Real Property Institute of Canada 2014 RPIC Federal Contaminated - - PowerPoint PPT Presentation

real property institute of canada
SMART_READER_LITE
LIVE PREVIEW

Real Property Institute of Canada 2014 RPIC Federal Contaminated - - PowerPoint PPT Presentation

Real Property Institute of Canada 2014 RPIC Federal Contaminated Sites National Workshop April 2014 2 / 34 Esquimalt Graving Dock Waterlot Remediation Project (Phase 1B) Environmental Management Plan (EMP) Implementation Stream H:


slide-1
SLIDE 1

Real Property Institute of Canada

2014 RPIC Federal Contaminated Sites National Workshop

April 2014

slide-2
SLIDE 2

Esquimalt Graving Dock Waterlot Remediation Project (Phase 1B)

Environmental Management Plan (EMP) Implementation

Stream H: Contaminated Sites Management for Aquatic Environments and Sediment

Presenter: David McKeown (SLR Consulting) Collaborators: Rae Ann Sharp, Kristen Ritchot, David Osguthorpe (PWGSC)

2 / 34

slide-3
SLIDE 3

Project Background

  • The EGD is a federally owned, operated and maintained

facility.

  • Ship repair and maintenance facility for military and

civilian vessels since 1927.

  • Industrial activities at the EGD have resulted in

contamination of the surrounding sediments.

  • PWGSC managed the remediation project through

FCSAP funding.

  • The Waterlot Remediation Program aimed to clean up

the site to meet federal and provincial environmental standards.

3 / 34

slide-4
SLIDE 4

Project Background (Cont’d)

  • Primary CoCs in sediment included metals, PAH, and

PCB.

  • Other contaminants included TBT, dioxins/furans, and

select pesticides.

  • Contaminant levels identified as IL+ for disposal

considerations.

  • Contaminated sediments were removed through

remedial dredging and off-site disposal.

  • Environmental monitoring during all in-water activities

carried out to ensure environmental protection goals were met during the large-scale remediation project.

4 / 34

slide-5
SLIDE 5

Project Location

Esquimalt Graving Dock

5 / 34

slide-6
SLIDE 6

Project ¡Boundary ¡ 6 / 34

slide-7
SLIDE 7

Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡

7 / 34

slide-8
SLIDE 8

Environmental Management Implementation Plan (EMIP)

Objectives:

  • Provide EMs with necessary information

to conduct all aspects of monitoring work throughout program.

  • EMIP prepared as a field manual for on-

site guidance.

  • The EMIP provides procedures to

conduct the environmental monitoring in accordance with the EMP, Project Specifications, BMPs, Fisheries Authorization, and overall environmental protection goals.

8 / 34

slide-9
SLIDE 9

Monitoring Components

q Water Quality

q Underwater Noise q Ambient Noise q Artificial Light q Air Quality q Aquatic Mammals q Fish Aggregations & Spawning q Environmental Awareness Training q Offloading/Transfer Facility q Non-Hazardous Waste Management q Spill Prevention & Emergency Response q Hazardous Material Management & Storage q Imported Sand & Backfill Material q Conformance with EGD BMPs, Specs, EPP q Water Treatment Barge water sampling q Review of analytical data for imported materials

9 / 34

slide-10
SLIDE 10

Planning, Logistics & Preparation

  • EMP & WQMP prepared by Golder

Associates Ltd.

  • Development of site-specific limits

– Predictive modeling based on sediment chemistry and dispersion modeling – Pre-field assessment (TSS/turbidity relationship)

  • Fisheries Act Authorization

– EMP and WQMP details rolled in to Authorization

  • Laboratory coordination (SOR)
  • Training & Health and Safety
  • Integration of First Nations Staff
  • Equipment
  • Test Dredge Process

10 / 34

slide-11
SLIDE 11

Field Implementation

  • Regular monitoring of Turbidity,

pH and DO readings were recorded at four monitoring locations and two background reference points at multiple water depths for each derrick (twice daily).

  • Use of real-time on-site

management limits that correlate to anticipated and field-validated COC concentrations.

– Use of management action flow chart to determine when, where and what type of actions could be implemented during non-compliance events.

Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡

11 / 34

slide-12
SLIDE 12

Water Sampling Locations

In-Situ WQ Compliance Monitoring

1 ¡m below ¡surface 2 m above ¡seabed mid ¡water ¡column Compliance ¡ Point Decisions ¡Based ¡On Measurements ¡From:

Adapted ¡from ¡Golder ¡Associates ¡Ltd. ¡

Management ¡Limits ¡set ¡for ¡ AP ¡and ¡CP ¡Loca@ons ¡and ¡ WQMAs: ¡ Assessment ¡Point ¡(100 ¡m) ¡ <8 ¡NTU ¡above ¡Background ¡ ¡ (All ¡WQMAs) ¡ Compliance ¡Point ¡(25 ¡m) ¡ <20 ¡NTU ¡above ¡Background ¡ (WQMA-­‑A ¡& ¡B) ¡ <25 ¡NTU ¡above ¡Background ¡ (WQMA-­‑C)

12 / 34

slide-13
SLIDE 13

Water Quality Management Areas

In-Situ WQ Compliance Monitoring

Compliance ¡Point ¡WQ ¡Limits ¡for ¡ each ¡WQMA ¡based ¡on ¡exis@ng ¡ sediment ¡contaminant ¡ concentra@ons ¡and ¡predic@ve ¡ modeling ¡of ¡suspended ¡sediment ¡ loads ¡during ¡dredging

WQMA-­‑A ¡ WQMA-­‑B ¡ WQMA-­‑C

SOUTH JETTY

13 / 34

slide-14
SLIDE 14

Water Sampling Locations

In-Situ WQ Compliance Monitoring

Adapted ¡from ¡Golder ¡Associates ¡Ltd. ¡

14 / 34

slide-15
SLIDE 15

In-Situ WQ Compliance Monitoring

Regular ¡monitoring ¡at ¡Background ¡(2) ¡and ¡Assessment ¡Point ¡(3) ¡ Loca@ons ¡– ¡3 ¡depths ¡at ¡each ¡loca@on Induced ¡Turbidity ¡at ¡AP ¡* >20 ¡NTU ¡above ¡ Background ¡levels >8 ¡and ¡<20 ¡NTU ¡above ¡ Background ¡levels <8 ¡NTU ¡above ¡ Background ¡levels

STEP ¡1

Go ¡To ¡Step ¡2 Con@nue ¡Dredging

* ¡Monitoring ¡also ¡ conducted ¡at ¡CP ¡(3 ¡ depths) ¡to ¡verify ¡levels ¡ were ¡within ¡site-­‑specific ¡ compliance ¡limits.

15 / 34

slide-16
SLIDE 16

No@fy ¡PWGSC ¡PCO ¡of ¡exceedance ¡– ¡ State ¡that ¡confirmatory ¡ measurements ¡will ¡be ¡taken. ¡ ¡ Confirmatory ¡turbidity ¡measurements ¡ taken ¡a_er ¡30 ¡minutes ¡at ¡3 ¡loca@ons ¡ along ¡the ¡AP ¡and ¡at ¡CP, ¡at ¡3 ¡depths.

In-Situ WQ Compliance Monitoring

STEP ¡2

>20 ¡NTU ¡above ¡ Background ¡levels >8 ¡and ¡<20 ¡NTU ¡above ¡ Background ¡levels <8 ¡NTU ¡above ¡ Background ¡levels Con@nue ¡Dredging Go ¡To ¡Step ¡3

16 / 34

slide-17
SLIDE 17

No@fy ¡PWGSC ¡PCO ¡of ¡exceedance. ¡ ¡ Implement ¡Management ¡Ac<ons ¡ State ¡that ¡Background ¡condi@ons ¡ will ¡be ¡re-­‑assessed. ¡ ¡ Re-­‑Assess ¡Background ¡levels ¡and ¡check ¡ for ¡other ¡poten@al ¡sources ¡of ¡induced ¡ turbidity ¡(e.g., ¡vessel ¡traffic, ¡ouballs, ¡etc). ¡ Reassess ¡CP ¡and ¡AP ¡levels ¡based ¡on ¡any ¡ changes ¡to ¡Background ¡condi@ons. ¡

In-Situ WQ Compliance Monitoring

STEP ¡3

>20 ¡NTU ¡above ¡ Background ¡levels >8 ¡and ¡<20 ¡NTU ¡above ¡ Background ¡levels <8 ¡NTU ¡above ¡ Background ¡levels Con@nue ¡Dredging Go ¡To ¡Step ¡4

