Southeast Boulevard Technical Planning Study Presentation to the Community December 11, 2014 Southeast Boulevard Planning Study C ommunity Presentation December 11, 2014 Existing Conditions Southeast Boulevard Planning Study C ommunity


slide-1
SLIDE 1

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Southeast Boulevard Technical Planning Study

Presentation to the Community

December 11, 2014

slide-2
SLIDE 2

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Existing Conditions

slide-3
SLIDE 3

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

1 2 3 4 5 6 7 8

Today

  • 1. View along L Street
  • 4. View from L Street looking east
  • 6. View along Water Street looking west
  • 2. View from L Street looking south
  • 3. Residential and trees along L Street
  • 5. View from Barney Circle looking west
  • 8. Barney Circle
  • 7. View from across the Anacostia River
slide-4
SLIDE 4

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Constraints

slide-5
SLIDE 5

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Opportunities

slide-6
SLIDE 6

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Where We Were

Concept A1 - Avenue Concept A2 – Grid Extended Concept A3 – L as Boulevard

slide-7
SLIDE 7

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Where We Were

Concept B1 – Split Linear Park Concept B2 - Parkway

slide-8
SLIDE 8

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Where We Were

Concept C1 – Central Park Concept C2 – Linear Park

slide-9
SLIDE 9

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept A (largely based on A-1)

slide-10
SLIDE 10

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept A before development

slide-11
SLIDE 11

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept A (largely based on A-1)

Land Uses

  • Extension of neighborhood fabric, street and block system
  • Moderate to medium density residential: multifamily and rowhouse
  • Small amount of ground-floor retail along 13th and 15th Streets
  • Potential future park at Boathouse Row
  • Potential future commercial or recreational building along M Street

New Streets

  • 4 lane boulevard with bike lanes and on-street parallel parking
  • L Street becomes double-sided with on-street parallel parking
  • Extension of grid streets south to boulevard

Connections to Waterfront

  • Pedestrian connections over CSX tracks at 13th, 14th, and 15th Streets to

Boathouse Row

Bus/ Streetcar Parking

  • Potential for parking in deck under boulevard
  • Entry/ exit from 11th and/or Barney Circle areas
slide-12
SLIDE 12

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept A view looking northeast

slide-13
SLIDE 13

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept A view looking southeast

slide-14
SLIDE 14

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept A view looking southwest

slide-15
SLIDE 15

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept A illustrative rendering

slide-16
SLIDE 16

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept B (largely based on A-2)

slide-17
SLIDE 17

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept B (largely based on A-2)

Land Uses

  • Extension of neighborhood fabric, street and block system
  • Moderate to medium density residential: multifamily and rowhouse
  • Small amount of ground-floor retail along 13th and 15th Streets
  • Potential future park at Boathouse Row with Harbor Bath
  • Potential future commercial or recreational building along M Street

New Streets

  • 2 lane streets with bike lanes and on-street parallel parking
  • L Street becomes double-sided with on-street parallel parking
  • Extension of grid streets south to new street

Connections to Waterfront

  • Pedestrian connections over CSX tracks at 13th, 14th, and 15th Streets to

Boathouse Row

Bus/ Streetcar Parking

  • None
slide-18
SLIDE 18

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept B view looking northeast

slide-19
SLIDE 19

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept B view looking southeast

slide-20
SLIDE 20

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept B view looking southwest

slide-21
SLIDE 21

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept B illustrative rendering

slide-22
SLIDE 22

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept C (largely based on C-1)

slide-23
SLIDE 23

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept C (largely based on C-1)

Land Uses

  • Neighborhood park between Capitol Hill and CSX right-of-way
  • Potential future park at Boathouse Row
  • Potential future commercial or recreational building along M Street

New Streets

  • 4 lane boulevard with bike lanes and on-street parallel parking
  • Boulevard Splits around park
  • Separated from L Street by tree-lined promenade
  • Extension of grid streets south to boulevard

Connections to Waterfront

  • Pedestrian connections over CSX tracks at 13th, 14th, and 15th Streets to

Boathouse Row

Bus/ Streetcar Parking

  • Potential for parking in deck under boulevard and park
  • Entry/ exit from 11th and/or Barney Circle areas
slide-24
SLIDE 24

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept C view looking northeast

slide-25
SLIDE 25

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept C view looking southeast

slide-26
SLIDE 26

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept C view looking southwest

slide-27
SLIDE 27

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Concept C illustrative rendering

slide-28
SLIDE 28

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Discussion Concept A Concept B Concept C

slide-29
SLIDE 29

Southeast Boulevard Planning Study C

  • mmunity Presentation – December 11, 2014

Southeast Boulevard Planning Study

Presentation to the Community

December 11, 2014

Next Steps

  • Completion of Technical Report
  • DDOT-Led Feasibility Study