Real Property Institute of Canada
2014 RPIC Federal Contaminated Sites National Workshop
April 2014
Real Property Institute of Canada 2014 RPIC Federal Contaminated - - PowerPoint PPT Presentation
Real Property Institute of Canada 2014 RPIC Federal Contaminated Sites National Workshop April 2014 2 / 37 Esquimalt Graving Dock Waterlot Remediation Project (Phase 1B) Confirmatory Sampling, Analysis and Evaluation Plan (CSAEP)
April 2014
Stream H: Contaminated Sites Management for Aquatic Environments and Sediment
Presenter: David McKeown (SLR Consulting)
Collaborators: Jeff Nyman (SLR), Andrew Mylly (PWGSC), Rae Ann Sharp (PWGSC), Tom Wang (Anchor QEA), Dan Berlin (Anchor QEA), Matt Woltman (Anchor QEA)
2 / 37
3 / 37
4 / 37
Esquimalt Graving Dock
5 / 37
Project ¡Boundary ¡ 6 / 37
Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡
7 / 37
8 / 37
based on pre-dredge contaminant profiles.
– Zone 10 further broken into sub-zones
dredging activities using a 25 x 25 m grid spacing.
accuracy GPS
location with concurrent surface grab samples (petite ponar).
intertidal area of Munroe Head.
Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡
9 / 37
10 / 37
– Cores were sampled at 0.5 m intervals to identify missed inventory contamination. – Surface grab samples were used to identify dredge residual contamination.
– Not included in re-dredge decisions due to geotechnical considerations.
11 / 37
– Based on most stringent and previously accepted applicable marine environmental quality guidelines, including:
assessment (Golder)
– Metals – PAH – PCB – Dioxins & Furans – TBT – Select Pesticides
12 / 37
– Minimum recovery targets established for acceptance of cores.
13 / 37
– Upper 1.0 m samples submitted for analysis. – Remaining samples archived.
14 / 37
Concurrent grab samples collected using petite ponar sampler. Diver assisted grabs/cores collected where vibracoring was not possible (e.g., dry dock sill area, hard substrate areas).
15 / 37
Munroe Head intertidal area (Zone 9) sampled by test- pitting during low tides. All grab, core, test pit samples homogenized to be representative.
16 / 37
– Required detection limits to meet NRAO levels. – Turn-around-times for specific parameters. – Detailed schedule for samples and analysis requirements on a daily, weekly and monthly basis. – Communication requirements. – Data management and QA/QC requirements.
17 / 37
Management Tool (EMT) developed to provide accessible and up to date data repository.
automatically to the EMT.
provide QA/QC review, data tabulation and management, and statistical analysis.
NRAOs
18 / 37
19 / 37
– Overall dredge zone compliance with NRAOs based on statistical approach (surface samples only). – Single point compliance assessment.
– Considered eventual mixing of upper sediment layers (up to 10 cm) with placed RMC layer (30 cm)
20 / 37
– These parameters were drivers in most zones and other contaminants (i.e., pesticides, TBT, dioxins/furans) were generally shown to co-locate. – Pesticides, TBT, dioxins/furans analyzed on a 7-day TAT. – Where other parameters were drivers within a zone, results were re- assessed once they became available. – Modifications to the re-dredge decision were then provided to the contractor.
– Re-dredge decisions formally relayed to contractor through PWGSC.
21 / 37 21 / 37
– Residuals assessment only.
Photo ¡courtesy ¡of ¡Heath ¡Moffa5 ¡
22 / 37
ZONE DREDGING COMPLETED CONFIRMATORY SAMPLING
(Vibracore and Surface Sampling)
SURFACE SAMPLING
(0 – 0.1 m)
Analytical Data Receipt, Tabulation and Review
Lab analysis (3-7 working days)
CORE SAMPLING
(0 – 2.0 m with min 75% recovery) Composite samples to lab (0-0.5 m and 0.5-1.0 m) Archive Samples below 1.0 m (in 0.5 m intervals)
23 / 37
(based on surface samples only) Method 1 – Single Sample Assessment Method 2 – Statistical Approach
Are the surface sample concentrations less than NRAO? Are there any surface sample concentrations >4X NRAO? Is the 90th Percentile or 95% UCLM surface sample concentrations below NRAO? Is the 90th Percentile or 95% UCLM surface sample concentrations below NRAO? If No, RMC thickness to be evaluated based on in-situ concentrations RESIDUAL RE- DREDGE (0-0.3 m) PLACE RMC RESIDUAL RE- DREDGE (0-0.3 m)
YES ¡ NO ¡ YES ¡ NO: ¡<4X ¡NRAO ¡ NO: ¡>4X ¡NRAO ¡ YES ¡ If ¡<NRAO ¡ If ¡<4X ¡NRAO ¡ 2nd Round Surface Sampling 2nd Round Surface Sampling YES ¡ NO: ¡<4X ¡NRAO ¡
NO FURTHER ACTION REQUIRED
24 / 37
(based on sediment cores)
Is the core sample concentration below NRAO? Is the confirmatory surface sample concentration below the NRAO? MISSED INVENTORY RE-DREDGE (0.5-0.8 m) NO FURTHER ACTION REQUIRED PROCEED TO COMPLIANCE UNIT ASSESSMENT METHOD
2nd Round Surface Sampling NO ¡ YES ¡ YES ¡ NO ¡ 25 / 37
<NRAO ¡ 1-‑4 ¡X ¡NRAO ¡ >4X ¡NRAO ¡
26 / 37
<NRAO ¡ 1-‑4 ¡X ¡NRAO ¡ >4X ¡NRAO ¡
27 / 37
28 / 37
Z 3
2
29 / 37
<NRAO ¡ 1-‑4 ¡X ¡NRAO ¡ >4X ¡NRAO ¡
30 / 37
31 / 37
– Combined with RMC thickness assessment
32 / 37
10 cm
33 / 37
<NRAO ¡ 1-‑4 ¡X ¡NRAO ¡ >4X ¡NRAO ¡
34 / 37
<NRAO ¡
35 / 37
difficult and required appropriate budgeting and time allocation for proper planning.
– Diver cores required in some locations. – Very hard substrate areas only allowed for diver grabs. – Program modified in select areas to conduct diver video surveys to document residual sediment layer thickness to re-adjust post-mixing assumptions where further re-dredging was not feasible or effective.
– Adjustments were needed in coring technique to provide adequate recovery.
to contractor.
36 / 37
Special Thanks to:
37 / 37