PBJ Diversion

Sponsored by Bear lake SWCD Garth Boehme Chairman

slide-2
SLIDE 2

Project location

Bear Lake HUC # 16010201 Stream Effected:

Ovid Creek and Bear River

Pollutants:

Sediment

Beneficial uses

Cold Water Aquatic Life Secondary Contact Recreation Ag Water Supply Industrial Water Supply Wildlife Habitat Aesthetics

TMDL Load Reductions

Ovid Creek: 115 tons Bear River: 30 tons

slide-3
SLIDE 3

BMPs

Structure for water control Streambank Stabilization Measuring device Willow planting Fence

slide-4
SLIDE 4

Benefits Reduce 40 tons of sediment Stabilize 300ft of streambank Measure diversion rate Make the diversion safer to operate

slide-5
SLIDE 5

319 Match Total Administrative $8,437 $3,375 $11,812 Indirect $138 $0.00 $138 Subcontractual $102,198 $72,405 $174,603 Travel $4,536 $866 $5,402 Supplies, Operating, and Equipment $8,546 $6,374 $14,921 Total $123,857 $83,021 $206,878

PBJ Diversion Budget

slide-6
SLIDE 6

Questions