Bear Road Elementary School Additions and Renovations Tasks - PowerPoint PPT Presentation

Bear Road Elementary School Additions and Renovations Tasks Underway Foundations for Area A addition are currently underway, backfill expected to start next week Asbestos Abatement Courtyard site work has begun Demolition in


  1. Bear Road Elementary School Additions and Renovations

  2. Tasks Underway • Foundations for Area A addition are currently underway, backfill expected to start next week • Asbestos Abatement • Courtyard site work has begun • Demolition in various areas • Photos • Top: Courtyard site work • Bottom: Foundations in Area A

  3. Status of • Area C asbestos abatement is underway, expected to be completed in the first week Asbestos of August • Area A asbestos abatement is complete Abatement • Additional ACM discovered in exterior walls

  4. Status of Demolition • Area A Demolition Complete • Area C Demolition 50% complete • Crawlspace mechanical, electrical and plumbing demolition is underway • Photos: • Top left and bottom: taken during Area A demolition • Top Right: taken during crawlspace demolition

  5. Bus Loop Mock-Up / Transportation • July 15 th this area was simulated in the M&O parking lot • Drivers navigated the proposed route and provided comments • Overall route is feasible though several concerns were raised • A/E is reviewing and will share possible solutions at next project meeting

  6. Wetlands Work • Storm drainage improvements from the school to the wetlands will be taking place this summer • Photos • Top: existing conditions at storm drain outlet • Bottom: Proposed site grading plan from Appel Osborne

  7. • Structural Steel erection in Area A expected early August Upcoming • Plumbing rough in of Area A Work • Excavation of crawl space • Roofers expected to begin work by mid August

  8. Potential Roadblocks • COVID-19 impacts on material deliveries • Shortage of manpower due to private/public work restarting simultaneously

  9. Where We Expect to be • Steel super structure complete at the Kindergarten wing Come • Roofing over Kindergarten wing September • Corridor between Area A and Area B complete • Wetlands / drainage improvements complete

  10. Brick Work at Junior/Senior High School • Brick work at flashings, expected to be complete in approximately 2 months

  11. Playground Work • Main St. Playground demo scheduled for next week • Installation only a few weeks away • Bear Rd Playground design completed, many thanks to committee members for all of their input and assistance • Virtual tour is available on district website https://www.youtube.com/watch?v=vliRBWy2AqM&feature= youtu.be

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.