Northgate Link Extension Update Citizen Oversight Panel September 2, 2020 Project Overview 4.3 mile extension from UW to Northgate 3 light rail stations & 1 parking garage Fast and reliable service in congested I-5 corridor (14


slide-1
SLIDE 1

Northgate Link Extension Update

Citizen Oversight Panel

September 2, 2020

slide-2
SLIDE 2

2

  • 4.3 mile extension from UW to Northgate
  • 3 light rail stations & 1 parking garage
  • Fast and reliable service in congested I-5

corridor (14 minutes from Northgate to Downtown)

  • Estimated over 60,000 weekday boardings (2030)
  • Serves academic facilities (North Seattle College,

Roosevelt High School and UW)

  • Serves active business districts at Northgate,

Roosevelt and U District

  • Transit Oriented Development (TOD) projects are

planned for all three station sites

Project Overview

slide-3
SLIDE 3

3

  • Integrated Sound Transit

Team:

  • ~25 dedicated ST staff
  • ST support staff
  • Design/CM consultants
  • 11 separate construction

contracts

Project Organization

slide-4
SLIDE 4

4

Project Safety

  • Safety is a core Agency value and the top priority on the Northgate Link

Extension

  • Project Safety Metrics thru July 2020:

Data/Measure July 2020 Year to Date Project to Date Recordable Injury/Illness Cases 1 114 Days Away From Work Cases 6 Total # of Hours (GC & Subs) 48,516 364,126 5,442,250 OSHA Incident Rates Month Year to Date Project to Date Recordable Injury Rate 0.00 0.55 4.19 LTI Rate 0.00 0.00 0.22 Recordable Injury Rate WA State Average 6.00 LTI Rate WA State Average 1.90

slide-5
SLIDE 5

5

Project Budget

BUDGET AND CONTINGENCY

Project Budget (incl Contingency)

$ 1,899,755,500

Commitments To-Date (08-17-20)

$ 1,710,973,956

Contingency Remaining

$ 136,825,374

% of Contingency Spent

65.5%

% Physical Percent Complete (estimated)

96.1%

  • Currently projecting $52M+ savings at completion
slide-6
SLIDE 6

6

  • Currently 96% complete

with construction

  • On schedule to open for

Revenue Service in September 2021

Project Schedule

2013 2013 2014 2014 2015 2015 2016 2016 2017 2017 2018 2018 2019 2019 2020 2020 2021 2021

TBM T Tunn unnels els Nor

  • rthga

hgate S e Stat ation ion Roos

  • osev

evelt elt S Stat ation ion U-D

  • Dis

istrict ict S Stat ation ion Track ackwor

  • rk

Systems ems Tes est & & C Comm

  • mmis

ission ion Projec

  • ject Flo

Float at Pre-R e-Rev evenu enue S e Ser ervice ice Rev evenu enue S e Ser ervice ice

9/13 3/18 9/16 9/20 12/16 10/19 4/17 7/20 8/16 10/19 6/17 1/21 9/20 4/21 4/21 6/21 6/21 9/21

Construction Rail Activation

slide-7
SLIDE 7

7

Project Alignment

N

slide-8
SLIDE 8

8

TBM Tunnels UW Station to MLP

Contract Overview:

  • Design-Bid-Build contract with JCM

Northlink LLC

  • Scope of Work: portal structure, 2

station box excavations, 3.5 miles twin 18-ft 10-in tunnel, 23 cross passages, tunnel invert, walkway & raceways, tunnel lighting and dry standpipe

  • Contract Amount: $500m
  • Construction Start: September 2013
  • Construction Complete: March 2018
slide-9
SLIDE 9

9

TBM at Roosevelt Station

slide-10
SLIDE 10

10

TBM Removal at UWS

slide-11
SLIDE 11

11

Cross Passage Construction

slide-12
SLIDE 12

12

Project Alignment

N

slide-13
SLIDE 13

13

Northgate Station, Guideway, Garage

Contract Overview:

  • Design-Bid-Build contract with Absher

Construction

  • Scope of Work: 0.7 mile elevated

guideway, elevated station, 450-stall parking garage

  • Contract Amount: $187m
  • Construction Start: October 2016
  • Construction 97% Complete
slide-14
SLIDE 14

14

Northgate Station, Guideway, Garage

Looking NW towards Station

slide-15
SLIDE 15

15

Northgate Station, Guideway, Garage

Looking North towards South Entrance Looking South from Platform Level

slide-16
SLIDE 16

16

SDOT Northgate Pedestrian & Bicycle Bridge

  • Scope of Work: 16-ft wide, 1900-ft

long bridge spanning I-5 from NSC to Northgate Station

  • Construction Start: January 2020
  • Scheduled Completion: August 2021
  • Progress Summary:
  • 40% complete overall
  • all shafts complete
  • 90% of columns installed
  • 75% of precast girders installed
  • main span fabrication (offsite)

started

slide-17
SLIDE 17

17

SDOT Northgate Pedestrian & Bicycle Bridge

Bridge Column adjacent to Station Looking SW at Bridge Ramp from Station

slide-18
SLIDE 18

18

Project Alignment

N

slide-19
SLIDE 19

19

Roosevelt Station

Contract Overview:

  • GC/CM contract with Hoffman

Construction

  • Scope of Work: 90-ft deep, 480-ft long, 4-

level underground station; 2 head houses

  • Contract Amount: $168m
  • Construction Start: February 2017
  • Construction Complete: October 2019
slide-20
SLIDE 20

