Lynnwood Link Extension Project Update
Citizen Oversight Panel 2/21/19
Lynnwood Link Extension Project Update Citizen Oversight Panel - - PowerPoint PPT Presentation
Lynnwood Link Extension Project Update Citizen Oversight Panel 2/21/19 Lynnwood Link Extension Project Update Project Status Early Work Activities Community Outreach During Construction 2 Lynnwood Link Extension 8.5 miles
Citizen Oversight Panel 2/21/19
2
Construction
3
Northgate to Lynnwood with 4 stations
(30% increase in the corridor)
22,000 new
4
Subhead
2010-14 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Planning, PE and Environmental Final Design and Preconstruction Services Civil Construction and Structures Right of Way Acquisition Systems Startup Systems Installation Rail Service Begins
Baseline Project
Early Work Early ROW Acquisitions
FFGA Execution
Procurements
We are Here
Lynnwood Parking Garage Opens Project Float
Top Schedule Risks
Resource Agencies
construction
5 Budget Phase Baseline Budget (YOE$, M) Administration 98.2 $ Preliminary Engineering 39.1 $ Final Design 164.2 $ Construction Services 128.4 $ Third Parties 14.6 $ Construction 1,921.4 $ Right of Way 235.7 $ Project Contingency 170.2 $ Lynnwood Link Extension Project Total 2,771.6 $
Budget Status
date (20% of baseline budget) Top Cost Risks
price escalation, labor shortages
utility conditions
6
L200 L300 L800
Northgate Station to NE 200th Street
NE 200th Street to Lynnwood Station
7
Design completion status
Permitting status
construction permits concurrently with land use permits to minimize schedule impacts
8
L200 Civil (South)
December 2018
June 2019
September 2019
L300 Civil (North)
February 2019
July 2019
January 2020
L800 Systems
September 2020
9
Elected Officials
North Corridor Leadership Forum December 7 Edmonds City Council January 15 Lynnwood City Council January 16 Mountlake Terrace City Council January 17 Mukilteo City Council February 11 Snohomish County Council February 19 Shoreline City Council March 4 Everett City Council March TBD
Public Open Houses
Shoreline February 26 Mountlake Terrace Mid-April TBD Lynnwood Mid-April TBD
11
12
spring 2019
Migratory Bird Treaty Act
property after removal
next phase of contract
13
will be removed during Early Work
installed prior to existing noise wall removal as much as possible
mitigations may be employed by Sound Transit’s outreach team as needed
14
guideway construction will be constructed in Early Work
coordinated with WSDOT and cities during design
measures to be set up in Early Work
control
15
Roger’s Market Garage I-5 236th St SW
Temporary Parking
16
200th St SW 44th St W 48th St W
18
Sound Transit is committed to being a good neighbor during construction. We will work to manage impacts on surrounding communities by:
19
and maintain relationships within the community in
represent Sound Transit’s interests within the community and community’s interests within Sound Transit.
20
21
206-370-5664
normal business hours
Thank you.