KWS Bear Road Renovation

Board of Education January 6, 2020

slide-2
SLIDE 2

Project Approval Status (Local Referendum)

Thank You!

The additional funding for the project was approved by an overwhelming majority

slide-3
SLIDE 3

Project Approval Status (SED)

  • Renovation Portion

– Submitted to SED, traditional review and approval process

  • Initial Engineering review complete, currently responding to their comments
  • Initial Architectural Review (Face-to Face), comments received and responses in progress
  • Current expectation of final approval in next 4-6 weeks
  • Roofing Portion

– Submitted to SED for Third Party Review last week

  • Expecting approx. 45 day review period
  • Currently exploring bid strategies to include a placeholder should it be necessary
slide-4
SLIDE 4

Next Steps

  • Bid Preparations

– “Final” review sessions to verify documents are complete (Entire project team comes together) – Finalize bid strategies and selection of alternates for bid protection and potential additional items – Final run at Cost Estimates

  • Community and Staff Engagement

– Today’s Phasing conversation – Faculty “Relocation” Committee – Kick off 1/14 – Community Forum – 1/16

slide-5
SLIDE 5

Project Phasing

  • Initial phasing plan was based upon the completed Smith Rd Renovations

– Multiple Phases – 16 month duration – Multiple Shifts – Swing Space

  • Since the beginning, this has been the assumption for Bear Road’s Project
  • Current Market conditions have lead us to question these assumptions
slide-6
SLIDE 6

What’s Changed

  • High Volume of work on the market, several area schools either out to bid or in queue with us
  • Statewide lack of construction labor resources, evidenced by our own current roofing projects
  • Increased cost of raw materials
  • Revisit original phasing plan to align with current market conditions
  • Explore alternatives to minimize impacts to student learning and ensure safety

Recommendation

slide-7
SLIDE 7

Updated Multi-Phase Plan (4 Phases)

  • 32-36 Month Duration
  • Relocation likely to impact 3 cohorts, 1 each school year, for 3 school years
  • Multiple moves of students and faculty remaining on location

– Possibility of moves during school year to maintain schedules

  • Limited Space, conflicts with parking and staging of construction materials
  • Maintaining separation of education and construction is complex
  • More likely to strain budget and increased potential for cost overruns
slide-8
SLIDE 8

Updated Multi-Phase Plan (4 Phases)

slide-9
SLIDE 9

Alternative Phasing Plan (2 Phases)

  • 24-27 month duration
  • Relocation likely to impact 3 cohorts, 2 each school year, for 2 years
  • No expectation for students and faculty remaining on location to be displaced in any school year
  • Ample Space, no expected conflicts with parking and staging of construction materials
  • Maintaining separation of education and construction is less complex
  • More likely to be under budget and significantly less potential for cost overruns
slide-10
SLIDE 10

Alternative Phasing Plan (2 Phases)

slide-11
SLIDE 11

Looking Ahead

  • Community and Staff Engagement does not end when the construction begins

– Staff “Relocation” Committee will be actively engaged for the duration of the project – Community Forums will continue as required to collect input and to share critical information – Periodic Updates – Website, letters home, etc. – Safety Briefings and Project Orientation for Students and Faculty, …

slide-12
SLIDE 12

KWS Bear Road: Current Floor Plan

50' 25' 15' 5' LOBBY 167 178 179 163 165 161 180 181 182 100 168 170 172 174 176 177 175 173 171 169 181A TOIL . 131A 130A TOIL . TOIL . 129A 127A 126A 128A 124A 122A TOIL . TOIL . 123A 125A CORRIDOR C5 TOIL . STORAGE STORAGE TABLE 115 ROOM BOYS LOCKER ROOM 163A 123 125 127 129 COURTYARD TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . TOIL . 176A 177A 174A 172A 173A 175A 171A 170A 168A 169A 156A 155A 153A 154A 152A 151A 150A 148A 146A 144A 142A 140A 138A 136A 121A 120A CLASSROOM 144 C9a VESTIBULE 181b 132 117 110B 104 101C 100B CUST FREEZER SPEECH PRINCIPAL MAIL RECEPT C4 C3 C9 C11 C10 C8 CLASSROOM 146 AUDIO VISUAL 119 100C C6 CORRIDOR C7 CORRIDOR CLASSROOM CLASSROOM CLASSROOM 134 136 138 140 142 148 150 152 154 156 151 153 155 157 159 157a 159a 158 LIBRARY RESOURCE ROOM RM. WORK CONFERENCE VISUAL AID CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM STORAGE CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM GYM GIRLS' LOCKER ROOM ART STORAGE JAN . CLOSET CLASSROOM CLASSROOM CLASSROOM CORRIDOR 163b CORRIDOR GYMNASIUM CLASSROOM STORAGE LOBBY CLOS TOILET 161a GYM INSTRUCTOR 160 165a TOILET TOILET STAGE 110C AUDITORIUM-CAFETERIA 110 TOIL . WAITING ROOM ROOM SPEECH 180a NURSE TEACHER'S ROOM CORRIDOR WORK TOIL . 100E 100D C2 MEN 113 JANITOR WOMEN 111 OFFICE PROC WORD 100A COOLER 101A KITCHEN STORAGE 101B DISHWASH. 109 KITCHEN 101 CORRIDOR 102 OFFICE 107 LOCKER ROOM 108 106 SWITCH ROOM 105 TRANSFORMER VAULT 104A STOR. 110A 103 BOILER ROOM 120 CLASSROOM 122 CLASSROOM 124 CLASSROOM 126 CLASSROOM 128 CLASSROOM 130 CLASSROOM 121 CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM 131
slide-13
SLIDE 13

KWS Bear Road: Preliminary Site Plan

slide-14
SLIDE 14

KWS Bear Road: Revised Floor Plan