westerly
play

Westerly FRANK LOCKER Educational Planning School Committee - PowerPoint PPT Presentation

Westerly FRANK LOCKER Educational Planning School Committee Meeting Site Concepts Observations & Findings F R A N K L O C K E R Educational Planning December 16, 2015 Agenda A Brief History School Design Priorities


  1. Westerly… FRANK LOCKER Educational Planning School Committee Meeting Site Concepts Observations & Findings F R A N K L O C K E R Educational Planning December 16, 2015

  2. Agenda • A Brief History • School Design Priorities • Identify Options • Validate or Disqualify Options • Discuss Option Sequencing • Evaluate Advantages & Disadvantages • Question & Answer F R A N K L O C K E R Educational Planning

  3. A Brief History • Vision 2020 (2001) • Middle School (2005) • High School (2012/13) • JCJ Report (2013) • School Redesign Advisory Committee (2014) • Engaged Dr. Frank Locker & StudioJAED for Strategic Facilities Planning (2015) • Forum for Educators • Forum for Public – August 18, 2015 • Forum for Public – September 29, 2015 • Preliminary Observations & Findings – December 2, 2015 • Model Options & Concept Site Plans – December 16, 2015 • Planned Model Vote – December 22, 2015 F R A N K L O C K E R Educational Planning

  4. School Design Priorities • 21 st Century Schools • Green School Buildings • Efficient and Effective Use of Capacity • Elementary Grades Pre-k to 4 • Climate Controlled • Flexible Learning Spaces • “Maker Spaces” • Smaller Schools (350) F R A N K L O C K E R Educational Planning

  5. Identify Options • Overview of Options Considered (RS) • Current 3 School Model Options Bradford Option • Renovate / Additions at Springbrook ES • Renovate / Additions at Dunn’s Corners ES • Renovate / Additions at Bradford ES F R A N K L O C K E R Educational Planning

  6. Identify Options State Street Option • Renovate / Additions at Springbrook ES • Renovate / Additions at Dunn’s Corners ES • New School at STATE Street Tower Street Option • Renovate / Additions at Springbrook ES • Renovate / Additions at Dunn’s Corners ES • New School at TOWER Street F R A N K L O C K E R Educational Planning

  7. Validate or Disqualify Options • Baseline Parameters for All Concept Plans • 350 Students (Subject to change based on Demographic Study) • 60,900 SF based on RIDE Guidelines (minimum) • Strategic / Functional Addition Locations • No Basements • 90+ Parking Spaces • Separate Parent & Bus Vehicular Drop-Off • Consistent Size Soft & Hard Play Areas • Area for Storm Water Management • Area for Septic Field Expansion (if required) • Wetland Avoidance F R A N K L O C K E R Educational Planning

  8. Bradford Elementary F R A N K L O C K E R Educational Planning

  9. Bradford ES Site Concept Plan • Current Student Enrollment • 86 (100) • Existing Building Area (SF) • First Floor 31,874 • Upper Floor 2,042 • Total 33,916 • Proposed Addition • Lower Level 10,384 • Main Level 16,600 • Total 60,900 F R A N K L O C K E R Educational Planning

  10. Bradford ES Site Concept Plan F R A N K L O C K E R Educational Planning

  11. Bradford ES Site Concept Plan • Single Site Entrance • Maximized Site Area – No Flexibility • Church Street / Rt. 216 Traffic • Limited Outdoor Activity / Play Areas • Triple Activity of Existing Site (100-350 Students) • Sensitivity to Community / Neighbors • Septic System Required to be Moved and Expanded for Building Additions F R A N K L O C K E R Educational Planning

  12. Dunn’s Corners Elementary F R A N K L O C K E R Educational Planning

  13. Dunn’s Corners Site Concept Plan • Current Student Enrollment • 290 • Existing Building Area (SF) • Basement -7,478 *Re-purpose for District Stg • First Floor 25,559 • Second Floor 17,165 • Total 42,724 • Proposed Addition • First Floor 10,483 • Second Floor 7,693 • Total 60,900 F R A N K L O C K E R Educational Planning

  14. Dunn’s Corners Site Concept Plan DUNN’S CORNERS SCHOOL F R A N K L O C K E R Educational Planning

  15. Dunn’s Corners Site Concept Plan • Classroom Addition is Not Contiguous With The Existing Classroom Space • Plateau Road • School Parking on Both Sides of Road • Consider Taking Control of Road as School Property from Town With Signage • Consistent With Family Property Donation • Activity Level of New Proposed Use Similar to Existing Student Body (290 – 350) • Septic System Will Require Expansion F R A N K L O C K E R Educational Planning

