Lynnwood Link Extension Project Update Systems Expansion Committee - - PowerPoint PPT Presentation

lynnwood link extension project update
SMART_READER_LITE
LIVE PREVIEW

Lynnwood Link Extension Project Update Systems Expansion Committee - - PowerPoint PPT Presentation

Lynnwood Link Extension Project Update Systems Expansion Committee Meeting 7/9/2020 Why we are here Today we are here to provide a general project progress update and inform the Boards decision on two proposed actions: Modify


slide-1
SLIDE 1

Lynnwood Link Extension Project Update

Systems Expansion Committee Meeting

7/9/2020

slide-2
SLIDE 2

2

Why we are here

  • Today we are here to provide a general project progress

update and inform the Board’s decision on two proposed actions:

  • Modify construction contract for Heavy Civil GC/CM

systems construction to include Lynnwood Link (Motion No. M2020-42)

  • Modify systems construction management consultant

services contract to include Lynnwood Link (Motion No. M2020-43)

slide-3
SLIDE 3

3

Today’s Presentation

  • Project Overview
  • Key Issues & Challenges
  • Proposed Board Actions
  • Questions
slide-4
SLIDE 4

4

Project Overview

  • 8.5 miles of aerial and at-grade guideway
  • Entirely grade-separated
  • Adds four new Link stations
  • Includes provisions for a future station at NE 130th
  • Adds three public parking garages
  • Civil construction underway via two Heavy Civil

GC/CM contracts

  • Revenue Service projected mid-2024
slide-5
SLIDE 5

5

Financial Snapshot

  • Financials as of May 2020
  • Year of Expenditure dollars
  • Project baselined in May 2018
  • Budget is inclusive of all allocated and unallocated contingencies
  • Major civil construction contracts underway, ~ 15% complete

Project Baseline Budget $2,771.6 M Committed $2,223.3 M Incurred $779.3 M 80% 28%

slide-6
SLIDE 6

6

Baseline Schedule

Subhead

  • Bullet

2010-14 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Planning, PE and Environmental Civil Construction and Structures Right of Way Acquisition Systems Startup Systems Installation Rail Service Begins

Baseline Project

Early Work Early ROW Acquisitions

FFGA Execution

Procurements

We are Here

Lynnwood Parking Garage Opens Project Float

Top Schedule Risks

  • City / AHJ Permitting
  • Civil / Systems Interfaces
  • Remaining ROW Acquisition

Final Design and Preconstruction Services

slide-7
SLIDE 7

7

Design, Permitting, and Right of Way

Design completion status

  • All elements Issued for Construction except:
  • 200th Street SW Widening (90%)

Permitting status

  • Major land use permits have been issued by Seattle, Shoreline,

Mountlake Terrace, and Lynnwood

  • Currently working to secure final development and building permits

with these cities

Right of Way status

  • 364 of 393 parcels acquired (93%)
slide-8
SLIDE 8

8

Construction Progress (King County)

slide-9
SLIDE 9

9

Construction Progress (King County)

slide-10
SLIDE 10

10

Construction Progress (Snohomish County)

slide-11
SLIDE 11

11

Construction Progress (Snohomish County)

slide-12
SLIDE 12

12

Community Outreach

  • Door-to-door outreach (pre-COVID) now

performed via phone and email

  • Community events have transitioned to
  • nline / remote formats
  • Neighborhood notifications continue
  • Construction alerts to ~9,000 subscribers
  • Noise mitigation packages offered
  • Addressing construction hotline issues
  • Gates being left unlocked overnight
  • Dust / debris in neighborhood areas
  • Noise / vibration
slide-13
SLIDE 13

13

Key Issues and Challenges

  • Tight budget and limited contingency
  • Timely acquisition of remaining right-of-way
  • Timely delivery of all construction permits from jurisdictional partners
  • Highway and neighborhood impacts during construction
  • Additional protocols associated with COVID-19 protections
  • Risks associated with “getting out of the ground”
  • Differing site conditions, unidentified utilities
  • Safety risks associated with transition to elevated work
  • Fall protection, dropped objects, work over roadways
slide-14
SLIDE 14

Proposed Board Actions

slide-15
SLIDE 15

15

Today’s Proposed Board Actions

Planned Modifications to Systems Construction and Systems Construction Management Contracts for the Lynnwood Link Extension

  • M2020-42: Authorize a modification to the Systems Construction

Contract (Mass Electric Construction Company) for $158.4 M, including a 7% contingency

  • M2020-43: Authorize a modification to the Systems Construction

Management Contract (Northwest Transit Systems Partners) for $19.8 M, including a 7% contingency

slide-16
SLIDE 16

16

Today’s Proposed Board Actions

  • Construction contract scope will include procurement and

installation of:

  • Train control, wayside train signal equipment and control houses
  • Traction electrification, traction power substations and overhead catenary
  • Communications systems for stations and garages
  • Supervisory Control and Data Acquisition (SCADA) updates
  • Construction Management contract scope includes contract

management services for the above construction elements.

slide-17
SLIDE 17

17

Small and Disadvantaged Businesses

Contract Small Business Disadvantaged Business Enterprise Mass Electric Construction Co. Goal 6% 3% Commitment 6% 3% Through June 2020 4.2% 3.7% Northwest Transit Systems Partners Goal 9.5% 4.5% Commitment 11% 6% Through June 2020 4.2% 3.6%

slide-18
SLIDE 18

18

Workforce Utilization

Contract Women People of Color Apprentices Mass Electric Construction Co. Goal 12% 21% 20% Commitment 12% 21% 20% Through June 2020 3.4% 30.4% 14.4%

slide-19
SLIDE 19

19

Lynnwood Link Extension: Baseline Budget $2,771.62M

ALLOCATION $ COMMITMENTS

Illustrative - Not to Scale

Approved Today’s Action Future Action

$2,771.62M Pjt Dvt. F/D Construction

slide-20
SLIDE 20

20

Lynnwood Link Extension: Board Approves Construction Contract $158.36M and Construction Services Contract $19.76M

ALLOCATION $ COMMITMENTS

Illustrative - Not to Scale

Approved Today’s Action Future Action

$2,771.62M Pjt Dvt. F/D Construction

slide-21
SLIDE 21

Thank you.

soundtransit.org

Thank you.