Case Study: Active Vapor Mitigation System Design for a Complex - - PowerPoint PPT Presentation

case study
SMART_READER_LITE
LIVE PREVIEW

Case Study: Active Vapor Mitigation System Design for a Complex - - PowerPoint PPT Presentation

Case Study: Active Vapor Mitigation System Design for a Complex Industrial Building Renovation Application of Multiple Active Depressurization Technologies (ADT) in the Renovation of a Historical Landmark Building 2nd Annual RE3 Conference


slide-1
SLIDE 1

NTH Consultants, LTD.

Case Study: Active Vapor Mitigation System Design for a Complex Industrial Building Renovation

Application of Multiple Active Depressurization Technologies (ADT) in the Renovation of a Historical Landmark Building

January 29, 2014

2nd Annual RE3 Conference Philadelphia, Pennsylvania

slide-2
SLIDE 2

NTH Consultants, LTD.

Part 1:

Project Background

2

slide-3
SLIDE 3

NTH Consultants, LTD.

Project Background

Building Layout

3

Garage (slab on grade) Crawlspace (earthen) Basement Partially Excavated KEY Building Area = 253,000 ft2 Property = 3.94 Acres Base Drawing by NTH

slide-4
SLIDE 4

NTH Consultants, LTD.

Project Background

Building Layout

4

Native Silt and Clay Garage (slab on grade) Crawlspace (earthen) Basement Partially Excavated KEY Garage Floor 3 Floor 2 Floor 1 Floor 4…… Garage

(Future Gymnasium)

West Basement Crawlspace Conceptual Representation, not to scale Sandy Fill 1–4 ft.

slide-5
SLIDE 5

NTH Consultants, LTD.

Aerial View

Former Michigan Bell Building, Detroit, MI

5

slide-6
SLIDE 6

NTH Consultants, LTD.

Project Background

Contaminants of Concern

  • VOCs – Detected Below Building:

– Not all of below exceeded “generic” sub-slab residential soil gas screening levels: – However, not fully delineated due to access and water issues.

6 Compound Highest Soil Gas Conc. Detected (mg/m3) 1,1-DCA 8,800 1,1-DCE 5,500 cis-1,2-DCE 640 TCE 99 Benzene 260 Ethylbenzene 160 1,2,4-TMB 1,400 1,3,5-TMB 440

slide-7
SLIDE 7

NTH Consultants, LTD.

Criteria and Risk

Federal and State Requirements

  • More Stringent:

– Barriers integrated with active depressurization?

  • EPA guidance (current) suggests active often enough
  • Some State guidance recommended both
  • Required by HUD and MSHDA
  • Client Owner Risk Objectives:

– Future Property Use – Long Term Liability

  • Health: FCM (Fetal Cardiac Malformation)

– Short Term Exposure - TCE 2 mg/m3

  • NHDES recommends relocation even with a short term exposure risk

7

slide-8
SLIDE 8

NTH Consultants, LTD.

Part 2:

Construction Challenges

8

  • Bell Building, Stairwell, 2009. Preservation was required by historic commission.
slide-9
SLIDE 9

NTH Consultants, LTD.

Challenges and Unknowns

Designing a “Presumptive Remedy”

  • Unknown VOCs Concentrations:

– Water/access prevented full characterization

  • Silty Clay Soils:

– Below basements, depressurization influence issues

  • Various Sub-Slab Features:

– Grade beams, voids, or variable permeability fill – Utility Penetrations

  • Groundwater and Surface Water Infiltration:

– Active Sumps/Drains

9

slide-10
SLIDE 10

NTH Consultants, LTD.

10

…Possible vapor intrusion points?

slide-11
SLIDE 11

NTH Consultants, LTD.

11

slide-12
SLIDE 12

NTH Consultants, LTD.

Part 3: Demonstrating Vapor Control

Overcoming Building Envelope Effects

12

EPA 1993 Radon Guidance Target Sub-Slab Vacuum

  • Maintain “any measurable value” (all

season) above 0.001 in. H2O

  • In cold weather while appliances

running (heating systems) 0.015 in. H2O

  • In mild weather while appliances

running (cooling systems) 0.01-0.02 in. H2O.

  • Cold weather no appliances

0.025 -0.035 in. H2O

EPA 2008 VI Guidance: 4 to 10 Pascals (Pa) or 0.016 to 0.04 in H2O

slide-13
SLIDE 13

NTH Consultants, LTD.

13

Net Pressure Level (DP = 0) Net Pressure Level (DP = neg.) Net Pressure Level (DP = pos.)

  • Stack Effect – What is it?

– Significant in tall buildings

  • Stairwells, elevator shafts, etc.

– Air Pressure/Temperature/Humidity – Winter “stack effect” can result in LOWER (neg.) pressure lower levels – Architects control this with HVAC and entry vestibules, etc. – Drives potential for VI and affects design

Sub-Slab Depressurization Considerations Weather, Ventilation, and Architects

slide-14
SLIDE 14

NTH Consultants, LTD.

Got Stack Effects?

I think this qualifies

14

Summer Stack Effect On a hot day with air cond. on: POSITIVE Pres. +0.01 to +0.02 in. H2O DP on ground floor Winter Stack Effect On a cold day with heat on: NEGATIVE Pres.

  • 0.05 to - 0.06 in. H2O

DP on ground floor

slide-15
SLIDE 15

NTH Consultants, LTD.

Demonstrating Effectiveness

Need Year Round Vapor Control

  • Seasonal Variations:

– Highest vapor conc. in winter typically (Jan-Mar) (EPA 2012) – Affected by:

  • HVAC trends / Ventilation
  • Building Envelope-Specific
  • Barometric pressure swings

– Affected by source

  • Deeper source can result in greater

seasonal fluctuations (EPA 2012)

  • Groundwater fluctuations

15

Typical residential building exchange rates: 0.18 to 1.26 Air Changes Per Hour (ACH) Commercial/Industrial vary widely depending on use and area: 0.3 to 4.1 ACH (EPA 2011)

slide-16
SLIDE 16

NTH Consultants, LTD.

Demonstrating Effectiveness

Year Round Vapor Control

16

  • Design for a cold, windy day....
  • People Walking Up Hill In a Snow Storm

Wind Effects Windward Side of Building: POSITIVE Pres. +0.02 to +0.03 in. H2O Difference (typically upper floors have maximum DP) Barometric Pressure Effects Often Ignored as Insignificant: Swing of +/- 1 in. Hg. (1.2 feet H2O !) 20-75% transmission efficiency to sub-slab/soils Relation to Sub-Slab: Often see a positive pressure below the slab during sub-slab vacuum monitoring (before SSD activation) This is often stack effect and the potential driver for vapor intrusion

slide-17
SLIDE 17

NTH Consultants, LTD.

Building Pressurization

Viable Technique?

  • Mechanical Ventilation

– Intake / Relief Blowers cause pressure differential – Summer: Zero to Positive Pressure (+0.05 to +0.10

  • in. H2O)

– Winter: Zero to Negative (-0.02 to -0.10 in. H2O) – Building “tightness” controls ability to pressurize/depressurize

17

Ideal Building Pressurization for the Architect: Slight negative during winter and slight positive during summer….. Not good for our purposes.

  • If Excessive DP:

– Doors hard to open, “whistling” air exiting building windows/doors – Impedes air flow/temp. control in high pressure areas – Air infiltration / exfiltration, drafts – Affects HVAC loads/operation costs

slide-18
SLIDE 18

NTH Consultants, LTD.

Architects vs. Engineers

Can’t we just get along?

18

slide-19
SLIDE 19

NTH Consultants, LTD.

  • Compartmentalized Areas:

– Identified Major Structural Features:

  • Crawlspace
  • Slab on Grade (varying void space below)
  • Basement (water infiltration concerns)

– Other Special Features:

  • Partially unexcavated crawlspace (void below floor)
  • Smoke stack, elevator shafts, stairwells (contribute to stack effects)
  • Sumps, drains (floor/footer), utility penetrations, equipment
  • Basement Walls
  • Garage and loading docks
  • Requires Multiple Technologies and Verification:

– Unknowns (voids, grade beams, trenches) – Pilot and Post-Construction Verification

19

Base Drawing by NTH

Part 4:

Design Approach

slide-20
SLIDE 20

NTH Consultants, LTD.

Selecting Technologies

Providing Performance Verification

  • Active Depressurization:

– Sub-slab vacuum distribution

  • Overcome stack effects, HVAC, etc.
  • Ventilation (when depressurization not

suitable):

– Areas in contact with groundwater – Diffusion a concern due to potentially elevated sub-slab concentrations?

  • Demonstrate Effectiveness:

– SVE testing principles required for existing construction (pilot)

20

New Construction: A 200 scfm fan is suggested as being able to create a 0.02 in H2O vacuum over a 4,000 ft2 area within the crushed stone if slab leakage is not excessive (NAVFAC, 2011). One suction point per 5,000 ft2 (NAVFAC, 2011)

slide-21
SLIDE 21

NTH Consultants, LTD.

Part 5:

Design In Practice

21

slide-22
SLIDE 22

NTH Consultants, LTD.

Sub-Membrane Depressurization (SMD) Crawlspaces and Unexcavated Areas

  • Challenges:

– Considered ventilation via air exchanges (HVAC load issues) – Some areas not accessible (partially unexcavated areas) – Leakage points (concrete columns)

22

Drawings by NTH

slide-23
SLIDE 23

NTH Consultants, LTD.

Sub-Slab Depressurization Design

Garages / Slabs on Grade

  • Challenges:

– Soils vary from sand to silty clay with voids (high leakage) – Loading docks not accessible (SMD) – Leakage points (utilities, etc.) – Garage negative pressure per code

  • Design Parameters:

– Agency proposed 0.10 in H2O vacuum requirement

  • Typical SVE ROI design parameter

– Negotiated 0.075 in. H2O (still higher than most guidance)

  • Verification: Add more extraction points /

flow as needed to achieve vacuum distribution 23

Drawings by NTH

slide-24
SLIDE 24

NTH Consultants, LTD.

Sub-Slab Depressurization

West Garage - Before and After

24 Garages required ventilation for automobile exhaust

slide-25
SLIDE 25

NTH Consultants, LTD.

Sub-Slab Depressurization

First Floor – Before and After

25

Ground Level Showing Piping

slide-26
SLIDE 26

NTH Consultants, LTD.

Slab on Slab Ventilation Design

Basements

  • Challenges:

– Soils silty clay – Perched water in contact with basement / sumps – Sub-Slab Depressurization not viable

  • Design Parameters:

– Ventilation design – Air inlet points – Membrane, venting layer, and new slab – Integrated drains

26

Drawings by NTH

slide-27
SLIDE 27

NTH Consultants, LTD.

Cupolex and Polyurea

Technologies

  • Venting Layer:

– Original design was for gravel venting layer – Cupolex was coming into market

  • Provides open venting layer
  • Membrane:

– Polyurea Coating

  • More flexible and durable than epoxy
  • Developed for marine applications (deep sea oil platforms, tunnel coatings,

secondary containment, etc.)

  • Primer coat (urethane) and thick polyurea coatings (80 mil)
  • Low permeation rates (comparable to other liquid-applied membranes)
  • Spray over geotextile backing

27

slide-28
SLIDE 28

NTH Consultants, LTD.

Basement Drains

Ventilation

28

  • Maintained Functioning

Drains:

– Equipment Leaks / Pipe Breaks above – Perched Water below

slide-29
SLIDE 29

NTH Consultants, LTD.

Summary

Former Michigan Bell Building, Detroit, MI

  • Renovation:

– Funding received – Building renovated between 2011-2013 – Residents moving in as of 2012

  • Design:

– Presumptive Remedy Approach – must work under all conditions – Guidance available, but historical buildings often too complex – SVE Design Concepts

29

slide-30
SLIDE 30

NTH Consultants, LTD.

Thank You! Questions?

30

Scott C. Crawford, P.E. crawford@xdd-llc.com Steven Innes. P.E. sinnes@nthconsultants.com Robert Moore, P.E. rmoore@nthconsultants.com

Let your fingers do the walking….contact us!