lynnwood link extension project update
play

Lynnwood Link Extension Project Update Board Meeting 7/23/2020 - PowerPoint PPT Presentation

Lynnwood Link Extension Project Update Board Meeting 7/23/2020 Why we are here Today we are here to provide a brief project progress update and inform the Boards decision on two proposed actions: Modify construction contract for


  1. Lynnwood Link Extension Project Update Board Meeting 7/23/2020

  2. Why we are here • Today we are here to provide a brief project progress update and inform the Board’s decision on two proposed actions: • Modify construction contract for Heavy Civil GC/CM systems construction to include Lynnwood Link (Motion No. M2020-42) • Modify systems construction management consultant services contract to include Lynnwood Link (Motion No. M2020-43) 2

  3. Today’s Presentation • Project Overview • Key Issues & Challenges • Proposed Board Actions • Questions 3

  4. Financial Snapshot and Key Issues Financials as of June 2020: Project Baseline Budget $2,771.6 M 80% Committed $2,229.0 M Incurred $803.1 M 29% Key Issues: • Tight budget and limited contingency • Additional protocols associated with COVID-19 protections • Safety risks associated with transition to elevated work e.g. fall protection, dropped objects, work over roadways 4

  5. Baseline Schedule 2010-14 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 We are Here Planning, PE and Top Schedule Risks Subhead Environmental • City / AHJ Permitting Procurements • Bullet Final Design and Preconstruction • Civil / Systems Interfaces Services • Remaining ROW Acquisition Baseline Project Right of Way Acquisition Lynnwood Parking Early ROW FFGA Execution Garage Opens Acquisitions Civil Construction and Structures Early Systems Installation Work Systems Project Startup Float Rail Service Begins 5

  6. Construction Progress (King County) 6

  7. Construction Progress (Snohomish County) 7

  8. Proposed Board Actions

  9. Today’s Proposed Board Actions Planned Modifications to Systems Construction and Systems Construction Management Contracts for the Lynnwood Link Extension • M2020-42: Authorize a modification to the Systems Construction Contract (Mass Electric Construction Company) for $158.4 M, including a 7% contingency • M2020-43: Authorize a modification to the Systems Construction Management Contract (Northwest Transit Systems Partners) for $19.8 M, including a 7% contingency 9

  10. Today’s Proposed Board Actions • Construction contract scope will include procurement and installation of:  Train control, wayside train signal equipment and control houses  Traction electrification, traction power substations and overhead catenary  Communications systems for stations and garages  Supervisory Control and Data Acquisition (SCADA) updates • Construction Management contract scope includes contract management services for the above construction elements. 10

  11. Mass Electric Construction Small/Disadvantaged Business Participation Contract SBE DBE Mass Electric Construction Co. Goal/Commitment 6% 3% Through June 2020 4.2% 3.7% The existing contract is approximately 40% complete. The S / DBE subcontract work has been awarded and is on target to achieve the contract commitments. 11

  12. Mass Electric Construction Workforce Utilization People of Contract Women Apprentices Color Mass Electric Construction Co. PLA/Goal 12% 21% 20% Through June 2020 3.4% 30.4% 14.4% Through July 15 3.5% 31% 15.7% 12

  13. Mass Electric Construction Women Workforce Utilization Forecast 13

  14. Mass Electric Construction Apprentice Workforce Utilization Forecast 14

  15. Northwest Transit Systems Partners Small/Disadvantaged Business Participation Contract SBE DBE Northwest Transit Systems Partners Goal 9.5% 4.5% Commitment 11% 6% Through June 2020* 10.27% 1.4% * Updated to reflect current statistics from Sound Transit’s Small Business program 15

  16. Northwest Transit Systems Partners DBE Utilization Forecast 16

  17. Illustrative - Not to Scale Lynnwood Link Extension: Baseline Budget $2,771.62M ALLOCATION $ COMMITMENTS Construction $2,771.62M F/D Dvt. Pjt Today’s Action 17 Approved Future Action

  18. Illustrative - Not to Scale Lynnwood Link Extension: Board Approves Construction Contract $158.36M ALLOCATION $ COMMITMENTS and Construction Services Contract $19.76M Construction $2,771.62M F/D Dvt. Pjt Today’s Action 18 Approved Future Action

  19. Thank you. Thank you. soundtransit.org

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend