webex etiq iquette guidelines
play

Webex Etiq iquette Guidelines Participants will be muted upon - PowerPoint PPT Presentation

Webex Etiq iquette Guidelines Participants will be muted upon entering the Webex meeting If you have a question you can press *6 on your telephone and you will be unmuted After your question has been addressed press *6 again to re-


  1. Webex Etiq iquette Guidelines • Participants will be muted upon entering the Webex meeting • If you have a question you can press *6 on your telephone and you will be unmuted • After your question has been addressed press *6 again to re- mute your line • It is encouraged to wait for a “Question” slide to ask questions, but if a question or need for clarification is urgent then they may be asked at any time • Thank you for helping us provide an accessible presentation for all attendees Intertie & Parker-Davis Project Draft 10-Year Plan 1

  2. Intertie & Parker-Davis Project Draft 10-Year Plan July 29, 2020 Desert Southwest Region Phoenix, AZ

  3. Agenda • Welcome • Delayed Execution • Draft 10-Year Plan • Seed Project Update • Analysis of Alternatives Studies • Rate Impact • Capital O&M Update • Next Steps Intertie & Parker-Davis Project Draft 10-Year Plan 3

  4. Dela layed Executio ion • DSW is currently addressing the impacts of COVID-19 regarding active construction and capital planning • As a risk mitigation measure, DSW is exploring options for optimizing fiscal year execution by re-evaluating project priorities • This may include shifting future projects from 3+ years out into the budget formulation window • The overall objective is to match funding forecasts outlined in previous year’s budget formulations • As the full impacts and expected timeline of COVID-19 becomes clearer, these strategies will be refined and updated • The 10-Year Plan is retaining its original sequence of project priorities as much as feasible for project continuity Intertie & Parker-Davis Project Draft 10-Year Plan 4

  5. Draft 10-Year Pla lan Intertie & Parker-Davis Project Draft 10-Year Plan 5

  6. Estim imate Accuracy Explanation As a reminder, the 10-Year Plan is color coded for the following criteria • Yellow – Project Request Phase – Pre-Conceptual Design • Red – AOA Study Phase – Conceptual Design • Green – Seed Funded Phase – Preliminary Design • Blue – Active Construction Phase – Final Design, Construction and Closeout Intertie & Parker-Davis Project Draft 10-Year Plan 6

  7. Fin inal 10-Year Pla lan October 2019 PARKER-DAVIS PROJECT FINAL 10-YEAR PLAN PROJECTED PROJECT NAME FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 TOTAL Gila-Wellton Mohawk I-8 Crossing Rebuild $ 7,623 $ 40 Gila Substation 161-kV Rebuild $ 23,873 $ 3,100 $ 25 Dome Tap-Gila 161-kV Rebuild $ 5,630 $ 2,966 $ 50 Coolidge-Valley Farms 115-kV Rebuild $ 2,543 $ 932 $ 25 Crossman Peak Microwave Facility $ 4,525 $ 170 $ 2,534 $ 333 Kofa-Dome Tap 161-kV Rebuild $ 5,138 $ 4,634 $ 130 $ 50 Bouse-Kofa 161-kV Rebuild $ 26,520 $ 614 $ 21,095 $ 2,556 $ 1,800 $ 40 Bouse Upgrade Project $ 45,916 $ 1,208 $ 704 $ 9,658 $ 11,493 $ 12,925 $ 7,950 $ 537 Parker-Blythe 161-kV #2 Rebuild Phase-1 $ 18,542 $ 250 $ 237 $ 17,086 $ 805 $ 164 Parker-Blythe 161-kV #2 Rebuild Phase-2 $ 18,542 $ 237 $ 17,336 $ 805 $ 164 Parker-Blythe 161-kV #2 Rebuild Phase-3 $ 18,542 $ 237 $ 17,336 $ 805 $ 164 Parker Substation 161-kV Replacements $ 16,850 $ 300 $ 100 $ 100 $ 8,000 $ 7,700 Blythe-Headgate Rock #1 161-kV Rebuild $ 23,900 $ 1,195 $ 100 $ 100 $ 9,560 $ 11,711 Parker Substation 230-kV Replacements $ 12,100 $ 600 $ 100 $ 100 $ 2,000 Gila Substation 69-kV Rebuild $ 10,500 $ 800 $ 100 $ 100 Gila-Knob 161-kV Remaining Rebuild $ 23,000 $ 800 $ 100 Gila Substation 34.5-kV & 14-kV Rebuild $ 15,250 $ 500 Final 10-Year Plan (2019) FY Totals $ 278,995 $ 13,664 $ 24,813 $ 13,308 $ 30,379 $ 31,106 $ 27,750 $ 2,306 $ 1,264 $ 18,560 $ 22,111 INTERTIE PROJECT FINAL 10-YEAR PLAN PROJECTED PROJECT FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 TOTAL Liberty Series Capacitor Bank Replacement $ 9,835 $ 1,598 $ 25 Final 10-Year Plan (2019) FY Totals $ 1,598 $ 25 Intertie & Parker-Davis Project Draft 10-Year Plan 7

  8. Project Manager: R Roger Wrig ight Projects Coolidge Valley Farms Liberty Capacitor Bank Contact Info Wright@WAPA.gov (602) 605-2498 Intertie & Parker-Davis Project Draft 10-Year Plan 8

  9. Coolidge-Valley Farms 115-kV Rebuild 2019 Final 10-Year Plan PROJECTED FY20 FY21 TOTAL $ 2,543 $ 932 $ 25 2020 Draft 10-Year Plan PROJECTED FY20 FY21 TOTAL $ 2,543 $ 932 $ 25 Previous Status • Structure and conductor replacement had begun with an expected energization date of 2020 Current Status • The line was energized 4/13/2020 • No changes to project budget Intertie & Parker-Davis Project Draft 10-Year Plan 9

  10. Liberty Series Capacitor Bank Replacement 2019 Final 10-Year Plan PROJECTED FY20 FY21 TOTAL $ 9,835 $ 1,598 $ 25 2020 Draft 10-Year Plan PROJECTED FY20 FY21 TOTAL $ 9,835 $ 1,598 $ 25 Previous Status • Remaining punch-list items were forecast to be completed by March 2020 Current Status • The punch-list has been completed and the project is in financial close-out • No changes to project budget Intertie & Parker-Davis Project Draft 10-Year Plan 10

  11. Project Manager: Tony Gagajewski Projects Gila-Wellton I-8 Crossing Gila Substation 161-kV Bouse-Kof 161-kV Rebuild Dome Tap-Gila 161-kV Rebuild Kofa-Dome Tap 161-kV Rebuild Seed: Bouse Upgrade Contact Info Gagajewski@WAPA.gov (602) 605-2629 Intertie & Parker-Davis Project Draft 10-Year Plan 11

  12. Gil ila-Wellt lton Mohawk I-8 Crossing Rebuil ild 2019 Final 10-Year Plan PROJECTED FY20 TOTAL $ 7,623 $ 40 2020 Draft 10-Year Plan PROJECTED FY20 TOTAL $ 7,623 $ 40 Previous Status • Project is in financial closeout Current Status • Project will closeout successfully in FY20 and will be removed from the 10-Year Plan in October 2020 • No changes to project budget Intertie & Parker-Davis Project Draft 10-Year Plan 12

  13. Gil ila Substatio ion 161-kV Rebuild 2019 Final 10-Year Plan PROJECTED FY20 FY21 TOTAL $ 23,873 $ 3,100 $ 25 2020 Draft 10-Year Plan PROJECTED FY20 FY21 FY22 TOTAL $ 25,070 $ 2,565 $ 1,655 $ 102 Previous Status • Prepayment funding reallocation to complete project voted on successfully in December 2019 • Remaining construction was slated to continue through July 2020 Current Status • Due to delays caused by COVID-19, the project has been extended by one year • Project budget has increased by $1.19M due to required demobilization and holding through the summer of 2020 Intertie & Parker-Davis Project Draft 10-Year Plan 13

  14. Bouse-Kofa 161 161-kV Rebuild 2019 Final 10-Year Plan PROJECTED FY20 FY21 FY22 FY23 FY24 TOTAL $ 26,520 $ 614 $ 21,095 $ 2,556 $ 1,800 $ 40 2020 Draft 10-Year Plan PROJECTED FY20 FY21 FY22 FY23 FY24 FY25 TOTAL $ 26,520 $ 614 $ 113 $ 21,502 $ 1,919 $ 1,937 $ 20 Previous Status • Design was approaching 50% completion • Lands and environmental work was beginning Current Status • Design has reached 50% and is working toward 75% • Due to delays caused by COVID-19, this project has been extended by one year • No changes to total project budget Intertie & Parker-Davis Project Draft 10-Year Plan 14

  15. Dome Tap-Gila 161-kV Rebuild 2019 Final 10-Year Plan PROJECTED FY20 FY21 TOTAL $ 5,630 $ 2,966 $ 50 2020 Draft 10-Year Plan PROJECTED FY20 FY21 FY22 TOTAL $ 5,630 $ 1,074 $ 1,840 $ 102 Previous Status • Construction began in October 2019 with a projected energization date of 2020 Current Status • Due to delays caused by COVID-19, this project has been adjusted to include an additional fiscal year • No changes to total project budget Intertie & Parker-Davis Project Draft 10-Year Plan 15

  16. Kofa-Dome Tap 161-kV Rebuild 2019 Final 10-Year Plan PROJECTED FY20 FY21 FY22 TOTAL $ 5,138 $ 4,634 $ 130 $ 50 2020 Draft 10-Year Plan PROJECTED FY20 FY21 FY22 FY23 FY24 TOTAL $ 5,138 $ 1,850 $ 1,200 $ 1,064 $ 650 $ 50 Previous Status • The construction contract for this project was awarded February 2020 and all government furnished equipment was anticipated to be received October 2020 Current Status • Due to delays caused by COVID-19, this project has been adjusted to include an additional two years • No changes to total project budget Intertie & Parker-Davis Project Draft 10-Year Plan 16

  17. Questions? Intertie & Parker-Davis Project Draft 10-Year Plan 17

  18. Seed Project Update

  19. Bouse Upgrade Alt lternative His istory ry • Parker-Bouse and Parker- Headgate transmission lines require replacement • The original replacement project was placed on hold and a new alternative path was studied and shared with stakeholders • The alternative path entered a seed funding phase, in which appropriations are used for preliminary design work • The work on the seed funded design continues, to ensure there are no show stoppers to the full construction of the project prior to request for a vote Intertie & Parker-Davis Project Draft 10-Year Plan 19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend