esquimalt graving dock waterlot sediment remediation
play

Esquimalt Graving Dock Waterlot Sediment Remediation Phase 1B - PowerPoint PPT Presentation

Esquimalt Graving Dock Waterlot Sediment Remediation Phase 1B Open-Water Dredging Presenters: Tim Smiley Tervita - Project Manager Water Solu:ons, Environmental Services Kris:en


  1. Esquimalt Graving Dock Waterlot Sediment Remediation Phase 1B Open-Water Dredging Presenters: ¡ Tim ¡Smiley ¡– ¡Tervita ¡-­‑ ¡Project ¡Manager ¡– ¡Water ¡Solu:ons, ¡Environmental ¡Services ¡ Kris:en ¡Seabloom ¡– ¡Fraser ¡River ¡Pile ¡and ¡Dredge ¡(GP) ¡Inc ¡-­‑ ¡Senior ¡Project ¡Manager ¡ RPIC ¡OIawa ¡– ¡April ¡14-­‑16, ¡2014 ¡

  2. Introduction Esquimalt Graving Dock (EGD) • South Western tip of Vancouver Island, Esquimalt BC • PWGSC owned and operated since 1927 (constructed 1921-1926) • “open-access” multi-user facility • Largest deep-sea shipbuilding and repair facility on Canada’s Pacific coast • Accommodate “Panamax” size vessels • Phase 1B Project – 9.7 Ha April 15, 2014 | Slide 2 of 20

  3. Introduction EGD Waterlot Remediation Phase 1B – Open-Water Dredging 37 million dollar contract to • Tervita via competitive tender FRPD – major marine • subcontractor Project at a glance: • • 150,000 m 3 open-water dredging, transportation, disposal • Structure demolition and reinstatement • Slope protection • Residual management cover April 15, 2014 | Slide 3 of 20

  4. Administration & Contract Management Major Submittals Prior to Ongoing Submittals • • Mobilization Daily/Weekly Reports • Construction Work Plan Daily Multi-Beam • • Hydrographic Survey Environmental Protection • Plan Weekly progress meetings • Quality Control Plan 300+ Request for • • Information Health and Safety Plan • 300+ Advisories • Complete construction • schedule Approximately 10 change • orders Monthly progress billing • Updated schedule • April 15, 2014 | Slide 4 of 20

  5. Structural Demolition, Reinstatement & Slope Protection Removal (Demolition) • and Reinstatement of: • Timber dock fender system • Marina floats, breakwater structure • Various site floats Slope Protection • • Slope filter layer • Slope armour layer April 15, 2014 | Slide 5 of 20

  6. Operation of Active Drydock Facility Completion of zones to • meet EGD operations EGD booking schedule Working without • interrupting an active dry-dock facility Adapting to a changing • schedule Ongoing coordination and • communication with EGD operations Requirement to leave • 50% of the South Jetty and North Landing Wharf for EGD operations use April 15, 2014 | Slide 6 of 20

  7. Dredging by Sequence Sequential design to work • zone by zone Work two marine derricks • concurrently while maintaining the sequential order Adapt sequence as • required to meet EGD operational requirements Comply with DFO permit • and restrictions on particular zones CFSA Marina protection • April 15, 2014 | Slide 7 of 20

  8. Types of Dredging at EGD Land based excavators – • 4,000 m3 Mechanical dredging with • a clamshell - 145,000 m3 Diver assisted suction • dredging for sensitive structures – 50 m3 April 15, 2014 | Slide 8 of 20

  9. Marine Derrick and Bucket Positioning Real Time Kinetic • (RTK) Receivers Crane and Barge • Positioning (Qinsy) Electronic depth • control via line counters (first time for FRPD) Surface updated • daily from multi- beam survey and continuous from derrick software April 15, 2014 | Slide 9 of 20

  10. Water Quality Concerns and Mitigations Silt curtains (7m deep) • Sealed material barges • No passive dewatering • Bucket cycle times varied • as required Level cut environmental • clamshell bucket (contractor choice) Contractor supplied • environmental monitor QC Full time PWGSC water • quality monitoring consultant QA April 15, 2014 | Slide 10 of 20

  11. Barging Logistics Transporting • contaminated soil Authorization by Victoria • Harbour Master and Queens Harbour Master (Esquimalt) Inclement weather • conditions (wind/waves/ fog) Move to Plumper Bay • mid way through the project April 15, 2014 | Slide 11 of 20

  12. Water Resources Transfer Water management: • • 250m 3 high turbidity water per barge • Lock block wall wrapped in filter cloth Challenges: • • Debris • Sludge • Thixotropic material Solution • • Gabion wall • Slurry and Vacuum Trailer April 15, 2014 | Slide 12 of 20

  13. Water Resources Treatment Water Barges: • • 2 Identical equipment setups on similar barges Water Storage: • • 500m 3 on deck • 1,100m 3 below deck Treatment: • • Average throughput 20L/ sec April 15, 2014 | Slide 13 of 20

  14. Water Resources Discharge & QA/QC Water Discharge: • • Requirement: 40mg/L suspended solids or less (20 NTU) • Actual: 2 NTU Average • Automated discharge and recirculation valves QA/QC • • Discharge based on inline turbidity analyzer • Regular laboratory verification April 15, 2014 | Slide 14 of 20

  15. Offloading Offload Barge • • 2 Excavators • Spill tray • Loader on dredgeate barge Challenges • • High moisture content • Thixotropic material Response • • Various amendments (wood pellets & cement) • Minimize agitation April 15, 2014 | Slide 15 of 20

  16. Offloading Off-Load Facility and Trucks Loading trucks • • 2 truck and pups at a time • Average of 110 trips per day Containment • • Sealed end gates • Hog fuel • Wheel wash • Regular monitoring • Storm water control berms April 15, 2014 | Slide 16 of 20

  17. Upland Transportation Route Planning Challenges • • Lane closure permits Craigflower Bridge closure • • (construction) Trucking routes • Lane closure restrictions • Community • Stakeholder management communications • Monitoring • April 15, 2014 | Slide 17 of 20

  18. Disposal Facility and Logistics Truck Traffic • • Long turnaround times • Scale congestion • Road cleaning Solution • • Dedicated scale (80% of daily traffic from EGD) • Expanded the receiving/ dumping area • Installed a wheel wash and manual cleaning area April 15, 2014 | Slide 18 of 20

  19. Residual Management Cover Placement Fraser River washed • sand, loaded onto barges and shipped to site Place sand layer • • 0.3m to 0.6m thick • 75,000m 2 foot print • With clamshell bucket on grid pattern • Utilized bucket positioning to track progress • Completed during January to early March (weather) April 15, 2014 | Slide 19 of 20

  20. Conclusion Esquimalt Graving Dock Waterlot Sediment Remediation Phase 1B Open-Water Dredging Project complete: • • Under budget • Ahead of schedule (aggressive) • Minimal impact to operations and tenants of the Esquimalt Graving Dock • Successful environmental cleanup Questions?? • Photo credits in this presentation to: Heath Moffatt Joe Pursley Tervita, FRPD and PWGSC staff April 15, 2014 | Slide 20 of 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend