canadian p3 rail experience
play

Canadian P3 Rail Experience August 21, 2018 The Stewart Group | - PowerPoint PPT Presentation

Canadian P3 Rail Experience August 21, 2018 The Stewart Group | www.thestewartgroup.ca | +1 604-428-4424 | #207 990 Homer St. | Vancouver, CA 1 Canadian Transit Market Overview 2 2 Vancouvers Canada Line


  1. Canadian P3 Rail Experience August 21, 2018 The Stewart Group | www.thestewartgroup.ca | +1 604-428-4424 | #207 – 990 Homer St. | Vancouver, CA 1

  2. Canadian Transit Market Overview 2 2

  3. Vancouver’s Canada Line • Project Background • Structure • Performance • Lessons Learned 3 3

  4. Project Background • Canada’s first & largest P3 partnership • 19 km with 16 stations, Automated • Opened 2009 • Separate line • Separate O&M • 35-year concession agreement 4 4

  5. Project Background 5 5

  6. Structure - Contractual 6 6

  7. Structure - Funding 7 7

  8. Performance - Ridership • Day 1 – 82K passengers • Year 1 - 36.2M passengers • 3.8M passengers during Winter Olympics • System availability – 99.9% • Station availability – 99.9% Source - TransLink ---- Actual Ridership ---- 2005 Ridership Forecast 8 8

  9. Performance - Customer Satisfaction Source - TransLink 9 9

  10. Lessons Learned – Owner’s View • Accept a certain amount of loss of control • Risk transfer – retain those that are important to your organization • Distance project decisions from politics • There will be disputes – ensure resolution process is clear and acceptable • Difficult to manage and implement • Anticipate growth and changes, clarify in PA 10 10

  11. Lessons Learned – Proponent’s View • Performance based; not overly prescriptive • Reasonable honorarium • Limit the amount of change (freeze scope) • Risk costs money - concessionaire will always price risks that are transferred to them • Reasonable handback standards • Tight budget and schedule made it a good candidate for P3 • Knowledgeable owner’s team acting for all gov’t stakeholders 11 11

  12. P3 Projects in Development 12 12 12

  13. Edmonton Valley Line 13 13

  14. Project Background • 27 km “urban-style” LRT • Largest transit investment in City’s history - >$4B • Developed in two phases 14 14

  15. Project Background • Phase 1 - $1.8B • Pre-procurement and procurement phase 2012-2016 • 13 km • 12 stations/stops • At-grade, elevated and tunnelled • Bridge crossing • New technology - low floor, surface rail • Separate but integrated 15 15

  16. Structure • Edmonton’s first P3 rail project • Contract awarded – Feb 2016 • DBFOM + V • 30-year O&M term • VfM achieved – 24% 16 16

  17. Performance • 2.5 years into construction • Schedule and financial pressures • City monitoring Project Co closely 17 17

  18. Phase Two - Challenges of Expansion • 14 km extension, connecting in Downtown Core • $2.2B - $2.4B estimate • Early availability of funding accelerated project timeline • P3 contract schedule on expansion provided limited guidance on expansion protocols • Owner faced with possible sole source for scope elements vital for system interoperability 18 18

  19. Considerations • Re-negotiating a 30-year O&M contract is challenging • Agreements not designed for flexibility • Lender’s issues • Interface and integration risk • Customer experience (transfer point) • Performance to date • Maintaining VfM achieved in Phase One • Untested O&M performance 19 19

  20. Ottawa Confederation Line 20 20

  21. Project Background 4 th largest metropolitan hub in Canada • • $2.1B LRT system • 12.5 km with 13 stations/stops • At-grade, elevated & 2.5 km tunnel 21 21

  22. Structure • Ottawa’s first P3 rail project • Contract awarded - Dec 2012 • DBFM + V • 30-year maintenance term • Operated by municipality 22 22

  23. Performance • Construction launch – Winter 2013 • Original revenue service date - Spring 2018 • Revised revenue service date - Fall 2018 • Sink hole challenges 23 23

  24. Challenges of Expansion • Package of three rail extensions • Contract didn’t contemplate extension of this magnitude 24 24

  25. Approach • Required sole source and competitive tender • Owner purchased additional vehicles, maintenance, systems and expansion to OMF ~ $500M • Project Co also given CM role to maintain quality regime • Competitive tender for remaining scope • Interface agreements required • Systems integration an evolving challenge • Satisfying lenders costly - long-term debt buy-out required 25 25

  26. Surrey-Newton-Guildford LRT 26 26

  27. Project Background • Two phase LRT project in Vancouver suburb • Phase One – 10.5 km of surface rail; fully funded • Phase Two – 16.5 km (technology still under review) • Phase Two not funded 27 27

  28. Approach for Phase One • DBFOM • Shorter O&M term – 7 years • Rationale • Start up and early Ops risk transferred to private sector • Shorter term gives owner more flexibility on expansion & avoids expensive termination payments 28 28

  29. Conclusions • Contemplate future expansion; plan for it in the PA • Understand termination costs at project outset • Examine possibilities of pre-pricing certain key expansion elements/ both civil and debt • Lenders are a big deal • Change is inevitable in a transit system • Current P3 model not designed to be flexible 29 29 29

  30. Lecia Stewart Lecia@thestewartgroup.ca 604-764-8424 Source: xxx 30 30

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend