Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo - - PowerPoint PPT Presentation

purple line extension
SMART_READER_LITE
LIVE PREVIEW

Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo - - PowerPoint PPT Presentation

Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations June 5, 2019 1 Agenda Project oject Overvi rview ew Section ion 2 Pre-Con onst struction uction Upda dates tes Section ion 1 Cons nstruct uction


slide-1
SLIDE 1

Purple Line Extension

Wilshire/La Cienega and Wilshire/Rodeo Stations June 5, 2019

1

slide-2
SLIDE 2

Agenda

2

  • Project
  • ject Overvi

rview ew

  • Section

ion 1 Cons nstruct uction

  • n Updates

dates

  • Wilshire/La Cienega Station

Excavation

  • Section

ion 2 Pre-Con

  • nst

struction uction Upda dates tes

  • Wilshire/Rodeo Station
  • Staging Yards
  • Utility Work
  • Geotechnical

Instrumentation

  • N Cañon Closure
  • Piling
  • Decking
  • Business

ness Inter terru rupt ption

  • n Fund
  • Eat Shop

p Play y #Beverly verlyHill ills

slide-3
SLIDE 3

Purple Line Extension

Project Alignment

3

slide-4
SLIDE 4

Sections 1, 2 & 3 Status

4 *Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Foreca cast sted ed Sched edule ule Section ion

Section 1 Section 2 Section 3

Leng ngth th

3.92 Miles 2.59 Miles 2.56 Miles

New Stat ation ions

Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital

Pre-Const nstruct ruction ion Activiti vities es

2014 – 2015 2016 – 2018 2018 – 2019

Const nstruct ruction ion

2015 – 2023 2018 – 2025 2019 – 2027

Opera rati tion

  • ns

2023 2025 2027

slide-5
SLIDE 5

Section 1

Wilshire/La Cienega Station

5

slide-6
SLIDE 6

Wilshire/La Cienega Station Box

6

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

slide-7
SLIDE 7

Wilshire/La Cienega Station

*As of June 2019, subject to change 7

slide-8
SLIDE 8

Wilshire/Gale

Intermittent Daily Gale Closure – North of Wilshire Bl

  • Gale Dr will be intermittently

closed Monday to Saturday, 6am to 6pm

  • This closure is a public safety

measure due to high volumes of ingress/egress from the property

  • Access to N Gale Dr will be

maintained from San Vicente Bl

  • Hauling operation to occur

until 10pm*

8

Gale Dr from north of Wilshire Bl

*Pending City of Beverly Hills approval

slide-9
SLIDE 9

Wilshire/La Cienega

9

Excavation progress inside Wilshire/La Cienega Station

slide-10
SLIDE 10

Wilshire/La Cienega – Upcoming Work

Instrumentation Work & Street Maintenance

When: Ongoing ing through gh 2019 Instrume ument ntation ion work on Wilshire ire Bl and La Cienega ga Bl

  • Intermittent lane reductions on

Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Street Maintenanc nce, e, Dewatering ing Well Maintenanc nce, e, and Utility ty Work on Wilshire e Bl

  • Intermittent lane reductions on Wilshire

Bl and side streets during off-peak hours (non-rush hour)

10

Example of instrumentation drilling

slide-11
SLIDE 11

Staging Yard Mitigation

La Cienega ga Yard

  • Active ventilation fans and fan

lines were wrapped with sound blankets

  • 24’ steel frame placed around

the ventilation system with sound blankets

  • Sound blankets surrounding

the ventilation system have been upgraded allowing for more sound absorption

11

Gale Yard

  • 14’ fences with sound blankets placed

around the crane

  • Applied an acoustic dampening material

to the 895 crane engine enclosure

  • Added a muffling panel on the exhaust

door and engine compartment door

  • Relocated slew alarm
  • Added a noise barrier rubber mat to the

lower engine panels

  • Acoustic plate under mounted on the

crane counterweight

  • Adjusted the crane start up schedule,

when possible

  • Started closing the gate, when feasible
  • Installed noise dampening louvre adjacent

to crane motor

slide-12
SLIDE 12

Section 2 Wilshire/Rodeo Station

slide-13
SLIDE 13

Wilshire/Rodeo Station Box

Station Box

13

Rendering shows length of the underground station box

  • n Wilshire Bl from Canon Dr to Beverly Dr
slide-14
SLIDE 14

Wilshire/Rodeo Station Schedule

*As of May 2019, subject to change. Pending Council approval. 14

slide-15
SLIDE 15
  • Upcom

coming ng Activi iviti ties es:

  • Site grading
  • Utility installation
  • Work

k hours rs: Monday – Friday, 8am – 6pm

  • Site for the future

re portal tal entra rance nce

  • Yard will contain:
  • Electrical substation
  • Ventilation system
  • Scrubbers
  • Water treatment plant
  • Equipment and material storage

15

Wilshire/Reeves Staging Yard

Draft Stag aging ng Yard rd layout

  • ut

*Subject to change

slide-16
SLIDE 16
  • N. Cañon Drive Staging Yard

Sidewalk Repair and Driveway Installation

  • Duration:

tion: 2 weeks

  • Start

t Date: e: Mid-June 2019

  • Work

k Hours: s: Monday – Friday 8am – 6pm

16

Traffi ffic c Control: ntrol:

  • Sidewalk closure in place

during work hours

  • Intermittent closure of

curb lane on Wilshire Bl and

  • N. Cañon Dr from 9am – 4pm
  • For your

r safety ety, do not t use street eets s as a walk lk way

slide-17
SLIDE 17
  • N. Cañon Staging Yard

Installation of Sound Wall

  • 20-foot sound wall around the staging yard will be installed to mitigate

noise to adjacent properties and public ROW

  • Antic

icipated pated Star art t Dat ate: e: Mid-June 2019

  • Compl

pleti etion

  • n Date:

e: July 2019

  • Work

k Hours: s: Monday – Friday, 8am – 6pm

17 *Subject to change

Photo of Reeves Staging Yard sound walls

slide-18
SLIDE 18

18

Utility Work

*Subject to change

Example of potholing for water line

  • Potholing work to identify

existing utilities below the street

  • Sewer and water line replacement and

relocation Start Date: April 8, 2019 Duration:

  • n: 6 months* for both potholing and

sewer and water line relocation Anticip ipated ted Compl pletion: ion: October 2019* Work Hours: rs:

  • Weekdays: 9am – 4pm
  • 8pm – 7am (as needed, per City approval)
  • Weekends: 10am – 6pm (as needed)

Traffic c Control

  • l
  • Lane and crosswalk closures as well as turn restrictions will be required for this work.
  • Two lanes in each direction will be maintained for day work on Wilshire Bl
  • One lane in each direction will be maintained for night work on Wilshire Bl
slide-19
SLIDE 19

19

Installation of Geotechnical Instrumentation

*Subject to change

Example of geotechnical instrument installation in Century City Instruments will be installed within the station box area to monitor ground movement, settlement and other geological conditions. These installations will be within the public right of way and within privately owned properties. Anticip ipated ted Start Date: June 24, 2019* Duration:

  • n: Will continue for several months in

coordination with other construction activities Work Hours: rs:

  • Weekdays: 7am – 4pm
  • Weekends: 8am – 7pm (as needed)

Traffic c Control

  • l
  • Intermittent lane, sidewalk, and crosswalk

closures will be required for this work.

  • Two lanes in each direction will be

maintained for day work on Wilshire Bl

  • One lane in each direction will be

maintained for night work on Wilshire Bl

slide-20
SLIDE 20
  • N. Cañon Drive Closure

Traffic Configuration

  • N. Canon Drive

Clifton Way Sound wall with art on Cañon Dr side and public information graphics on Wilshire Bl side

  • Install before piling for a minimum of 2 years
  • New traffic signal at Clifton/ Crescent
  • Existing meters / valet spaces on Clifton Way

shift to the north

  • Maintain existing valet time periods
  • Relocate some meters on N Cañon Dr from

East to West side Pedestrian walkway

slide-21
SLIDE 21
  • N. Cañon Drive Closure

Anticipated Summer 2019*

21 *Dates subject to change

slide-22
SLIDE 22

Wilshire Bl Piling Set-up

South Side Piling Set-up

22

Example of construction area with piling set-up on the south side of Wilshire Bl

slide-23
SLIDE 23

Wilshire Bl Piling Set-up

North Side Piling Set-up

23

Example of construction area with piling set-up on the north side of Wilshire Bl

slide-24
SLIDE 24

Pile Drilling Installation

24

Pile installat ation ion include des:

  • Drill rig to drill holes
  • Crane to lift piles into holes
  • Truck to backfill holes
  • All work occurs behind K-rail and/or

traffic closures Schedul dule

  • Following utility relocation, anticipated to

start Q3 of 2019

  • Work Hours:
  • 7 days a week
  • 8am – 9pm, drilling
  • 9pm – 11pm, non-drilling
  • Work in certain areas restricted to

weekends

Example of piling work in Century City

*Dates subject to change

slide-25
SLIDE 25

25

Pile Drilling Installation

Example of progress on Constellation Bl

slide-26
SLIDE 26

Decking

26

Followi

  • wing

ng Piling: g: Anticip ipate ated d late 2019* 9*

  • Construction of a concrete deck, curb-to-

curb on Wilshire Bl

  • Decking will serve as the temporary street

surface

  • Work Hours:

rs: Full closures Friday night at 8pm through Monday mornings at 7am for an anticipated 13 weekends

  • Metro will work closely with first responders
  • n emergency access and safety
  • Additional activities under decking closures:

ground improvements, piling, temporary civil improvements, dewatering system installation Asphalt removal on Wilshire Bl near Detroit St Steel beams welding prior to concrete deck panel installation

*Dates subject to change

slide-27
SLIDE 27

Help lping g loca cal l bu busines esses ses as we bu build. Purp rple le Line Ext xten ensio sion n Update te

slide-28
SLIDE 28

BIF Information and Eligibility

> Financial assistance to small “mom and pop” businesses with 25 or fewer full-time employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > Businesses are eligible for up to $50,000 per impact year

slide-29
SLIDE 29

BIF Information and Eligibility

> To date, 917 grants have been awarded with a total value of more than $21.8 million along all three project areas > Crenshaw/LAX Transit Project > Regional Connector, Little Tokyo area > Purple Line Extension Section 1 and Section 2 > February 2019 Metro’s Board of Directors authorized the expansion of the BIF to Section 3 of the Purple Line Extension

slide-30
SLIDE 30

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion n Secti tion

  • n 1 (as

s of 6/ f 6/03/19) 3/19) > BIF Grants Awarded: 195 > BIF Grant Amount Awarded: $5,034,835.09 > Number of small businesses awarded: 75 > City of Beverly Hills only > BIF Grants Awarded: 33 > BIF Grant Amount Awarded: $877,061.20 > Number of small businesses awarded: 14 > BIF Business Advisor: Brian Lazo, PCR, 213.739.2999

slide-31
SLIDE 31

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion n Secti tion

  • n 2 (as

s of 6/ f 6/03/19) 3/19) > BIF Grants Awarded: 47 > BIF Grant Amount Awarded: $1,330,913.59 > Number of small businesses awarded: 29 > City of Beverly Hills only > BIF Grants Awarded: 41 > BIF Grant Amount Awarded: $1,181,828.52 > Number of small businesses awarded: 25 > BIF Business Advisor: Darrell Smith, PCR, 213.739.2999

slide-32
SLIDE 32

32

Pione

  • neer

er Hardwa dware re 315 N Crescent Dr Beverly Hills, CA 90210 310.276.1167

slide-33
SLIDE 33

Construction Updates on La Cienega and Rodeo Stations Wednesday, July 10 6:30pm – 8pm

Beverly Hills City Hall 2nd Floor Municipal Gallery 445 N Rexford Dr Beverly Hills, CA 90210

2 hour free parking before 5pm Free after 5pm, no validation necessary

33

Next Construction Update

Beverly Hills

slide-34
SLIDE 34

Stay in Touch

34