3
SLIDE 3

Status of Asbestos Abatement

  • Area C asbestos abatement is underway,

expected to be completed in the first week

  • f August
  • Area A asbestos abatement is complete
  • Additional ACM discovered in exterior walls
slide-4
SLIDE 4

Status of Demolition

  • Area A Demolition Complete
  • Area C Demolition 50% complete
  • Crawlspace mechanical, electrical and plumbing

demolition is underway

  • Photos:
  • Top left and bottom: taken during Area A demolition
  • Top Right: taken during crawlspace demolition
slide-5
SLIDE 5

Bus Loop Mock-Up / Transportation

  • July 15th this area was simulated in the M&O parking lot
  • Drivers navigated the proposed route and provided

comments

  • Overall route is feasible though several concerns were

raised

  • A/E is reviewing and will share possible solutions at

next project meeting

slide-6
SLIDE 6

Wetlands Work

  • Storm drainage improvements from the

school to the wetlands will be taking place this summer

  • Photos
  • Top: existing conditions at storm drain outlet
  • Bottom: Proposed site grading plan from Appel

Osborne

slide-7
SLIDE 7

Upcoming Work

  • Structural Steel erection in Area A expected early

August

  • Plumbing rough in of Area A
  • Excavation of crawl space
  • Roofers expected to begin work by mid August
slide-8
SLIDE 8

Potential Roadblocks

  • COVID-19 impacts on material deliveries
  • Shortage of manpower due to private/public work

restarting simultaneously

slide-9
SLIDE 9

Where We Expect to be Come September

  • Steel super structure complete at the

Kindergarten wing

  • Roofing over Kindergarten wing
  • Corridor between Area A and Area B

complete

  • Wetlands / drainage improvements

complete

slide-10
SLIDE 10

Brick Work at Junior/Senior High School

  • Brick work at flashings, expected to be complete in approximately 2 months
slide-11
SLIDE 11

Playground Work

  • Main St. Playground demo scheduled for next week
  • Installation only a few weeks away
  • Bear Rd Playground design completed, many thanks to

committee members for all of their input and assistance

  • Virtual tour is available on district website

https://www.youtube.com/watch?v=vliRBWy2AqM&feature= youtu.be