Alviso Dock Feasibility Study Phase II: Follow-Up HOUSIN G, LAND - - PowerPoint PPT Presentation

alviso dock feasibility study phase ii follow up
SMART_READER_LITE
LIVE PREVIEW

Alviso Dock Feasibility Study Phase II: Follow-Up HOUSIN G, LAND - - PowerPoint PPT Presentation

Alviso Dock Feasibility Study Phase II: Follow-Up HOUSIN G, LAND USE, ENVIR ON MENT & TRANSPOR TATI ON (HLUET) COMMIT TE E COU NTY OF SA NTA CLARA NOVEMBER 15, 2018 1 Background Apr. 2015 Public asks County to Apr. 2017: Alviso Dock


slide-1
SLIDE 1

Alviso Dock Feasibility Study Phase II: Follow-Up

HOUSIN G, LAND USE, ENVIR ON MENT & TRANSPOR TATI ON (HLUET) COMMIT TE E

COU NTY OF SA NTA CLARA

NOVEMBER 15, 2018

1

slide-2
SLIDE 2

Background

  • Apr. 2015 Public asks County to

consider replacing dock at SBYC

  • Jun. 2016: Funding approved to

perform study

  • Apr. 2017: Alviso Dock Feasibility

Study Phase (I) presented at HLUET

Dredging is a core issue. HLUET requests additional study

  • 6.8ft. Mean Lower Low Water(MLLW)

Scenario presented costing $21M HLUET requests a lower cost analysis

  • Jun. 2018: Bathymetric Survey &

Report (Phase II)

  • Nov. 2018

County Parks presents

  • 4.0 MLLW Scenario at

HLUET

2

slide-3
SLIDE 3

Comparison of Dock Construction Costs

*Soft Costs include design, contingency, environmental and permits, engineering, etc.

3

slide-4
SLIDE 4

Comparison of Scenarios

4

slide-5
SLIDE 5

Comparison of -4 MLLW and -6.8MLLW Scenarios

Mean Lower Low Water (MLLW) The average height of low tide each

  • day. Measured twice a day, in the

morning and afternoon Draft The draft determines the minimum depth of water a boat can safely sail Dredge Zone Location of sediment needed to be removed above -4.0 and -6.8 Scenarios respectively

5

slide-6
SLIDE 6

Number of Days per Month where Accessis Impacted by Tides within AlvisoSlough

10% 7% 10% 100% 100% 82% 81% 90% 100% 93% 77% 81% 90% 100% 100% March February 18% January 19% June May April August 23% July 19% December November October September 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% % of Days Not Affected % of Days Affected

  • 4.0 MLLW SCENARIO
  • 6.8 MLLW SCENARIO

December 100% November 100% October 100% September 100% August 100% July 100% June 100% May 100% April 100% March 100% February 100% January 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% % of Days Not Affected % of Days Affected

6

100%

slide-7
SLIDE 7

Number of Mornings and Afternoons per Monthwhere Access is Impacted by Tides within AlvisoSlough

20% 10% 0% 30% 40% 50% 90% 80% 70% 60% % of Mornings Affected % of Afternoons Affected

  • 4.0 MLLW SCENARIO
  • 6.8 MLLW SCENARIO

ACCESS WILL NOT BE IMPACTED BY TIDES.

7

slide-8
SLIDE 8

Summary

8

  • If the proposed public dock were to be developed, dredging is recommended
  • Relative to the -6.8ft. MLLW scenario costs can be reduced by dredging to
  • 4.0ft. MLLW, but access is significantly impacted
  • Both scenarios involve high initial capital expenditure and significant ongoing

maintenance costs and staff time for permitting

slide-9
SLIDE 9

Questions

9