Oversight Team Meeting September 18, 2014 INTRODUCTIONS (15 - - PowerPoint PPT Presentation

oversight team meeting
SMART_READER_LITE
LIVE PREVIEW

Oversight Team Meeting September 18, 2014 INTRODUCTIONS (15 - - PowerPoint PPT Presentation

Oversight Team Meeting September 18, 2014 INTRODUCTIONS (15 MINUTES) Name and affiliation Review agenda Edits to Junes Oversight Team meeting summary Review the policy statements 2 Agenda Introduction (15 min) Statements from the


slide-1
SLIDE 1

Oversight Team Meeting

September 18, 2014

slide-2
SLIDE 2

INTRODUCTIONS (15 MINUTES)

Name and affiliation Review agenda Edits to June’s Oversight Team meeting summary Review the policy statements

2

slide-3
SLIDE 3

Agenda

 Introduction (15 min)  Statements from the public (10 min)  Discuss bridge types (25 min)  Break for lunch (20 min)  Recommend a bridge type for Final EIS (60 min)  Discuss construction phasing (20 min)  Technical work update (15 min)  Statements from the public (10 min)  Next steps (5 min)

3

slide-4
SLIDE 4

STATEMENTS FROM THE PUBLIC (10 MINUTES)

Name and affiliation Sign in so we know the number of speakers Each person has 2 minutes (please be respectful of the time limit) There is also time to speak at the end of the meeting

4

slide-5
SLIDE 5

BRIDGE TYPE DISCUSSION (25 MINUTES)

5

slide-6
SLIDE 6

Bridge types for the Final EIS

 Importance of bridge type discussion

 Assess bridge impacts in the Biological Assessment and Final

EIS document

 Comply with US Coast Guard (USCG) navigational requirements  Determine project cost estimate

 Bridge type needed for Final EIS analysis  Bridge design details decided upon post-Final EIS,

including:

 Aesthetic elements such as lighting, railings, facade treatments  Aesthetic bridge and street connections into the neighborhood

6

slide-7
SLIDE 7

Typical bridge type selection process

Identify possible bridge types Potential bridge types Concept design, cost estimates (per square foot), risks Feasible bridge types Select bridge type

Screening criteria

  • Engineering

constraints

  • Navigation
  • Aesthetics
  • Cost
  • Environmental
  • Accommodates

widening

  • Constructability
  • Maintenance

Pass/ fail Screening Initial Screening Final Screening

7

slide-8
SLIDE 8

Decisions made at last OT meeting

Alternative 1 - Cable-Stayed Alternative 2 - Steel Tied Arch Alternative 3 - Cast-in-place Segmental Concrete Box Girder Alternatives 4a - Segmental Precast Concrete Box or 4b - Steel Girder Alternative 5 - Precast Concrete T-Girder Alternative 2a – Single Steel Tied Arch Alternative 2b – Double Steel Tied Arch Alternative 3 - Cast-in- place Segmental Concrete Box Girder Alternatives 4a - Segmental Precast Concrete Box Alternatives 4b - Steel Girder

8

slide-9
SLIDE 9

Typical bridge type selection process

Identify possible bridge types Potential bridge types Concept design, cost estimates (per square foot), risks Feasible bridge types Select bridge type

Screening criteria

  • Engineering

constraints

  • Navigation
  • Aesthetics
  • Cost
  • Environmental
  • Accommodates

widening

  • Constructability
  • Maintenance

Pass/ fail Screening Initial Screening Final Screening

9

slide-10
SLIDE 10

Cost range

# Type Cost Range ($ million)

1 Cable-Stayed 2a Single Steel Tied Arch 2b Double Steel Tied Arch 3 Cast-in-place 4a Segmental Precast 4b Steel Girder 5 Precast Concrete Bulb-T Girder

90 100110 120 130 140 150 160 170 180 190 200 210 220 230 240 250

Estimated costs are for the approximately 4000 feet of structure, from Marine Drive NW to Commercial Street NE.

$175 - $245 $165 - $210 $110 - $160 $100 - $140 $95 - $120 $125 - $165 $95 - $135

slide-11
SLIDE 11

Alternative 2a – Single Steel Tied Arch

11

slide-12
SLIDE 12

Alternative 2a – Single Steel Tied Arch

12

slide-13
SLIDE 13

Alternative 2a – Single Steel Tied Arch

13

slide-14
SLIDE 14

Alternative 2a – Single Steel Tied Arch

14

slide-15
SLIDE 15

 Design options (to be determined in future phase)

Alternative 2a – Single Steel Tied Arch

15

slide-16
SLIDE 16

Alternative 2b – Double Steel Tied Arch

16

slide-17
SLIDE 17

Alternative 2b – Double Steel Tied Arch

17

slide-18
SLIDE 18

Alternative 2b – Double Steel Tied Arch

18

slide-19
SLIDE 19

Alternative 2b – Double Steel Tied Arch

19

slide-20
SLIDE 20

 Design options (to be determined in future phase)

Alternative 2b – Double Steel Tied Arch

20

slide-21
SLIDE 21

Alternative 3 – Cast-in-place Segmental Concrete Box Girder

21

slide-22
SLIDE 22

Alternative 3 – Cast-in-place Segmental Concrete Box Girder

22

slide-23
SLIDE 23

Alternative 3 – Cast-in-place Segmental Concrete Box Girder

23

slide-24
SLIDE 24

Alternative 3 – Cast-in-place Segmental Concrete Box Girder

24

slide-25
SLIDE 25

 Design options (to be determined in future phase)

Alternative 3 – Cast-in-place Segmental Concrete Box Girder

25

slide-26
SLIDE 26

Alternative 4a – Segmental Precast Concrete Box Girder

26

slide-27
SLIDE 27

Alternative 4a –Segmental Precast Concrete Box Girder

27

slide-28
SLIDE 28

Alternative 4a –Segmental Precast Concrete Box Girder

28

slide-29
SLIDE 29

Alternative 4a –Segmental Precast Concrete Box Girder

29

slide-30
SLIDE 30

 Design options (to be determined in future phase)

Alternative 4a –Segmental Precast Concrete Box Girder

30

slide-31
SLIDE 31

Alternative 4b – Steel Girder

31

slide-32
SLIDE 32

Alternative 4b – Steel Girder

32

slide-33
SLIDE 33

Alternative 4b – Steel Girder

33

slide-34
SLIDE 34

Alternative 4b – Steel Girder

34

slide-35
SLIDE 35

 Design options (to be determined in future phase)

Alternative 4b – Steel Girder

35

slide-36
SLIDE 36

Typical bridge type selection process

Identify possible bridge types Potential bridge types Concept design, cost estimates (per square foot), risks Feasible bridge types Select bridge type

Screening criteria

  • Engineering

constraints

  • Navigation
  • Aesthetics
  • Cost
  • Environmental
  • Accommodates

widening

  • Constructability
  • Maintenance

Pass/ fail Screening Initial Screening Final Screening

We are here

36

slide-37
SLIDE 37

BREAK (20 MINUTES)

Lunch is provided for Oversight Team members

37

slide-38
SLIDE 38

RECOMMEND A BRIDGE TYPE FOR FINAL EIS (60 MINUTES)

38

slide-39
SLIDE 39

Typical bridge type selection process

Identify possible bridge types Potential bridge types Preliminary design, quantities, cost estimates, risks Feasible bridge types Select bridge type

Screening criteria

  • Engineering

constraints

  • Navigation
  • Aesthetics
  • Cost
  • Environmental
  • Accommodates

widening

  • Constructability
  • Maintenance

Pass/ fail Screening Initial Screening Final Screening

We are here

39

slide-40
SLIDE 40

QUESTIONS/DISCUSSION

40

slide-41
SLIDE 41

DISCUSS CONSTRUCTION PHASING (20 MINUTES)

41

slide-42
SLIDE 42

Project Funding FHWA requires that a Financial Plan be developed with the following elements addressed:

 Project cost estimate  Implementation Plan  Financing and revenues  Cash flows  Risk identification and mitigation factors

42

slide-43
SLIDE 43

Potential Construction Phases

43

slide-44
SLIDE 44

Potential Construction Phases: “Phase B”

Estimated Cost: $300 million

Key Elements:

  • Construct new bridge and

ramp connections on both east and west sides of river

  • Realignment of Front Street

and other street widenings in North Salem

  • Widening of Wallace/Hope

Avenue intersection

  • Widening of Wallace/Orchard

Heights Road intersection

44

slide-45
SLIDE 45

Potential Construction Phases: “Phase M-South”

Estimated Cost: $16 million

Key Elements:

  • Construct southern section
  • f Marine Drive (from Hope

Avenue Extension to Glen Creek Road)

  • Construct Beckett Street
  • Construct extension of 5th

Avenue (from Cameo Street to Marine Drive)

45

slide-46
SLIDE 46

Potential Construction Phases: “Phase M-North”

Key Elements:

  • Construct northern section of

Marine Drive (from Hope Avenue Extension north to River Bend Road)

  • Connection to Wallace Road

via Harritt Drive extension

Estimated Cost: $10 million

46

slide-47
SLIDE 47

Potential Construction Phases: “Phase R”

Estimated Cost: $100 million

Key Elements:

  • Construct fly-over ramps

from Marine Drive to Highway 22

  • Construct Marine Drive at-

grade section between Glen Creek Road south to fly-over ramps

  • Modifications to Highway 22

47

slide-48
SLIDE 48

QUESTIONS/DISCUSSION

48

slide-49
SLIDE 49

TECHNICAL WORK UPDATE (15 MINUTES)

49

slide-50
SLIDE 50

Technical work

 Design refinements for bicycle, pedestrian, and

transit facilities

 Final EIS analysis of Preferred Alternative  Land use approval process  Funding workshop

50

slide-51
SLIDE 51

STATEMENTS FROM THE PUBLIC (10 MINUTES)

Name and affiliation Each person has 2 minutes (please be respectful of the time limit)

51

slide-52
SLIDE 52

NEXT STEPS (5 MINUTES)

52

slide-53
SLIDE 53

Next steps

 Funding Workshop: early December, 2014  Next OT meeting: December 11, 2014

53

slide-54
SLIDE 54

54

slide-55
SLIDE 55

Publish Draft EIS Preferred Alternative Endorsement of Preferred Alternative Land Use Approval Process TSP, TIP, and RTSP Amendments Final EIS

Financial Feasibility Report & Strategy Document

February 2014 NEPA Local Approvals Funding

EIS = Environmental Impact Statement FHWA = Federal Highway Administration NEPA = National Environmental Policy Act ROD = Record of Decision TIP = Transportation Improvement Program TSP = Transportation System Plan (for Cities and Counties) RTSP = Regional Transportation System Plan (for the SKATS MPO)

ROD Design & Construction May 2016

Right of entry and field work

June 2012

EIS process schedule

Publish Final EIS 08/22/14

slide-56
SLIDE 56

THANK YOU!

56