Dock H Replacement Built in 1987 (32 years old) Pillar Point Marina - - PowerPoint PPT Presentation

Pillar Point Marina Dock H Replacement Built in 1987 (32 years old) Pillar Point Marina Dock H Replacement Project Status Contract Award May 2017 Board Presentation August 2017 Public Presentation January 2018 Public Presentation May


slide-1
SLIDE 1

Dock H Replacement

Pillar Point Marina Built in 1987 (32 years old)

slide-2
SLIDE 2

Project Status

Pillar Point Marina – Dock H Replacement

Contract Award May 2017 Board Presentation August 2017 Public Presentation January 2018 Public Presentation May 2018 65% Submitted Sept 2018 95% Submittal March 2019 Board Presentation March 2019 Combine with Johnson Pier Project? 100% Submittal TBD

slide-3
SLIDE 3

Proposed Layout

Pillar Point Marina – Dock H Replacement (35) 50-ft berths – 10 more than existing (12) 55-ft berths – 5 more than existing (15) 65-ft berths – 4 more than existing (2) end ties Proposed: 62 berths (plus 2 end ties) Existing: 45 berths (plus 2 end ties) (26) 50-ft berths (7) 55-ft berths (12) 65-ft berths (2) end ties

slide-4
SLIDE 4

Furnishings

Pillar Point Marina – Dock H Replacement Existing Guide Pile & Pedestal at Knee Braces

“Lighthouse” pedestal:

Electrical (metered) all slips: 30A/50A to each slip end tie #1: 30A/50A 50A/100A end tie #2: 30A/50A Water: Integrated hose bibbs (non-metered) hose bibb pedestal guide pile Rounded finger pier end

slide-5
SLIDE 5

Questions / Comments