17 / 34

slide-18
SLIDE 18

No@fy ¡PWGSC ¡PCO ¡of ¡exceedance. ¡ ¡ Implement ¡Management ¡Ac<ons. Confirmatory ¡turbidity ¡measurements ¡ taken ¡at ¡3 ¡loca@ons ¡along ¡the ¡AP ¡and ¡at ¡2 ¡ loca@ons ¡at ¡the ¡CP, ¡all ¡at ¡3 ¡depths. ¡

In-Situ WQ Compliance Monitoring

STEP ¡4

>20 ¡NTU ¡above ¡ Background ¡levels >8 ¡and ¡<20 ¡NTU ¡above ¡ Background ¡levels <8 ¡NTU ¡above ¡ Background ¡levels Con@nue ¡Dredging Go ¡To ¡Step ¡5

18 / 34

slide-19
SLIDE 19

No@fy ¡PWGSC ¡PCO ¡of ¡exceedance. ¡ ¡ STOP ¡DREDGING ¡

In-Situ WQ Compliance Monitoring

STEP ¡5

IMPLEMENT ¡ CORRECTIVE ¡ACTIONS RESUME ¡DREDGING ¡ AND ¡REASSESS Go ¡To ¡Step ¡1

19 / 34

slide-20
SLIDE 20

Communication and Notifications

20 / 34

slide-21
SLIDE 21

Management Actions

Operational Controls:

  • Reduce dredging rate (descent and ascent)
  • Use the environmental dredge bucket
  • Do not take multiple dredge bucket bites
  • Limit over-filling of dredge bucket
  • Reduce or stop dredging during peak currents
  • Prevent lateral movement of submerged dredge bucket
  • Speed up movement of dredge bucket from water to barge
  • Hold full dredge bucket at the water surface to allow water to drain before the

bucket is swung onto the barge

  • Use rinse tank to clean bucket
  • Use an absorbent boom (if sheen noted on water)

Engineering Controls:

  • Confirm that the silt curtain is not damaged and is deployed for maximum

effectiveness

21 / 34

slide-22
SLIDE 22
  • Water quality samples were

collected in each dredging zone and assessed for COCs.

– Further validation of predicted WQ levels confirmed.

  • Laboratory samples collected

concurrently with in-situ monitoring activities.

  • Submitted for select parameters of

concern:

– TSS; – Total metals; – Dissolved metals; – Total PAH; – Dissolved PAH; and – PCB (select areas only).

Field Implementation

Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡

22 / 34

slide-23
SLIDE 23
  • Samples collected once per day for

each derrick.

  • Sample frequency and laboratory turn-

around-time reduced over time for each activity pending water quality results.

– TSS analyzed at each location and depth. – T&D metals, PAH analyzed at 50% of all sampling points. – PCBs analyzed at select locations only.

  • Composite soil samples for

assessment of imported RMC material conducted for each barge load.

Field Implementation

23 / 34

slide-24
SLIDE 24

Laboratory Coordination & Sample Submissions

  • Daily sample pick-up/supply delivery

arranged through analytical laboratory.

  • Chartered air shipment for 24-hour

TAT samples.

  • Process changes throughout program

included: – Inclusion of PCB samples in select areas; – Reduction in dissolved PAH samples; – Addition of spot-check samples.

24 / 34

slide-25
SLIDE 25
  • Six permanent turbidity loggers

monitored for correlation of regional increases in turbidity.

  • Compliance monitoring for:

– Marine mammal and fish aggregation monitoring; – Waste management and spill control; – Dust management; – Ambient noise level; – Inspection of materials off-load facility; – Hydrophone monitoring of underwater noise during pile driving.

Field Implementation

25 / 34

slide-26
SLIDE 26

Data Management

  • Dedicated web-based Environmental

Management Tool (EMT) developed to provide accessible and up-to-date data repository.

  • Remote access for project personnel.
  • Laboratory and in-situ results loaded

to the EMT.

  • Data manager included on project to

provide QA/QC review and management.

  • Turbidity / TSS relationship reviewed

to ensure applicability of on-site limits.

Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡

26 / 34

slide-27
SLIDE 27

27 / 34

slide-28
SLIDE 28

28 / 34

slide-29
SLIDE 29

Results

  • In-situ monitoring results generally within compliance levels at

Compliance and Assessment Points for 90%+ sampling rounds during dredging.

– Exceedances were primarily very limited spatially and temporally

  • Silt curtain performance was very good and controlled siltation

within the receiving environment.

  • TSS/turbidity relationship was initially difficult to verify due to low

levels of TSS in first months of sampling.

– Addition of spot-check samples improved this assessment. – TSS / turbidity relationship was determined to be conservative and provided adequate environmental protection throughout the project.

  • Total copper periodically elevated above the ambient WQG at

both reference and down-current sampling locations.

– Due to elevated background levels within Esquimalt Harbour when not correlated to increased TSS.

29 / 34

slide-30
SLIDE 30
  • Backfill material placement

– Turbidity (and associated TSS) results were typically highest for this activity as silt curtains were not specifically required. – Despite analytically ‘clean’ material, presence of fines in backfill created higher TSS/turbidity levels for which management actions were required.

  • Residual Management Cover Placement

– Initial rounds of turbidity monitoring and water sampling indicated elevated levels as contractor determined best placement method. – Near surface placement determined to provide best results for coverage and water quality. – Turbidity and laboratory parameters within compliance following these adjustments.

Results

30 / 34

slide-31
SLIDE 31

Results

  • Underwater noise

– All levels within compliance levels. – Majority of installations used vibratory hammers and wooden piles to aid in maintaining compliance.

  • Ambient noise

– Infrequent night-time work required throughout project. – Levels were within compliance with municipal noise control bylaws.

  • Fish aggregations

– Work occurred outside of herring spawning periods. – Fish aggregations observed near project activities but no instances of distress were observed.

  • Marine mammals

– Pinnipeds were abundant during project activities but generally outside of defined safety perimeter. – No cetaceans observed during project activities.

31 / 34

slide-32
SLIDE 32

Lessons Learned

  • Logistical considerations and staffing requirements/re-scheduling

were difficult and required appropriate budgeting and time allocation for proper project planning.

  • Clear understanding of current fluctuations, particularly around

structures to determine turbidity plume dynamics and site-specific variations.

  • Projected laboratory sample frequency was inaccurate due to WQ

assumptions at project start up that were never realized.

– Impacts to contractual details with analytical laboratory.

  • Volume of monitoring and laboratory data during 10-month program

was extensive.

– Appropriate allocation of personnel, time and budget are required to effectively manage these items. – Application of the EMT provided opportunity for quick response and review of data throughout program.

32 / 34

slide-33
SLIDE 33
  • EMIP needs to be a working and evolving document / guidance

tool in order to accommodate unforeseen circumstances and changes to pre-project assumptions.

– Scheduled updates over the course of the project should be included to provide feedback loops and ensure all project components are effectively addressed.

  • Maintaining a good working relationship between client, EM staff

and project managers, design team, and contractor personnel is essential.

– Collaborative approach to decision making; – Effective lines of communication; – Mutual respect and courtesy amongst all project team members will aid in addressing project-related issues when they arise.

33 / 34

slide-34
SLIDE 34

Special Thanks to:

  • Rae Ann Sharp (PWGSC)
  • Andrew Mylly (PWGSC)
  • Kristen Ritchot (PWGSC)
  • David Osguthorpe (PWGSC)
  • Chris Major (PWGSC)
  • Jeff Nyman (SLR)
  • Cheryl Nyman (SLR)
  • Heather Grant (SLR)
  • Ricki Sahota (SLR)
  • Drew Rice (SLR)
  • Hailey O’Neill (SLR)
  • Ben McKinnon (SLR)
  • David Grafton (SLR)
  • Ingrid Sorensen (SLR)
  • Vanya Jongkind (SLR)
  • David Pugh (SLR)
  • Aaron Haegele (SLR)
  • Marci Martin (SLR)
  • Richard Plourde (SLR)
  • Chris Koziey (SLR)
  • Matt Woltman (Anchor QEA)
  • Dan Berlin (Anchor QEA)
  • Tom Wang (Anchor QEA)
  • Bud Whitaker (Anchor QEA)
  • Joe Persley (Anchor QEA)
  • Geoff Cooper (KCB)
  • Tervita
  • FRPD

34 / 34