1 Hamner Avenue Bridge Project Introduction Project Overview - - PowerPoint PPT Presentation

1 hamner avenue bridge project introduction project
SMART_READER_LITE
LIVE PREVIEW

1 Hamner Avenue Bridge Project Introduction Project Overview - - PowerPoint PPT Presentation

Hamner Avenue at Santa Ana River Bridge Replacement Project 1 Hamner Avenue Bridge Project Introduction Project Overview Project Update Q & A 2 Existing Hamner Avenue Bridge Existing bridge is 36 feet


slide-1
SLIDE 1

Hamner Avenue at Santa Ana River Bridge Replacement Project

1

slide-2
SLIDE 2

Hamner Avenue Bridge Project

  • Introduction
  • Project Overview
  • Project Update
  • Q & A

2

slide-3
SLIDE 3

Existing Hamner Avenue Bridge

  • Existing bridge is 36 feet wide
  • One lane in each direction plus a narrow sidewalk
  • 29,000 vehicles daily
  • 2045 Projection - 40,000 vehicles

3

slide-4
SLIDE 4

Existing Hamner Avenue Bridge

  • Bridge is 80 Years Old
  • Structurally Deficient

4

slide-5
SLIDE 5

Existing Hamner Avenue Bridge

December 2010 Storms

5

slide-6
SLIDE 6

Hamner Avenue Bridge Replacement Improvements

6

slide-7
SLIDE 7

Hamner Avenue Bridge Replacement

Funding Sources

7

  • Funding Sources

 HBP Funds: 88.53%  Local Matching Funds: 11.47%  SB 132  TUMF

slide-8
SLIDE 8

8

New Plan & profile

slide-9
SLIDE 9

9

New Cross Section

slide-10
SLIDE 10

10

Stage-1

slide-11
SLIDE 11

11

Stage-1 Cross Section

slide-12
SLIDE 12

12

Stage -2

slide-13
SLIDE 13

13

Stage-2 Cross section

slide-14
SLIDE 14

Hamner Avenue at Santa Ana River Bridge Replacement Project

Existing Bridge

  • Length = 676 ft
  • Width = 36 ft
  • 2 Lanes

Proposed Bridge

  • Length = 1200 ft
  • Width = 101 ft
  • 6 Lanes
  • State of the Art

 Structural Design  Seismic Design  Hydraulic Design  Multi-Purpose Trail

P14

slide-15
SLIDE 15

Proposed Hamner Avenue Bridge

15

slide-16
SLIDE 16

Multi-Purpose Trail

16

slide-17
SLIDE 17

View From River

17

slide-18
SLIDE 18

Hamner Avenue Roadway

18

slide-19
SLIDE 19

Retaining Walls

19

slide-20
SLIDE 20

Construction Challenges

  • Maintain Traffic During Construction
  • Minimize Impacts

 Environmental  Right of Way (No Permanent Takes)  Utilities (No Impacts on Transmission Lines)

  • SB 132 Funding

 Construction Deadline by June 2023

  • Coordination with Roadway Widening Project

20

slide-21
SLIDE 21

Project Update

  • Environmental Clearance (Completed)
  • Environmental Permits (Completed)
  • Temporary Construction Easements (Almost Completed)
  • Utility Coordination (Completed)
  • Project Plans (May 2020)
  • Anticipated Start of Construction (January 2021)

21

slide-22
SLIDE 22

Hamner Avenue Bridge Replacement

Schedule

22

2017 2018 2019 2020 2021 2022 2023

Construction Ends Construction Begins Final Plans Environmental Documentation

slide-23
SLIDE 23

Hamner Avenue Bridge RFP Requirements

23

  • Inquiries

– County of Riverside Transportation Department Attention: Hector Davila, Construction Project Manager Email: hedavila@rivco.org

  • RFP Key Dates

– Mandatory Pre-Proposal meeting (02/19/20) – Written Questions from Firms Due (02/26/20) – Latest Date for Addenda (03/04/20) – Closing Date for RFP (03/23/20) – Notification of Short List Selection (04/08/20) – Interviews (04/17/20) – DBE goal is 17%

slide-24
SLIDE 24

Hamner Avenue Bridge Replacement

24

Q&A