langdale dock langdale dock langdale dock langdale dock
play

Langdale Dock Langdale Dock Langdale Dock Langdale Dock - PowerPoint PPT Presentation

Langdale Dock Langdale Dock Langdale Dock Langdale Dock Alternative Approval Alternative Approval Alternative Approval Alternative Approval Process Process July 2011 July 2011 Background Background g Spring 2009 Spring 2009 - -


  1. Langdale Dock Langdale Dock Langdale Dock Langdale Dock Alternative Approval Alternative Approval Alternative Approval Alternative Approval Process Process July 2011 July 2011

  2. Background Background g  Spring 2009 Spring 2009 - - BC Ferries announces that private boats BC Ferries announces that private boats will no longer have access to the Langdale float due to will no longer have access to the Langdale float due to safety, security and liability issues. safety, security and liability issues.  March 14, 2009 March 14, 2009 - - Open house at the Gambier Open house at the Gambier C Community Hall with BC Ferries. Community Hall with BC Ferries. C it H ll it H ll ith BC F ith BC F i i  On March 31, 2009 On March 31, 2009 - - BC Ferries agrees to defer closure BC Ferries agrees to defer closure to October 2009 pending a review of options by the to October 2009 pending a review of options by the to October 2009 pending a review of options by the to October 2009 pending a review of options by the SCRD. SCRD.  April 20, 2009 April 20, 2009 – The inaugural meeting of the Langdale p The inaugural meeting of the Langdale g g g g g g Access Working Group (LAWG) is held. Access Working Group (LAWG) is held.  April 25, 2009 April 25, 2009 – – SCRD public meeting at the Gambier SCRD public meeting at the Gambier C C Community Hall to review options. Community Hall to review options. it H ll t it H ll t i i ti ti

  3. Options Options Options Options 1. Maintain Status Quo Maintain Status Quo Maintain Status Quo Maintain Status Quo 1 1. 1. Continue to provide access to the Stormaway float Continue to provide access to the Stormaway float 1. 2. Construct separate float for private boats Construct separate float for private boats p p p p 2. 2. New float north of Langdale terminal. New float north of Langdale terminal. 2. 1 Construct new float and walkway 1. Construct new float and walkway Construct new float and walkway Construct new float and walkway 1. 2. Use YMCA float (subject to agreement) Use YMCA float (subject to agreement) 2. 3. Use existing facilities Use existing facilities Use existing facilities Use existing facilities 3. 3 1. Hopkins Landing Hopkins Landing 1. 2. Gibsons Marina Gibsons Marina 2.

  4. Conclusions Conclusions 1. A A new float at a different location would be costly new float at a different location would be costly, , 1. involve involve a lengthy environmental process and would not a lengthy environmental process and would not likely address the needs of boaters and others. likely address the needs of boaters and others. likely address the needs of boaters and others likely address the needs of boaters and others 2. Hopkins Hopkins Landing Landing and and Gibsons Marina Gibsons Marina are not practical are not practical 2. options, and options, and in the case of Hopkins there is no adjacent options, and in the case of Hopkins there is no adjacent options, and in the case of Hopkins there is no adjacent in the case of Hopkins there is no adjacent parking and potential conflicts with swimmers. parking and potential conflicts with swimmers. 3. The impact of the closure of the Stormaway float The impact of the closure of the Stormaway float 3. would be lessened by expanding the Stormaway hours would be lessened by expanding the Stormaway hours of operation. of operation. 4. Options to retain access to the Stormaway float or 4 Options to retain access to the Storma a float or Options to retain access to the Stormaway float or Options to retain access to the Storma a float or 4. attached an alternative float are subject to the attached an alternative float are subject to the agreement of BC Ferries. agreement of BC Ferries. g 5. BC Ferries has committed to maintain 24 hour BC Ferries has committed to maintain 24 hour 5. emergency access to the Stormaway float. emergency access to the Stormaway float.

  5. Background cont. Background cont. g  May 7, 2009 May 7, 2009 – – staff submitted a report to the SCRD staff submitted a report to the SCRD Board summarizing options to address the issue of Board summarizing options to address the issue of Board summarizing options to address the issue of Board summarizing options to address the issue of access to the Langdale terminal. access to the Langdale terminal.  July 2009  July 2009 July 2009 July 2009 – SCRD staff, members of the LAWG and SCRD staff members of the LAWG and SCRD staff members of the LAWG and SCRD staff, members of the LAWG and other interested parties attempted to quantify the use of other interested parties attempted to quantify the use of the Stormaway dock in support of funding applications. the Stormaway dock in support of funding applications. y y pp pp g pp g pp  August 2009 August 2009 – – BC Ferries develops a possible option BC Ferries develops a possible option for a separate float near the existing Stormaway float. for a separate float near the existing Stormaway float. p p g g y y  September 2009 September 2009 – – staff report to the SCRD Board staff report to the SCRD Board concerning the option of a constructing a new float concerning the option of a constructing a new float near the Stormaway float. near the Stormaway float.

  6. Background cont. Background cont. g  September 2009 September 2009 – – staff make preparations to move staff make preparations to move forward with a feasibility study forward with a feasibility study forward with a feasibility study. forward with a feasibility study.  During 2009 and 2010 there were efforts to obtain During 2009 and 2010 there were efforts to obtain federal and provincial funding for a separate remote federal and provincial funding for a separate remote federal and provincial funding for a separate remote federal and provincial funding for a separate remote dock connected to the terminal parking lot. Funding dock connected to the terminal parking lot. Funding requests at the federal and provincial level were not requests at the federal and provincial level were not successful. successful.  November 2009 November 2009 – – SCRD, the LAWG and BC Ferries SCRD, the LAWG and BC Ferries begin the process of developing a license agreement begin the process of developing a license agreement that will govern the operation of the new dock. that will govern the operation of the new dock.

  7. Background cont. Background cont. g  January 2010 January 2010 – – the SCRD approves the draft agreement the SCRD approves the draft agreement and directs staff to move towards a final agreement. and directs staff to move towards a final agreement.  March 2010 March 2010 – – BC Ferries presents a new proposal BC Ferries presents a new proposal whereby they will construct and maintain a new dock whereby they will construct and maintain a new dock subject to a License Agreement with the SCRD. subject to a License Agreement with the SCRD.

  8. Proposed Float Proposed Float

  9. Background cont. Background cont. g  June 2010 June 2010 – – ongoing discussions with BC Ferries ongoing discussions with BC Ferries concerning liability and indemnity provisions in the concerning liability and indemnity provisions in the concerning liability and indemnity provisions in the concerning liability and indemnity provisions in the agreement. agreement.  April 5, 2011  April 5 2011 April 5 2011 April 5, 2011 – final meeting with BC Ferries on final meeting with BC Ferries on final meeting with BC Ferries on final meeting with BC Ferries on License Agreement. License Agreement.  April 28 2011  April 28, 2011 April 28 2011 – SCRD Board approves draft License April 28, 2011 SCRD Board approves draft License SCRD Board approves draft License SCRD Board approves draft License agreement and directs staff to undertake the Alternative agreement and directs staff to undertake the Alternative Approval Process (AAP). Approval Process (AAP). pp pp ( ( ) )

  10. License Agreement License Agreement g  Based on the lease between BC Ferries and the B.C. Based on the lease between BC Ferries and the B.C. Based on the lease between BC Ferries and the B.C. Based on the lease between BC Ferries and the B.C. Transportation Financing Authority. Transportation Financing Authority.  Term Term – 20 years + 10 year option. 20 years + 10 year option. y y y y p p  Fee Fee - - $35,000 per year + SCRD expenses for total $35,000 per year + SCRD expenses for total estimated cost of $40,280. estimated cost of $40,280.  BC Ferries retains control of the terminal including the BC Ferries retains control of the terminal including the new float. new float.  BC Ferries accepts all costs and liability. BC Ferries accepts all costs and liability.  Any operational issues will be referred to the SCRD’s Any operational issues will be referred to the SCRD’s y p y p Public Wharves Advisory Committee or other standing Public Wharves Advisory Committee or other standing committee. committee.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend