overview
play

Overview Dave Pushka Mu2e Muon Beamline Vacuum Level 3 Manager 9 - PowerPoint PPT Presentation

Mu2e Muon Beamline Vacuum Overview Dave Pushka Mu2e Muon Beamline Vacuum Level 3 Manager 9 Feb 2017 Outline of Items Covered in this Review Presentation: Orientation Key Requirements Overview of the Geography of the Production


  1. Mu2e Muon Beamline Vacuum Overview Dave Pushka Mu2e Muon Beamline Vacuum Level 3 Manager 9 Feb 2017

  2. Outline of Items Covered in this Review Presentation: • Orientation – Key Requirements – Overview of the Geography of the Production Solenoid (PS) and Detector Solenoid (DS) and the Transport Solenoid (TSu and TSd) – Piping and Instrumentation Diagram (P&ID) • Outgassing Methodology & Gas Load Summations for upstream muon beamline vacuum volume and downstream muon beamline vacuum volumes – Pie Charts of Gas Loads for upstream and downstream volumes – What is missing from the Outgassing Summation? • Hand Calculations for upstream and downstream muon beamline vacuum volumes • MOLFLO+ methodology – MOLFLO+ Results for the Upstream MB vacuum volume (a.k.a PS + TSu) – MOLFLO+ Results for the Downstream MB vacuum volume (a.k.a TSd + DS) • Interfaces and Physical Equipment Arrangement (locations of vacuum pumps). • Schedule Slide • Initial Evacuation – Simultaneous Initial Evacuation of the upstream and downstream MB vacuum volumes • Contamination and Diffusion Pump Oil • Vessels and Safety Conformance • Thin Windows • Interlocks, FEMA • Repressurization • Back-Up Material (FEM Risk Assessment, Key Outgassing Rates, Catalog Cuts, Performance Curves) 2 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  3. Requirement Document and Summary of the Requirements: • Mu2e docdb document 1481 provides the requirements for the muon beam line vacuum, which include the key items: • Required pressure levesl: PS + TSu (Upstream); ≤1 x 10 -5 torr. – TSd + DS (Downstream); ≤1 x 10 -4 torr (assuming the tracker and calorimeter achieve their gas load – requirements) • Required vacuum pump down time: – ~ 100 hours. • Required pre-operational cleanliness: – standard high vacuum cleaning and degreasing. • Required operational cleanliness: – minimize, but not eliminate vacuum pump oil back-streaming. 3 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  4. Over View of the Geography: Downstream Vacuum Mu2e 0,0,0 & pbar window Upstream Vacuum Downstream Upstream Vacuum vacuum Pumps pumps 4 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  5. Over View of the Geography: 5 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  6. Hardware Deliverables for Muon Beamline Vacuum: Mechanical Roughing & Backing Pump Vacuum By-Pass Line Production Solenoid End Cap And High Vacuum Pump out Line Mechanical Roughing & Backing Pump Vacuum Pump Spool Piece, VPSP Instrumentation Feed Through Bulkhead, IFB 6 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  7. Context Material - Mu2e & Past Large Vacuum Experience: Mu2e Verses Previous Systems Goal Actual Material Year Vol Vol Pressure Pressure ft 3 liters torr torr KTeV 1994 5,500 155,742 1 x 10 -4 1 x 10 -6 painted C.S. NuMI Decay Pipe 2004 73,467 2,120,575 1 torr < 1 torr Rusty primed C. S. Mu2e PS 2020 424 11,993 1 x 10 -5 TBD 316L Mu2e DS 2020 1,321 37,378 1 x 10 -4 TBD 316L Grumman BSTS 1990 2,674 75,705 2 x 10 -7 6 x 10 -8 304 White Sands 1987 65,450 1,853,330 2 x 10 -6 8 x 10 -7 304 7 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  8. Details of the View of the Areas in the Upstream (PS+TSu): Pump out Line Bore PS-TS and TS-TS COL 1 and 3u Interface Area 8 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  9. Details of the View of the Areas in the Downstream (TSd+DS) Vacuum Volume: Tracker, Calorimeter, Absorbers not Muon Beam Stop shown, but estimates of gas loads are used in MOLFLO+ model Detector Solenoid VPSP IFB Col 5 TSd Col3 9 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  10. Piping And Instrumentation Diagram (P&ID) from 6489: 10 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  11. Outgassing and Vacuum Calculation Methodology: • Sum up the surface areas exposed to muon beamline vacuum • Assign material (SS, Al, Ti, W, fiberglass tape, etc) • Estimate temperature. • Assign outgassing rate for temperature at time = 1hour, 10 hours, etc. – Using achievable surface conditions – For example, the HRS is not likely to be ultra sonically washed, dried, baked and never touched by human hands again • Calculate gas load, Q = outgassing rate * area for various times • Determine pressure ignoring geometry (1 large volume) P=Q/S • Assign Outgassing to model in MOLFLO+ such that the total gas load matches the sum of the Area* Outgassing Rate for the real volume. – MOLFLO+ Surface areas are smaller than actual areas, but cross sectional areas are very similar. • Determine pressure as a function of location. 11 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  12. Outgassing Gas Load Values: • Have reasonable outgassing numbers for everything in the PS+TSu. • Have reasonable outgassing numbers for surfaces and materials in the TSd+DS with the except of the Tracker and Calorimeter and the associated cabling and services. – For the tracker, the requirement on the gas load is ≤0.08 torr-l/s, and that is the value adopted for this analysis • Solid Model for Tracker is available and has been checked w.r.t. the requirement document values – For the calorimeter, an estimate of the outgassing load has been extracted based upon the surface area and materials expected in the calorimeter • The details of the calorimeter are still being refined • The long term gas load of the calorimeter is required to be negligible compared to the tracker gas load requirement of ≤0.08 torr-l/s • Outgassing rates come from literature (Elsey, Dayton, Santler, etc.) See the next few slides: 12 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

  13. Outgassing Summations for the Upstream Volume (Spread sheet on docdb document 6470): contributes to Outgassing 10 hour 10 hour gas PS Vacuum: outgassing Area temperature material outgassing rate load PS DP Tee Section Y 17,866 25 316L 2.10E-08 3.75E-04 24 inch vacuum pipe: Y 48,192 25 316L 2.10E-08 1.01E-03 end cap truncated cone Y 55,824 35 316L 2.10E-08 1.17E-03 end cap vacuum pumpout nozzle Y 6,004 35 316L 2.10E-08 1.26E-04 End cap head Y 44,887 40 316L 2.10E-08 9.43E-04 end cap center port truncated cone Y 11,732 60 316L 2.10E-08 2.46E-04 end cap center port cylinder Y 4,775 60 316L 2.10E-08 1.00E-04 end cap beam exit nozzle Y 7,388 60 316L 2.10E-08 1.55E-04 end cap extinction nozzle Y 3,234 60 316L 2.10E-08 6.79E-05 Center Port Window Y 2,027 60 Ti 4.00E-09 8.11E-06 Beam Exit Window Y 507 60 Ti 4.00E-09 2.03E-06 Extinction Window Y 182 60 Ti 4.00E-09 7.30E-07 Primary beam entrance window by PS Y HRS cone Y 38,022 50 316L 2.10E-08 7.98E-04 HRS bore Y 31,233 60 316L 2.10E-08 6.56E-04 target Y 59 1500 W 2.00E-07 1.19E-05 target support ring Y 911 60 Al 1.10E-07 1.00E-04 target support wires Y 57 600 W 1.00E-07 5.65E-06 primary beam pipe in HRS Y 4,907 30 316L 2.10E-08 1.03E-04 primary beam pipe in TSU Y 6,193 30 316L 2.10E-08 1.30E-04 antiproton absorber Y 1,924 30 Al 1.10E-07 2.12E-04 HRS d.s. end Y 15,088 30 316L 2.10E-08 3.17E-04 HRS d.s. single convolute bellow Y 16,198 30 316L 2.10E-08 3.40E-04 HRS bellow radial plate Y 4,398 30 316L 2.10E-08 9.24E-05 P.S. d.s. end in vacuum Y 8,233 30 316L 2.10E-08 1.73E-04 PS d.s. end to bellows horz cyl Y 14,019 30 316L 2.10E-08 2.94E-04 13 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017 PS to Tsu bellows Y 61,928 30 316L 2.10E-08 1.30E-03 TSU u.s. ring from bellows Y 5,341 30 316L 2.10E-08 1.12E-04

  14. Outgassing Summations for the Downstream Volume (Spread sheet on docdb document 6470): 10 hour Contributes Outgassing outgassing 10 hour gas DS Vacuum: to Outgassing Area rate load temperature material cm^2 C torr-liters /s-cm2 torr-liters/s IFB shell, F10017417 Y 32,288 30 316L 2.10E-08 6.78E-04 VPSP, F10034792 Y 130,473 30 316L 2.10E-08 2.74E-03 VPSP rails Y 8,704 30 316L 2.10E-08 1.83E-04 VPSP D.S. Face at IFB Y 1,912 30 316L 2.10E-08 4.01E-05 DS Stub extension, FC0043184 Y 7,282 30 316L 2.10E-08 1.53E-04 DS Inner wall, F10005007 Y 645,849 30 316L 2.10E-08 1.36E-02 Bellows Closure Ring Y 3,809 30 316L 2.10E-08 8.00E-05 TSd - DS Bellow Y 60,479 30 316L 2.10E-08 1.27E-03 TSd O.D at DS Y 57,540 30 316L 2.10E-08 1.21E-03 TSd D.S. Face Y 18,776 30 316L 2.10E-08 3.94E-04 TSd Bore Y 106,725 30 316L 2.10E-08 2.24E-03 TSd Vertical U.S. Face Y 18,568 30 316L 2.10E-08 3.90E-04 TSd Bellows at COL3b Y 60,569 30 316L 2.10E-08 1.27E-03 TSd Bellows closure ring at COL3b Y 5,520 30 316L 2.10E-08 1.16E-04 TSd O.D at COL 3 Y 16,293 30 316L 2.10E-08 3.42E-04 Col 3b (assume = Col 3a from PS) 14 Dave Pushka | Muon Beamline Vacuum Overview Feb 9, 2017

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend