25 th avenue grade separation
play

25 th Avenue Grade Separation JPB Board April 4, 2019 Agenda - PowerPoint PPT Presentation

25 th Avenue Grade Separation JPB Board April 4, 2019 Agenda Item#10 Agenda I. Project Need, Benefits & Description II. Construction Construction Status Construction Challenges III. Contract and Budget 2 Project Need,


  1. 25 th Avenue Grade Separation JPB Board April 4, 2019 – Agenda Item#10

  2. Agenda I. Project Need, Benefits & Description II. Construction – Construction Status – Construction Challenges III. Contract and Budget 2

  3. Project Need, Benefits and Description

  4. Project Location 4

  5. E. 25 th Ave Railroad Crossing • 92 Caltrain trains each weekday use this crossing, in addition to freight • No. 8 on California Public Utilities Commission (CPUC) priority list for railroad crossing safety. 5

  6. Project Benefits • Enhanced East-West connectivity • Improved pedestrian and motorist safety • Improved traffic flow • Fewer system-wide delays • Support Caltrain electrification • Improve Customer experience with new Station • Enable future California High Speed Rail (CAHSR) • Safe rail operations 6

  7. Factors Driving Award Date • Coordination with Peninsula Corridor Electrification Project (PCEP) required expedited Contract award: – Foundations Constructed as part of 25 th Grade Separation (GS). – Poles and wires installed by PCEP 7

  8. Risk Factors at Award • Fiber Optic relocation was pending resolution of negotiations with Union Pacific Railroad (UPRR) • Funding from CAHSR was pending 8

  9. Contract Award • Contract Awarded to Shimmick Disney JV July 2017 for $ 82,890,000 • Original Completion Date Jan. 2020. 9

  10. Project Funding, in Millions $ 180 Project Measure A $74 City of San Mateo $84 State Section 190 State HSR Prop 1A $12 $10 10

  11. Project Elements Construct Grade Separation (elevated rails, lowered roads) between Hillsdale Blvd and Highway 92  Five bridges  Approx. 1 mile of Mechanically Stabilized Earth (MSE) Wall  New elevated station at Hillsdale 11

  12. Elevated Track 12

  13. East-West Connection (28th Ave) 13

  14. Relocated Hillsdale Station 14

  15. Construction - Status

  16. Progress • Bridges – Beresford Creek Bridge Complete – Four (4) remaining Bridges substructure complete; superstructure ongoing. • Wall Construction – North of 25 th Complete this month – Betwn 25 th and 28 th Ongoing 16

  17. Bridges 17

  18. MSE Wall 18

  19. Construction - Challenges

  20. Project Impacts Utility Relocation – Major Utility relocations by Utility Companies, including:  Fiber Optic Duct Bank  PGE Gas Line  ATT Communication Duct Bank Station – Relocation and opening delayed by 10 months, with an anticipated opening of June 2020 20

  21. Impacts Due To Fiber Optic 21

  22. Working Around Live Fiber 22

  23. PG&E Gas Line Relocation 23

  24. AT&T 24

  25. Weather Impacts 2018-2019 “Atmospheric Rivers”  Caused Project Delays due to excess rain days  Created significant stormwater flows requiring substantial dewatering 25

  26. Weather Impacts 26

  27. Contract and Budget

  28. Contract and Budget • All impacts from the Fiber Optic delay in 2018 have been addressed and the project schedule has been re-baselined. • Fiber Optic delays continued through March 2019. Total Project Delayed up to 12 months. Current Anticipated Completion Date of January 2021. • Return to this board with a recommendation to: increase Contract Authority; No additional budget needed • No current impact to PCEP 28

  29. Questions

  30. Grade Separation (25th Ave) 30

  31. East-West Connection (31st Ave) 31

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend