Lynnwood Link Extension Seattle/Shoreline Open House Presentation - - PowerPoint PPT Presentation

lynnwood link extension
SMART_READER_LITE
LIVE PREVIEW

Lynnwood Link Extension Seattle/Shoreline Open House Presentation - - PowerPoint PPT Presentation

Lynnwood Link Extension Seattle/Shoreline Open House Presentation overview Introductions Project status Construction preview Open house guide Current service and approved projects Near term Link extensions:


slide-1
SLIDE 1

Lynnwood Link Extension

Seattle/Shoreline Open House

slide-2
SLIDE 2

Presentation overview

  • Introductions
  • Project status
  • Construction preview
  • Open house guide
slide-3
SLIDE 3

Near term Link extensions:

  • University of Washington – Northgate

(2021)

  • Northgate – Lynnwood (2024)
  • Downtown Seattle – Overlake (2023)
  • Angle Lake – Federal Way (2024)

Additional extensions were passed in Sound Transit 3.

Current service and approved projects

slide-4
SLIDE 4

Lynnwood Link Extension

  • 8.5 mile extension - Northgate to

Lynnwood City Center

  • 4 stations:
  • Shoreline South/145th – elevated
  • Shoreline North/185th – at grade
  • Mountlake Terrace – elevated
  • Lynnwood City Center – elevated

Service begins 2024

slide-5
SLIDE 5

NE 130th infill station

  • Located in Seattle at NE 130th and 5th Ave NE
  • Elevated Side-Platform design authorized

and funded under ST3

  • Scheduled to be operational in 2031
  • ST Board tasked staff with determining the

feasibility of building the station early

  • Purpose of an early build:
  • Avoid/minimize service impacts to LLE
  • Limit construction impacts
slide-6
SLIDE 6

Project status

  • Permitting
  • Federal funding
  • Thank you to our partners (Seattle, Shoreline, WSDOT, King County

Metro, Community Transit) Design Construction

slide-7
SLIDE 7

Shoreline South/145th

Vicinity Map and Site Plan

slide-8
SLIDE 8

Shoreline South/145th

Aerial View

slide-9
SLIDE 9

Shoreline South/145th

Platform View

slide-10
SLIDE 10

Shoreline North/185th

Vicinity Map and Site Plan

slide-11
SLIDE 11

Shoreline North/185th

South Entry View

slide-12
SLIDE 12

Shoreline North/185th

Platform View

slide-13
SLIDE 13

Construction preview

Work starting soon!

  • Early 2019
  • Structure demolition
  • Utility relocations
  • Clearing and grading
  • Mid-2019:
  • Light rail construction

begins

slide-14
SLIDE 14

Construction preview

slide-15
SLIDE 15

Construction preview

slide-16
SLIDE 16

Construction schedule

Construction schedules are fluid and subject to change.

slide-17
SLIDE 17

Tree removal and replacement

Trees and vegetation removed for construction access and staging

  • Begins early 2019
  • Keeping as many trees as

possible

Replanting more than twice as many as removed

  • Coordinating with cities and
  • ther partners
slide-18
SLIDE 18

Noise wall demolition

  • Existing WSDOT noise walls will be

removed in select locations

  • Temporary noise barriers will be

installed prior to existing noise wall removal as much as possible

  • New noise walls will be constructed

prior to light rail operations

slide-19
SLIDE 19

Parking changes

During construction

  • North Jackson P&R closes this

spring (~March 27)

  • Parking available at two

nearby lots

  • 1:1 replacement

Future parking

  • 500 new spaces at each

Shoreline station

slide-20
SLIDE 20

Long-term road closure

5th Ave NE will be closed

  • Starting as early as spring 2019
  • Closed between NE 130th and

NE 145th streets

  • Space required to build columns

for elevated structure

  • Pedestrian path to remain open
  • Local access to be maintained
slide-21
SLIDE 21

Additional early closures

  • Ronald Bog Park
  • New trails, signage and wetland

enhancements

  • NE 116th St. bike/ped path
  • Detour route and duration TBD
  • Enhanced bike/ped connection following

construction

  • I-5 ramps and lanes
  • Periodic closures
  • SR104
  • Ramp revisions

Typical work hours:

Monday – Saturday 7 am - 5 pm (periodic night and Sunday work will be necessary)

slide-22
SLIDE 22

Our commitment to you

Good neighbor commitments:

  • Provide advanced notification
  • Provide outreach staff on-site
  • Maintain a safe and secure

construction site

  • Maintain a clean work site and

protect the environment

  • Minimize noise, dust and

debris

  • Keep traffic moving
  • Provide a 24-hour

Construction Hotline Sign up for station-area email updates! soundtransit.org/subscribe

Community Outreach Specialist My Nguyen (Seattle & Shoreline)

  • 206-370-5690
  • My.Nguyen@SoundTransit.org
slide-23
SLIDE 23

Open House guide

What you’ll find:

  • Additional detail about upcoming

and future construction work

  • Meet the construction team
  • Partner tables

Online Open House: LynnwoodLink.Participate.Online Subscribe to construction alerts at soundtransit.org/subscribe

slide-24
SLIDE 24

soundtransit.org/LLE

Thanks!