20

Roosevelt Station

2013

slide-21
SLIDE 21

21

Roosevelt Station

2017

slide-22
SLIDE 22

22

Roosevelt Station

2019

slide-23
SLIDE 23

23

Roosevelt Station

South Entrance off NE 65th St. Station Platform Level

slide-24
SLIDE 24

24

Roosevelt Transit Oriented Development

  • 1.2 acres of TOD property used

for construction staging

  • Roosevelt Station opens for

revenue service 2021

  • TOD project (Cedar Crossing)

complete 2022

  • Developers are Bellwether

Housing and Mercy Housing NW

  • Will provide 250+ affordable

housing units & childcare

slide-25
SLIDE 25

Cedar Crossing TOD Schedule

2016 2017 2018 2019 2020 2021 2022

Board approves agreement terms Agreements FTA approvals; ST Board approvals; Final closing legal documents TOD RFP Goal setting Community engagement; Seattle Office of Housing partnership Board and Seattle Office of Housing select Bellwether-Mercy Feasibility report completed Permits issued and ready DEVELOP CONSTRUCT DEFINE Testing TRANSIT PROJECT Design & construction Start of revenue service TOD PROJECT TOD Construction 24 mo. Board action on development strategy Permitting Design development; Permitting

2023

Due diligence Property closing Financing closing TOD site available TOD substantial completion Financing Securing local funds; Securing tax credits and investors; Securing debt and equity; Negotiating agreements

slide-26
SLIDE 26

26

TOD Key Business Terms

Category Agreement

Housing units At least 230 units; Anticipate 254 Total housing units affordable 100% of units at or below 60% Area Median Income (AMI) Deeper affordability At least 20% of units below 60% AMI; Anticipate 40% Family sized units At least 20% of units sized 2+ bedrooms; Anticipate 40% Active street-level uses At least 12,000 SF of commercial space, excluding daycare space; not regulating daycare in agreement Sustainability Designed to meet or exceed Washington State Evergreen Standard Sale price $6,750,000 with $130,000 in sale proceeds held in escrow for environmental work, if encountered, otherwise released to ST

slide-27
SLIDE 27

27

TOD Under Construction

slide-28
SLIDE 28

28

Cedar Crossing TOD

slide-29
SLIDE 29

29

Project Alignment

N

slide-30
SLIDE 30

30

U District Station

Contract Overview:

  • GC/CM contract with Hoffman Construction
  • Scope of Work: 80-ft deep, 400-ft long, 4-

level underground station; 2 head houses

  • Contract Amount: $169m
  • Construction Start: July 2017
  • Construction Complete: July 2020
slide-31
SLIDE 31

31

U District Station

Looking NE on Brooklyn Ave NE to South Entrance Looking SW from North Entrance Roof

slide-32
SLIDE 32

32

U District Station

Looking North at the Mezzanine Level Looking South towards the SB Platform

slide-33
SLIDE 33

33

Trackwork

Contract Overview:

  • Design-Bid-Build contract with Stacy and

Witbeck

  • Scope of Work: Trackwork (plinth + rail)

for alignment; 5 Hz & 16 Hz floating slabs

  • Contract Amount: $76m
  • Construction Start: August 2016
  • Construction Complete: October 2019
slide-34
SLIDE 34

34

Trackwork – Floating Slabs

slide-35
SLIDE 35

35

Systems

Contract Overview:

  • Heavy Civil GC/CM contract

with Mass Electric (MEC)

  • Scope of Work: Traction

Power, Overhead Catenary System, Communications, Signaling

  • Contract Amount: $104m
  • Construction Start: June 2017
  • Scheduled Completion: Q1

2021

  • Construction 74% complete

Power Cable Installation at UDS Equipment Testing at RVS

slide-36
SLIDE 36

36

Systems

Looking North from Northgate Station at Overhead Catenary System (OCS)

slide-37
SLIDE 37

37

  • Currently 96% complete

with construction

  • On schedule to open for

Revenue Service in September 2021

Project Schedule

2013 2013 2014 2014 2015 2015 2016 2016 2017 2017 2018 2018 2019 2019 2020 2020 2021 2021

TBM T Tunn unnels els Nor

  • rthga

hgate S e Stat ation ion Roos

  • osev

evelt elt S Stat ation ion U-D

  • Dis

istrict ict S Stat ation ion Track ackwor

  • rk

Systems ems Tes est & & C Comm

  • mmis

ission ion Projec

  • ject Flo

Float at Pre-R e-Rev evenu enue S e Ser ervice ice Rev evenu enue S e Ser ervice ice

9/13 3/18 9/16 9/20 12/16 10/19 4/17 7/20 8/16 10/19 6/17 1/21 9/20 4/21 4/21 6/21 6/21 9/21

Construction Rail Activation

slide-38
SLIDE 38

38

Rail Activation

  • Rail activation is managed by the Project

Transition Office in the Executive Department, led by Rail Activation Manager (RAM)

  • RAM ensures coordination of schedule

and resources for multiple, simultaneous activation efforts to assure the Northgate Link Extension is delivered into revenue service efficiently and safely.

  • RAM is supported by a set of committees

comprised of Sound Transit staff with the responsibilities for performing, documenting, and certifying various program elements tied to the start-up and testing of the system.

slide-39
SLIDE 39

Thank you.