25 th avenue grade separation december 13 2017 agenda i
play

25 th Avenue Grade Separation December 13, 2017 Agenda I. - PowerPoint PPT Presentation

25 th Avenue Grade Separation December 13, 2017 Agenda I. Overview II. Project Description III. Project Benefits IV. Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25 th Ave Railroad Crossing


  1. 25 th Avenue Grade Separation December 13, 2017

  2. Agenda I. Overview II. Project Description III. Project Benefits IV. Project Construction V. Next Steps VI. Questions 2

  3. Overview

  4. Project Location 4

  5. E. 25 th Ave Railroad Crossing • 92 Caltrain trains each weekday use this crossing, in addition to freight • Lack of grade separation increases delays along corridor 5

  6. Project Description

  7. Project Elements Construct Grade Separation (elevated rails, lowered roads) between Hillsdale Blvd and Highway 92  Concrete bridge 25 th & 28 th Ave  Steel bridge at 31 st Ave  Concrete retaining walls  MSE walls 7

  8. Elevated Track 8

  9. Grade Separation (25th Ave) 9

  10. East-West Connection (28th Ave) 10

  11. East-West Connection (31st Ave) Ramp Access to Ped Viaduct 11

  12. Relocated Hillsdale Station 12

  13. Station Improvements 13

  14. Station Improvements – Mosaic Wall Station Signage 14

  15. Station Improvements Stairway Entrance to Platform 15

  16. Station Improvements - Platform New Station Platform, Shelters, Lights 16

  17. Station Improvements - Furnishings 17

  18. New Hillsdale Station Access 18

  19. Project Funding, in Millions Measure A $74 City of San Mateo $84 State Section 190 State HSR Prop 1A $12 $10 19

  20. Project Benefits

  21. Project Benefits • Safe rail operations • Fewer system-wide delays • Improved traffic flow • Improved pedestrian and motorist safety • Facilitate Caltrain electrification which will reduce noise and vibration 21

  22. Project Construction

  23. Schedule: Overview Activity Date Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Oct 2017 – Dec 2018 Hillsdale Station Temp Parking (available for public use) Nov 2017 – Mar 2019 Bridges and MSE Walls Nov 2017 – Oct 2019 E. 25 th Ave. (lane closures) May 2018 – Oct 2019 Bridge at E. 25th Ave (14FT clearance) 23

  24. Schedule: Overview cont. Activity Date Dec 2018 – May 2019 Station Closed Road Completed – 28 th Ave May 2019 Oct 2019 – Dec 2019 E. 25 th Ave. Closure (full) Oct 2019 – 31 st Ave Roads Completed Dec 2019 – 25 th Ave Project Completed Jan 2020 24

  25. Schedule: Night Work Overview Activity Date Nov 2017 – Dec 2017 Temporary Sheet Pile Shoring Nov 2017 – Feb 2018 Cast-in-drilled-hole pile construction Feb 2018 – July 2018 MSE walls March 2018 – July 2018 Bridge Final Track Cutover Nov 2018 25

  26. Existing Hillsdale Station Temporary Parking Lot Temporary Parking Lots Construction Activities 26

  27. Hillsdale Station Closure • Enhanced train service provided at Belmont Station • Enhanced Samtrans bus and shuttle service provided between Hillsdale and Belmont Stations 27

  28. Hillsdale Station Closure • Passengers who drive, get dropped off or use transit  use Belmont Station • Passengers who walk to Hillsdale  take Samtrans bus (ECR Line) or shuttle to Belmont Station • Shuttle schedule will match enhanced train schedule • Shuttle pick-up location at east triangular lot 28

  29. Example Lane Closure: 25th Ave 29

  30. Work Hours • Majority of construction activities will take place Mon-Fri during the day • Certain construction activities require work to be completed at night or on weekends when there is reduced or no revenue train service • JPB will notify community in advance of nighttime and weekend work

  31. Potential Impacts during Construction Noise and Vibration Impacts: • Temporary: Only during construction • Construction equipment and (Not to Scale) procedures selected to monitor noise and vibration impacts • Noise monitoring station at Peninsula Station (2901 ECR)

  32. Construction Impacts / Mitigation • Single tracking trains • Shoring Work o Pre-drilling (will also occur during day) o Different equipment obtained • Pile Work: Additional crew/equipment

  33. Next Steps

  34. Construction Notices Example of mailed notice 34

  35. Public Outreach & Community Engagement • Project website: www.caltrain.com/25thGS • Construction Outreach Hotline: 650.508.7726 • Email: SMGradeSep@Caltrain.com • Regular Updates and Public Meetings  Prior to Station Closure  Prior to Street Closure

  36. 36

  37. Contact Construction Information Service Information Office of Public Affairs Customer Service Department Phone: 650.508.7726 Phone: 800.660.4287 1250 San Carlos Avenue PO Box 3006 San Carlos, CA 94040-1306 www.caltrain.com/25thGS

  38. Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend