Summit Avenue Bridge
Public Participation Meeting #1 Project Introduction
4/5/2017 Public Participation Meeting #1
1
Summit Avenue Bridge Public Participation Meeting #1 Project - - PowerPoint PPT Presentation
4/5/2017 Public Participation Meeting #1 Summit Avenue Bridge Public Participation Meeting #1 Project Introduction 1 Presentation Outline Public Participation Meeting #1 4/13/2017 2 Purpose: Construct a bridge to safely accommodate
Public Participation Meeting #1 Project Introduction
4/5/2017 Public Participation Meeting #1
1
4/13/2017 Public Participation Meeting #1
2
4/13/2017 Public Participation Meeting #1
3
4/13/2017 Public Participation Meeting #1
4
Expect to see designs around July 2017
4/13/2017 Public Participation Meeting #1
5
4/13/2017 Public Participation Meeting #1
6
1897 1962 AYD MILL RD RAILROAD
4/13/2017 Public Participation Meeting #1
7
4/13/2017 Public Participation Meeting #1
8
4/13/2017 Public Participation Meeting #1
9
Roadway Bike Lane Shoulder Bridge Median Median Boulevard Sidewalk Other Paved SUMMIT GRIGGS SYNDICATE
4/13/2017 Public Participation Meeting #1
10 Around 9,000 vehicles/day Around 550 bikes/day Around 550 pedestrians/day Beneath Bridge: Ayd Mill Rd (20,000 veh/day) and CP Rail (12 trains/day)
4/13/2017 Public Participation Meeting #1
11
Rules & Regulations Geometric Constraints
4/13/2017 Public Participation Meeting #1
12 Roadway Safety Visual Impact Travel Needs Natural Resources Historic Review Utilities Watershed District MnDOT Cultural City Historians Public Artists Xcel & Water Dept City Parks City Planners Public Input Structural Integrity Districts & Wards Budget & Schedule Mayor & Council Maintenance Managers Consultant Services Contract Compliance MnDOT & FHWA Bridge Designers Traffic Engineers Residents & Business
Include… 1. Limited views 2. Slope off bridge 3. Curves 4. Lighting 5. Median use 6. Turning 7. Curb lines 8. Road width 9. Railing heights
4/13/2017 Public Participation Meeting #1
13 4% Overhead Elec Buried Pipe Lighting
RR clearances
Include… 1. Limited views 2. Slope off bridge 3. Curves 4. Lighting 5. Median use 6. Turning 7. Curb lines 8. Road width 9. Railing heights
4/13/2017 Public Participation Meeting #1
14 Lighting Median Turns Xing
4/13/2017 Public Participation Meeting #1
15
4/13/2017 Public Participation Meeting #1
16
4/13/2017 Public Participation Meeting #1
17
influenced our decisions. This meeting will be Informational Only.
4/13/2017 Public Participation Meeting #1
18
Rules & Regulations Geometric Constraints
4/13/2017 Public Participation Meeting #1
19 Roadway Safety Visual Impact Travel Needs Natural Resources Historic Review Utilities Watershed District MnDOT Cultural City Historians Public Artists Xcel & Water Dept City Parks City Planners Public Input Structural Integrity Districts & Wards Budget & Schedule Mayor & Council Maintenance Managers Consultant Services Contract Compliance MnDOT & FHWA Bridge Designers Traffic Engineers Residents & Business
20
4/13/2017 Public Participation Meeting #1
1. How do you use the Summit Avenue Bridge? Select all that apply.
4/13/2017 Public Participation Meeting #1
S0
Driving Biking Walking/Jogging Other: ______________ 2. Rank the following ISSUES in order of importance to you:
Issue Rank 1 to 6 (1 is most important) Accommodate Multi-Modal Use ___ Improve the “Look” of the Bridge ___ Improve Safety at Intersections or Crossings ___ Maintain or Restore Historic Bridge/Road Features ___ Minimize Traffic Impacts During Construction ___ Other: ___________________________________ ___
4/13/2017 Public Participation Meeting #1
S1
The bridge is >100’ wide. Extra width adds to construction and maintenance costs. Excess width tends to promote speeding.
vehicles, bicyclists and pedestrians. During design phase, the project team will:
4/13/2017 Public Participation Meeting #1
S2
The bridge is a combination of parts built in 1897 and 1962. The deck and railing is very simple. Piers and abutments vary.
constraints to provide a clean, visually pleasing bridge design. During design phase, the project team will:
4/13/2017 Public Participation Meeting #1
S3
Bridge approaches “flare out” based on a historic road design. Sightlines and speed contribute to safety at road intersections.
and accessibility, as well as bike/vehicle turning movements. During design phase, the project team will:
Roadway Bike Lane Shoulder SUMMIT
4/13/2017 Public Participation Meeting #1
S4
The bridge is located within the Summit West Heritage Preservation District and is subject to local and state review.
impacts” to the surrounding West Summit historic district. During design phase, the project team will:
4/13/2017 Public Participation Meeting #1
S5
Summit Avenue is a popular route for work commuting, recreation, and special events. There will be inconveniences.
can be phased or timed to reduce inconvenience to the public. During design phase, the project team will:
4/13/2017 Public Participation Meeting #1
F
Brent Christensen City Bridge Designer & Engineer Jeannette Rebar Community Engagement Coordinator
Website: www.stpaul.gov/summit-bridge Email: summit-bridge@stpaul.gov Phone: 651-266-6180