Alviso Dock Feasibility Study Phase II: Follow-Up
HOUSIN G, LAND USE, ENVIR ON MENT & TRANSPOR TATI ON (HLUET) COMMIT TE E
COU NTY OF SA NTA CLARA
NOVEMBER 15, 2018
1
Alviso Dock Feasibility Study Phase II: Follow-Up HOUSIN G, LAND - - PowerPoint PPT Presentation
Alviso Dock Feasibility Study Phase II: Follow-Up HOUSIN G, LAND USE, ENVIR ON MENT & TRANSPOR TATI ON (HLUET) COMMIT TE E COU NTY OF SA NTA CLARA NOVEMBER 15, 2018 1 Background Apr. 2015 Public asks County to Apr. 2017: Alviso Dock
HOUSIN G, LAND USE, ENVIR ON MENT & TRANSPOR TATI ON (HLUET) COMMIT TE E
COU NTY OF SA NTA CLARA
NOVEMBER 15, 2018
1
consider replacing dock at SBYC
perform study
Study Phase (I) presented at HLUET
Dredging is a core issue. HLUET requests additional study
Scenario presented costing $21M HLUET requests a lower cost analysis
Report (Phase II)
County Parks presents
HLUET
2
*Soft Costs include design, contingency, environmental and permits, engineering, etc.
3
4
Mean Lower Low Water (MLLW) The average height of low tide each
morning and afternoon Draft The draft determines the minimum depth of water a boat can safely sail Dredge Zone Location of sediment needed to be removed above -4.0 and -6.8 Scenarios respectively
5
10% 7% 10% 100% 100% 82% 81% 90% 100% 93% 77% 81% 90% 100% 100% March February 18% January 19% June May April August 23% July 19% December November October September 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% % of Days Not Affected % of Days Affected
December 100% November 100% October 100% September 100% August 100% July 100% June 100% May 100% April 100% March 100% February 100% January 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% % of Days Not Affected % of Days Affected
6
100%
20% 10% 0% 30% 40% 50% 90% 80% 70% 60% % of Mornings Affected % of Afternoons Affected
ACCESS WILL NOT BE IMPACTED BY TIDES.
7
8
maintenance costs and staff time for permitting
9