25 th Avenue Grade Separation San Mateo Community Meeting December - - PowerPoint PPT Presentation

25 th avenue grade separation san mateo community meeting
SMART_READER_LITE
LIVE PREVIEW

25 th Avenue Grade Separation San Mateo Community Meeting December - - PowerPoint PPT Presentation

25 th Avenue Grade Separation San Mateo Community Meeting December 20, 2017 Agenda I. Overview II. Project Description III. Project Benefits IV. Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25


slide-1
SLIDE 1

25th Avenue Grade Separation

San Mateo Community Meeting December 20, 2017

slide-2
SLIDE 2

Agenda

I. Overview II. Project Description III. Project Benefits IV. Project Construction V. Next Steps VI. Questions

2

slide-3
SLIDE 3

Overview

slide-4
SLIDE 4

Project Location

4

slide-5
SLIDE 5
  • E. 25th Ave Railroad Crossing
  • 92 Caltrain trains each weekday use this

crossing, in addition to freight

  • Lack of grade separation increases delays

along corridor

5

slide-6
SLIDE 6

Project Description

slide-7
SLIDE 7

Project Elements

Construct Grade Separation (elevated rails, lowered roads) between Hillsdale Blvd and Highway 92

  • Concrete bridge 25th & 28th Ave
  • Steel bridge at 31st Ave
  • Concrete retaining walls
  • MSE walls

7

slide-8
SLIDE 8

Elevated Track

8

slide-9
SLIDE 9

Grade Separation (25th Ave)

9

slide-10
SLIDE 10

East-West Connection (28th Ave)

10

slide-11
SLIDE 11

East-West Connection (31st Ave)

11

Ramp Access to Ped Viaduct

slide-12
SLIDE 12

Relocated Hillsdale Station

12

slide-13
SLIDE 13

Station Improvements

13

slide-14
SLIDE 14

Station Improvements – Mosaic Wall

14

Station Signage

slide-15
SLIDE 15

Station Improvements

15

Stairway Entrance to Platform

slide-16
SLIDE 16

Station Improvements - Platform

16

New Station Platform, Shelters, Lights

slide-17
SLIDE 17

Station Improvements - Furnishings

17

slide-18
SLIDE 18

New Hillsdale Station Access

18

slide-19
SLIDE 19

Project Funding, in Millions

$74 $12 $10 $84

Measure A City of San Mateo State Section 190 State HSR Prop 1A

19

slide-20
SLIDE 20

Project Benefits

slide-21
SLIDE 21

Project Benefits

  • Safe rail operations
  • Fewer system-wide delays
  • Improved traffic flow
  • Improved pedestrian and motorist safety
  • Facilitate Caltrain electrification which will

reduce noise and vibration

21

slide-22
SLIDE 22

Project Construction

slide-23
SLIDE 23

Schedule: Overview

23

Activity Date Mobilization Sept 2017 - Oct 2017 Begin Construction Oct 2017 Hillsdale Station Temp Parking (available for public use) Oct 2017 – Dec 2018 Bridges and MSE Walls Nov 2017 – Mar 2019

  • E. 25th Ave. (lane closures)

Nov 2017 – Oct 2019 Bridge at E. 25th Ave (14FT clearance) May 2018 – Oct 2019

slide-24
SLIDE 24

24

Activity Date Station Closed Dec 2018 – May 2019 Road Completed – 28th Ave May 2019

  • E. 25th Ave. Closure (full)

Oct 2019 – Dec 2019 Roads Completed Oct 2019 – 31st Ave Dec 2019 – 25th Ave Project Completed Jan 2020

Schedule: Overview cont.

slide-25
SLIDE 25

25

Activity Date Temporary Sheet Pile Shoring Nov 2017 – Dec 2017 Cast-in-drilled-hole pile construction Nov 2017 – Feb 2018 MSE walls Feb 2018 – July 2018 Bridge March 2018 – July 2018 Final Track Cutover Nov 2018

Schedule: Night Work Overview

slide-26
SLIDE 26

Existing Hillsdale Station Temporary Parking Lot

26

Temporary Parking Lots Construction Activities

slide-27
SLIDE 27

Hillsdale Station Closure

  • Enhanced train service provided at Belmont

Station

  • Enhanced Samtrans bus and shuttle service

provided between Hillsdale and Belmont Stations

27

slide-28
SLIDE 28

Hillsdale Station Closure

  • Passengers who drive, get dropped off or

use transit  use Belmont Station

  • Passengers who walk to Hillsdale  take

Samtrans bus (ECR Line) or shuttle to Belmont Station

  • Shuttle schedule will match enhanced

train schedule

  • Shuttle pick-up location at east triangular

lot

28

slide-29
SLIDE 29

Example Lane Closure: 25th Ave

29

slide-30
SLIDE 30

Work Hours

  • Majority of construction activities will take

place Mon-Fri during the day

  • Certain construction activities require work to

be completed at night or on weekends when there is reduced or no revenue train service

  • JPB will notify community in advance of

nighttime and weekend work

slide-31
SLIDE 31

Potential Impacts during Construction

Noise and Vibration Impacts:

  • Temporary: Only during

construction

  • Construction equipment and

procedures selected to monitor noise and vibration impacts

  • Noise monitoring station at

Peninsula Station (2901 ECR)

(Not to Scale)

slide-32
SLIDE 32

Construction Impacts / Mitigation

  • Single tracking trains
  • Shoring Work
  • Pre-drilling (will also occur during day)
  • Different equipment obtained
  • Pile Work: Additional crew/equipment
slide-33
SLIDE 33

Next Steps

slide-34
SLIDE 34

Construction Notices

34

Example of mailed notice

slide-35
SLIDE 35

Public Outreach & Community Engagement

  • Project website:

www.caltrain.com/25thGS

  • Construction Outreach Hotline: 650.508.7726
  • Email: SMGradeSep@Caltrain.com
  • Regular Updates and Public Meetings
  • Prior to Station Closure
  • Prior to Street Closure
slide-36
SLIDE 36

36

slide-37
SLIDE 37

Contact

Construction Information Service Information

Office of Public Affairs Phone: 650.508.7726 Customer Service Department Phone: 800.660.4287 1250 San Carlos Avenue PO Box 3006 San Carlos, CA 94040-1306 www.caltrain.com/25thGS

slide-38
SLIDE 38

Questions