25th Avenue Grade Separation

JPB Board April 4, 2019 – Agenda Item#10

slide-2
SLIDE 2

Agenda

I. Project Need, Benefits & Description II. Construction – Construction Status – Construction Challenges III. Contract and Budget

2

slide-3
SLIDE 3

Project Need, Benefits and Description

slide-4
SLIDE 4

Project Location

4

slide-5
SLIDE 5
  • E. 25th Ave Railroad Crossing
  • 92 Caltrain trains each weekday use this

crossing, in addition to freight

  • No. 8 on California Public Utilities Commission

(CPUC) priority list for railroad crossing safety.

5

slide-6
SLIDE 6

Project Benefits

  • Enhanced East-West connectivity
  • Improved pedestrian and motorist safety
  • Improved traffic flow
  • Fewer system-wide delays
  • Support Caltrain electrification
  • Improve Customer experience with new Station
  • Enable future California High Speed Rail

(CAHSR)

  • Safe rail operations

6

slide-7
SLIDE 7

Factors Driving Award Date

  • Coordination with Peninsula Corridor

Electrification Project (PCEP) required expedited Contract award: – Foundations Constructed as part of 25th Grade Separation (GS). – Poles and wires installed by PCEP

7

slide-8
SLIDE 8

Risk Factors at Award

  • Fiber Optic relocation was pending resolution
  • f negotiations with Union Pacific Railroad

(UPRR)

  • Funding from CAHSR was pending

8

slide-9
SLIDE 9

Contract Award

  • Contract Awarded to Shimmick Disney JV July

2017 for $ 82,890,000

  • Original Completion Date Jan. 2020.

9

slide-10
SLIDE 10

Project Funding, in Millions

$74 $12 $10 $84

Measure A City of San Mateo State Section 190 State HSR Prop 1A

10

$ 180 Project

slide-11
SLIDE 11

Project Elements

Construct Grade Separation (elevated rails, lowered roads) between Hillsdale Blvd and Highway 92

  • Five bridges
  • Approx. 1 mile of Mechanically

Stabilized Earth (MSE) Wall

  • New elevated station at Hillsdale

11

slide-12
SLIDE 12

Elevated Track

12

slide-13
SLIDE 13

East-West Connection (28th Ave)

13

slide-14
SLIDE 14

Relocated Hillsdale Station

14

slide-15
SLIDE 15

Construction - Status

slide-16
SLIDE 16

Progress

  • Bridges

– Beresford Creek Bridge Complete – Four (4) remaining Bridges substructure complete; superstructure ongoing.

  • Wall Construction

– North of 25th Complete this month – Betwn 25th and 28th Ongoing

16

slide-17
SLIDE 17

Bridges

17

slide-18
SLIDE 18

MSE Wall

18

slide-19
SLIDE 19

Construction - Challenges

slide-20
SLIDE 20

Project Impacts

Utility Relocation – Major Utility relocations by Utility Companies, including:

  • Fiber Optic Duct Bank
  • PGE Gas Line
  • ATT Communication Duct Bank

Station – Relocation and opening delayed by 10 months, with an anticipated opening of June 2020

20

slide-21
SLIDE 21

Impacts Due To Fiber Optic

21

slide-22
SLIDE 22

Working Around Live Fiber

22

slide-23
SLIDE 23

PG&E Gas Line Relocation

23

slide-24
SLIDE 24

AT&T

24

slide-25
SLIDE 25

Weather Impacts

2018-2019 “Atmospheric Rivers”

  • Caused Project Delays due to excess

rain days

  • Created significant stormwater flows

requiring substantial dewatering

25

slide-26
SLIDE 26

Weather Impacts

26

slide-27
SLIDE 27

Contract and Budget

slide-28
SLIDE 28

Contract and Budget

  • All impacts from the Fiber Optic delay in 2018 have

been addressed and the project schedule has been re-baselined.

  • Fiber Optic delays continued through March 2019.

Total Project Delayed up to 12 months. Current Anticipated Completion Date of January 2021.

  • Return to this board with a recommendation to:

increase Contract Authority; No additional budget needed

  • No current impact to PCEP

28

slide-29
SLIDE 29

Questions

slide-30
SLIDE 30

Grade Separation (25th Ave)

30