  16. Springbrook Elementary F R A N K L O C K E R Educational Planning

  17. Springbrook ES Site Concept Plan • Current Student Enrollment • 330 • Existing Building Area (SF) • Lower Level 8,129 • First Floor 34,693 • Total 42,822 • Proposed Addition • First Floor 15,758 • Second Floor 2,320 • Total 60,900 F R A N K L O C K E R Educational Planning

  18. Springbrook ES Site Concept Plan F R A N K L O C K E R Educational Planning

  19. Springbrook ES Site Concept Plan • Activity Level of New Proposed Use Similar to Existing Student Body (330 – 350) • (2) Site Entrances, But (1) Not Currently Used – Access Thru Locked Gate Into Small Residential Cul-de-sac • Extended Permitting Time F R A N K L O C K E R Educational Planning

  20. State Street Elementary F R A N K L O C K E R Educational Planning

  21. State St. ES Site Concept Plan • Current Student Enrollment • 370 • Existing Building Area (SF) • First Floor 47,403 • Total 47,403 • Proposed New Construction • First Floor 49,011 • Second Floor 11,889 • Total 60,900 F R A N K L O C K E R Educational Planning

  22. State St. ES Site Concept Plan F R A N K L O C K E R Educational Planning

  23. State St. ES Site Concept Plan • New School Cannot Be Built While Existing School is Occupied • Good Orientation of Public Spaces to Front of Site and Parking • Ideal Solar Orientation • Activity Level of New Proposed Use Similar to Existing Student Body (370 – 350) • Site Shape Provides Increased Potential For 21 St Century & Indoor / Outdoor Learning Environments • Town Sewer Line Relocation Required but Big Picture, the Cost is Insignificant F R A N K L O C K E R Educational Planning

  24. Tower Street School & CC F R A N K L O C K E R Educational Planning

  25. Tower St. & CC Site Concept Plan • Current Student Enrollment • Alternative HS • Alternative Sp.Ed. – Private Vendor • Preschool Program • Existing Building Area (SF) • First Floor 44,876 • Total 44,876 • Proposed New Construction • First Floor 49,011 • Second Floor 11,889 • Total 60,900 F R A N K L O C K E R Educational Planning

  26. Tower St. & CC Site Concept Plan F R A N K L O C K E R Educational Planning

  27. Tower St. & CC Site Concept Plan • Activity Level of New Proposed Use Significantly Different to Existing • Orientation of Public Spaces Not Optimally Located to Front of Site and Parking • Increased Site Access Will Likely Require a New Traffic Light • Relocating Developed Community Programs (Temporary or Long-Term) is Doable But Requires Special Handling F R A N K L O C K E R Educational Planning

  28. New School Option Sequencing Proposed Option Sequencing • State Street Option • Tower Street Option F R A N K L O C K E R Educational Planning

  29. WPS Sequencing New School Option Sequencing June thru September 2018 State Street Option 6 7 2 3 June thru September 2021 June thru September 2018 June 2021 – December 2022 4 June thru September 2019 September 2018 to September 2019 5 Additions & Renovations 1 New Construction June 2019 – September 2021 Fit Out F R A N K L O C K E R June 2017 – September 2018 Educational Planning Movement

  30. WPS Sequencing New School Option Sequencing June thru September 2018 Tower Street Option 7 2 3 June thru September 2021 6 June thru September 2018 June 2021 – December 2022* 4 June 2018 – September 2020 June thru September 2020 5 Additions & Renovations 1 New Construction June 2020 – June 2021 Fit Out F R A N K L O C K E R June 2017 – September 2018 Educational Planning Movement

  31. State Street Option Sequencing F R A N K L O C K E R Educational Planning

  32. Tower Street Option Sequencing F R A N K L O C K E R Educational Planning

  33. New Construction Site Pros Relatively Equal / No Major Driving Factor State Street Tower Street • Better Shaped Site • Preserves Potential to Re-Purpose High • Building Orientation Value State St. Site • Less Constrained • Stronger Potential • Potential for 21 St to Save Century Outdoor Operational Tax $ Learning • Possible Synergy with Elderly Center • Fewer Traffic Issues F R A N K L O C K E R Educational Planning

  34. Goals & Objectives December 22 nd Meeting: • Select Final Model • Not Required to Determine How Remaining Buildings Will Be Re-Purposed At This Time. F R A N K L O C K E R Educational Planning

  35. Questions & Answers F R A N K L O C K E R Educational Planning

  36. Appendices • Appendix 1 – Concept Site Plans • Appendix 2 – Concept Site Plans Preliminary Feasibility Review • Appendix 3 – Facilities Condition Assessment Report • Appendix 4 – Updated School Committee Presentation Observations & Findings (12/2/2015) • Appendix 5 – Wetlands Analysis • Appendix 6 – 1500’ Radius RIDE Site Conditions Analysis • Appendix 7 – Structural Integrity Analysis Report • Appendix 8 – Radon Analysis Report F R A N K L O C K E R Educational Planning

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.