harbour green dock
play

HARBOUR GREEN DOCK Proposed Change of Use, Management & - PowerPoint PPT Presentation

HARBOUR GREEN DOCK Proposed Change of Use, Management & Maintenance Park Board Committee Meeting April 15, 2019 Purpose of Presentation T o provide an update to the Board on the history and current condition of Harbour Green Dock and


  1. HARBOUR GREEN DOCK Proposed Change of Use, Management & Maintenance Park Board Committee Meeting April 15, 2019

  2. Purpose of Presentation  T o provide an update to the Board on the history and current condition of Harbour Green Dock and issues that have contributed to its closure;  To present a proposal for the addition of limited commuter ferry services at the dock with the intent to transfer management and maintenance of the dock to Engineering Services;  To describe a public engagement plan;  To present an interim plan to address current safety concerns; and  To seek approval of a go-forward plan, starting with public engagement. 2

  3. Background 3

  4. Dock Development Overview  Contemplated through the ODP (1992) and rezoning (1996)  Intended to provide a waterside walkway and self-regulated transient moorage  Owned by the City on a designated road parcel (allocated for a floating walkway)  Maintained and managed by the Park Board following construction by local developer ▲ Marinas and water uses plan (Figure 6, Coal Harbour Official Development Plan, 1992) 4

  5. Construction, Inspection & Maintenance Timeline 2005 Sept 2017 Crew repairs Bracket repairs (based on inspection, within (had been an ongoing crew’s ability) issue since construction) 1992-2005 Coal Harbour Feb 2018 - Present Oct 2017 May 2016 Development Closure ENG Report Parks marine and (Marathon) (independent report, bridge inspection noted same issues, raised safety concerns) 2016 Feb 2018 Crew repairs Reassessment ($25k regular inspection 2002-2003 (further deterioration of & maintenance) Aug 2017 brackets, recommended Construction Detailed inspection closure) (stabilization issues (engineers found further noted during deterioration, identified construction) immediate repairs) 5

  6. Overview of Dock Components Gangway Pile bracket Pile Concrete float 6

  7. Current Dock Condition Pile Brackets Piles Floats Fixtures damaged/missing abrasion damage to the pile and blocking & UHMW rub pads the concrete float transition plates pile condition damaged and replaced failed anchor is unknown damaged railings with temporary brackets damaged cleats & failed rollers concrete damage loose caps bull rails caused by (added in 2005 as fix) improper moorage failed bracket 7

  8. Dock Design Issues  excessive movement Brackets have not performed as in all directions intended and repairs have been under normal wave conditions ineffective  No fender system was designed or berthing energy concentrated at installed to dissipate berthing energy piles  Vertical movement continues to be a no fenders problem (stabilizers may need repair)  Many vessels using dock exceed limited design vessel specified original design capacity (15,000 lbs & 35 ft) 8

  9. Environmental Challenges  Wave conditions are affected by high volume of harbour traffic  Location is not as protected as some other docks  Repair and restoration is subject to environmental regulations that change frequently  Located near busy seaplane and commercial shipping lane 9

  10. Previous Dock Usage Recreational Usage Ferry Operations   Unlike other Park Board facilities, Temporary ferry service was offered during Olympics to Bowen Island non-motorized vessels not allowed in Coal Harbour  Operators began to use dock without  Majority of users are recreational permit a few years later boaters  In 2017 services were shutdown, but caused concern with commuters in Other Uses Gibsons and Bowen Island  A variety of other vessels (many  exceeding dock capacity) have Limited operations continued until berthed at the dock closure in February 2018 10

  11. Design Vessel Exceedance Incidents 11

  12. Management & Enforcement Challenges Harbour Green Dock is unique in the region  No moorage fees or permits required  No dedicated enforcement staff  Has largest uninterrupted berthing face (2.5 times next largest dock)  Located in busy waterfront with variety of vessels and commercial operations having open and unregulated access  Never intended for the type of usage and vessels it has received 12

  13. Management & Repair Options 13

  14. Repair/Restoration Options  Extensive damage to mooring brackets, float transitions and some of the concrete floats  Cost to restore to prior condition is $350K+ (at least 12 months to complete)  Recommended to add fenders and redesign ▲ Proposed float mooring solution (hybrid mooring and replace all mooring brackets (at least chain and cushion roller fender bracket) $200K+ in addition to above amount)  Full rebuild may be required to accommodate larger vessels (order of magnitude cost of approximately $2M+)  Without regulation of vessels, future damage ▲ Proposed fender system along the berthing face is highly likely 14

  15. Physical Berthing Barriers/Restriction Options  Options to physically restrict usage to original design vessels explored by marine engineering consultant ▲ Option 1: Floats in a finger arrangement ▲ Option 2: Floating barrier  Option 3 (attaching camels) is the most feasible and would cost $650K + (in addition to the repair costs)  Implementation on hold due to high cost and need for engagement and decision for future dock use ▲ Option 3: Interrupted berthing face with floating removable camels 15

  16. Review of Management Models Models for transient moorage Review Results   All docks have a fee structure Previous attempts show location is based on duration of moorage, challenging to regulate length of vessel, type of use and  Moorage fees will not cover cost of season management, enforcement and  Enforcement varies: in all cases maintenance involve dedicated staff who  Revenues from limited ferry regularly patrol and vessel operations could subsidize registration schemes recreational usage and reduce  List of facilities review provided in regulation overhead Appendix C of Board Report 16

  17. Discussion 17

  18. Addition of Limited Commuter Ferry Service  Continue to provide recreational General Ferry Operation Parameters boating and pedestrian access (to be verified through stakeholder and public engagement)  Provide opportunity for alternate  Sailings during peak morning & mode of transport (Transportation afternoon hours (15-20 minute docking 2040) at each sailing)  Respond to concerns of municipal  30 to 60 ft. vessels transporting 10 to 60 passengers per sailing leaders of neighboring communities  Operators selected through an open  Upgrade and increase resilience of bidding process the dock with better safety features  Tour boats, tugs, and harbour cruise  vessels continue to be restricted from Accommodate larger emergency berthing vessels (VPD & VFRS) 18

  19. Public Engagement  Public engagement is recommended to gather feedback about the proposed change of use Engagement Objectives  Engagement process will be a joint  Confirm current usage for pedestrians effort with Engineering Services and recreational boating  Engagement activities targeted to  Gauge interest in limited commuter services start in the summer 2019 to coincide with boating season and will include  Seek input on operating model and online surveys, social media functional requirements outreach and on-site open house(s)  Report back to the Board is targeted for the fourth quarter of 2019 19

  20. Proposed Transfer to Engineering Services If dock will include limited ferry services:  Transfer management and Principle for Future Operation maintenance to Engineering  Maintain public access as a  Manage as part of Boating & pedestrian walkway Blueways portfolio (incl. 8 public  Ensure availability of public docks in False Creek) recreational boating   Allow limited use of the dock for Ensure better alignment with core ferry services mandate and expertise of Park Board  and Engineering Protect the dock through appropriate monitoring and enforcement  Negotiated transfer terms will be captured in MoU between Park Board and Engineering General Managers 20

  21. Process & Timeline  Limited ferry services may require ODP and zoning amendments  Design and construction require independent marine structural engineer  Construction is regulated by Port of Vancouver and Transport Canada and may be subject to environmental and transport review and permitting  Depending on usage, funding must also be allocated for the repairs, upgrades, management, and operation 21

  22. Interim Removal and Storage  Eliminates risk and liability from continued unauthorized access  Prevents further damage to dock due to pre-existing damage and site wave conditions  Allows public engagement before further investment in the dock  Can be completed at minimal cost within month of approval  Gangways and concrete floats will be dismantled and transported offsite for storage 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend