Schematic Design Update for High School Additions/Renovations at Centennial HS, Roswell HS, and Tri-Cities HS June 11 , 2019 Overview Capital Plan 2022 High School Renovations Capital Renewal (Easy) Modifications and Additions for
Overview
Capital Plan 2022 High School Renovations
– Capital Renewal (Easy) – Modifications and Additions for Academic Programs (Difficult)
Challenges with Academic Programs in Capital Plan 2022:
– Budget – Construction market – Specific needs of each school – Priorities within educational specifications for identified programs – Site conditions / building limitations – Renovation vs New Construction
Objective is to Review and Approve Draft Schematics for:
– Centennial, Roswell, & Tri-Cities
2
Proposed Scope for Centennial HS
3
Academic Additions / Modifications
- CTAE Programs
- Public Safety
- Video Broadcasting
- Engineering (completed)
- Fine Arts Programs
- Physical Education Programs
- Black Box Theatre
Note: Existing Booster Club building will be converted to PE weight room.
EXISTING BOOSTER BUILDING TO BE USED AS PE WEIGHTROOM
Enlarged Plan for Centennial HS
4
5
Proposed Scope for Roswell HS
Alternate Bid Item Band Practice Area
Academic Additions / Modifications
- CTAE Programs
- Construction
- Cosmetology
- Engineering
(completed)
- Video
Broadcasting
- JROTC
- Fine Arts Programs
- Physical Education
Programs
- Black Box Theatre
Note: Existing rifle range will be renovated. Existing Booster Club building will be converted to PE weight room.
EXISTING BOOSTER BUILDING TO BE USED AS PE WEIGHTROOM
6
Enlarged Plan for Roswell HS
7
Proposed Scope for Tri-Cities HS
Academic Additions / Modifications
- CTAE Programs
- Engineering (completed)
- Culinary Arts
- Cosmetology
- Law and Justice
- Fine Arts Programs
- Physical Education Programs
- Black Box Theatre
BLACK BOX THEATER RENO FINE ARTS RENO
COSMET RENO
8
Enlarged Plan for Tri-Cities HS
Roswell HS & Centennial HS
- Capital Renewal Renovations - Summer 2019
- Remaining Construction Begins - Fall 2020
- Project Completion - Summer 2021
Tri-Cities HS
- Minor Renovations / Turf – Summer 2019
- Construction Begins - Fall 2020
- Project Completion-Summer 2021