the project is comprised of six major tasks
play

The Project is comprised of Six Major Tasks: 1. Outreach and Project - PowerPoint PPT Presentation

B AY P ARK /V ILLAGE OF E AST R OCKAWAY D RAINAGE I MPROVEMENTS Nassau County Governors Office of Storm Recovery Nelson & Pope MARCH 2017 P ROJECT B ACKGROUND AND O BJECTIVE March, 2014 GOSR releases the NY Rising Community


  1. B AY P ARK /V ILLAGE OF E AST R OCKAWAY D RAINAGE I MPROVEMENTS Nassau County Governor’s Office of Storm Recovery Nelson & Pope MARCH 2017

  2. P ROJECT B ACKGROUND AND O BJECTIVE ► March, 2014 – GOSR releases the NY Rising Community Reconstruction Program for Bay Park and Village of East Rockaway ► Nassau County commits to oversee a comprehensive Drainage I mprovement Study for the Bay Park/ Village of East Rockaway area. The Governor’s Office of Storm Recovery (GOSR) releases the Bay Park and East Rockaway Community Reconstruction Plan. This Plan identified the need for a comprehensive drainage study.

  3. P ROJECT I MPLEMENTATION ► I n September 2015, Nassau County released a Request for Proposal (RFP) to solicit proposals from qualified engineering firms to conduct a comprehensive drainage study and prepare preliminary design documents.

  4. P ROJECT I MPLEMENTATION Nassau County’s Department of Public Works to provide Project Oversight The Project Team consists of: ► Nelson & Pope, Engineers & Surveyors ► The LiRo Group ► Gayron de Bruin Land Surveying & Engineering (W/ DBE) ► Hirani Engineering & Land Surveying (M/ DBE) ► VJ Associates (M/ DBE)

  5. O VERALL S TUDY A REA

  6. The Project is comprised of Six Major Tasks: 1. Outreach and Project Coordination 2. Data Acquisition 3. Storm Event and Drainage System Analysis 4. Development of Alternatives 5. Preparation of H&H Technical Memo/ Final Report 6. Preparation of 30% Design Documents

  7. T ASK 1: O UTREACH AND P ROJECT C OORDI NATI ON Attend Project Coordination Meetings with County • February 2016 Kick Off Meeting with County and GOSR o April 2016 Progress Meeting with County o November 2016 Progress Meetings (2) with County o Outreach Meetings With County, Town, Governmental Agencies • March 2016 Committee Update with County, GOSR and the Village of East o Rockaway May 2016 Committee Update with County, GOSR, Town of Hempstead and the o Village of East Rockaway December 2016 Progress Meeting with County, GOSR, Town of Hempstead and o the Village of East Rockaway Coordination Meetings with Living with the Bay and GOSR on January 3rd and o 24 th of this year Focus Group/ Technical Meetings With Municipal Agencies • August 2016 Technical Meeting with County o August 2016 Technical Meeting with County and Village of East Rockaway o September 2016 Technical Meeting with County and Town of Hempstead o

  8. T ASK 2: D ATA A CQUI SI TI ON Prepare preliminary drainage plan depicting existing drainage • structures, piping, outfalls, recharge basins and other drainage related facilities; Obtain State, County, Town and Village Drainage records and pertinent • information; I nterview Personnel regarding system operation and issues; • Field I nventory of existing drainage facilities within the study area •

  9. T ASK 3: S TORM E VENT AND D RAI NAGE A NALYSI S • I dentify the overall drainage tributary area • Hydrology Method Used: SCD TR-55 • Perform analyses of the existing drainage system for 3 Storm Events: • 1-Year Storm (2.84”, 24-hour period); • 10-Year Storm (5.05”, 24-hour period) • 100-Year Storm (8.92”, 24-hour period) • Assumed Tidal Event used for Analysis: • Highest Annual Tide Cycle for Sandy Hook, NJ ( inf DPW ) nform at ion n receive ved from NCDP • Assumed Coincidental Rainfall and Tidal Events

  10. T ASK 3: S TORM E VENT AND D RAI NAGE A NALYSI S

  11. T ASK 3: S TORM E VENT AND D RAI NAGE A NALYSI S • Conduct a site visit during significant storm events to verify the model and operation of existing outfalls and valves

  12. T ASK 4: D EVELOPMENT AND A NALYSI S OF A LTERNATI VES Prepare and model various potential alternative flood mitigation • measures such as: o Storage basins o End-of and I n-Line Pipe Treatments I mplementation of green infrastructure pilot projects o I ncreasing Pipe Capacity o

  13. T ASK 5: P REPARATI ON OF F I NAL D RAI NAGE R EPORT The Report includes the following:  Description of existing conditions;  Summary of modeling and analyses; I dentification of deficiencies within the Study area;   Conceptual layouts of various strategies and improvements; Develop Preliminary Construction Costs based on the proposed alternatives;   Create Matrix comparing improvements, benefits, impacts and costs;  Utilize Matrix to identify high-priority project to move into preliminary design;  Prepare Recommendations for I mplementation and Development; Final Drainage Report Completed December 2016

  14. P ROPOSED PROJECT PRI ORI TY MATRI X Met with the County, the Town of Hempstead and the Village of East Rockaway in December 2016 to prioritize and select the Recommended Projects to be advanced to 30% Design Documents

  15. PROPOSED PROJECTS

  16. T ASK 6: P REPARATI ON OF 30% D ESI GN D OCUMENTS  Selected Projects: Lawson Avenue Long Term Solution o Multiple Check Valves I nstallation on Lawrence Street and North o Boulevard; North Boulevard at Rhame Avenue; West Boulevard; and East Boulevard  30% Plans, Specifications and Estimates for the selected projects are being developed and will be given to Nassau County upon completion (expected April 2017). To be further developed into Construction Documents under succeeding RFP

  17. LAWSON AVENUE LONG TERM SOLUTION

  18. MULTIPLE CHECK VALVE INSTALLATION

  19. OBSERVED FIELD CONDITIONS East Boulevard at Sampson Street January 24, 2017

  20. T ASKS C OMPLETED TO D ATE :  Reviewed and gathered Record Plans from State, County, Town and Village  Prepared Overall Study Aerial depicting all Record Plan Drainage Structures as well as GI S I nformation Completed Drainage Field I nventory   Analysis of the Existing Drainage Systems Completed  Developed Solutions, Alternatives and Recommended Projects  Final Drainage Report Completed December 2016  Selected Projects to be progressed to 30% Preliminary Plans  Commenced work on 30% Preliminary Plans for Selected Projects N EXT S TEPS :  Continue Development of 30% Preliminary Plans and Estimate for Selected Projects (expected completion April 2017).  Provide Nassau County with Completed 30% Preliminary Plans, Specifications & Estimate for Selected Projects

  21. Q UESTIONS & A NSWERS T HIS PROJECT WAS FUNDED BY AND CONCEIVED THROUGH THE NY R ISING C OMMUNITY R ECONSTRUCTION P ROGRAM OF THE G OVERNOR ’ S O FFICE OF S TORM R ECOVERY . F OR MORE INFORMATION CONTACT S EAN S ALLIE , P LANNING D IVISION , N ASSAU C OUNTY D EPARTMENT OF P UBLIC W ORKS , 1194 P ROSPECT A VENUE , W ESTBURY , NY 11590. EMAIL : SSALLIE @ NASSAUCOUNTYNY . GOV

  22. Addendum (slides inserted after 3/30/17 public meeting) • The previous slides, presented on 3/30/17, summarize the study process, findings and selected projects ( within available CDBG-DR funding allocation ). • The New York Rising Bay Park/Village of East Rockaway Community Reconstruction Plan (March, 2014) recommended the preparation of a study and several specific drainage improvement projects. • Excerpts from the Community Reconstruction Plan, pertaining to drainage recommendations, are called out in the following slides.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend