Alafaya Trail Project Update
Avalon Park Boulevard to Mark Twain Boulevard
Mark Twain Boulevard Avalon Park Boulevard
3.8 Miles Alafaya Trail
Board of County Commissioners Discussion Agenda Item # B-1 January 25, 2011
Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain - - PowerPoint PPT Presentation
Alafaya Trail Project Update Avalon Park Boulevard to Mark Twain Boulevard Mark Twain Boulevard Alafaya Trail 3.8 Miles Avalon Park Boulevard Board of County Commissioners Discussion Agenda Item # B-1 January 25, 2011 Alafaya Trail Project
Mark Twain Boulevard Avalon Park Boulevard
3.8 Miles Alafaya Trail
Board of County Commissioners Discussion Agenda Item # B-1 January 25, 2011
Project
Procurement
Action
Mark Twain Boulevard Avalon Park Boulevard
3.8 Miles Alafaya Trail
Project
Procurement
Action
Mark Twain Boulevard Avalon Park Boulevard
3.8 Miles Alafaya Trail
Identified in Comprehensive Plan Public/Private Partnership Agreement
Construction Plans Finalized 2009 Right-of-Way Acquisition Completed
10 Stormwater
4 Travel Lanes Raised Grass
12,000 Feet of
Utility Work
– Wastewater, Reuse, Water Mains (Pipe Size Varies from 24” to 36”)
3 Signalized Intersections (One New) No Landscaping or Lighting Due to Budgetary
Existing Signal Upgrade Golfway Bv. Existing Signal Upgrade Innovation Way New Signal Stoneybrook Bv.
Project
Procurement
Action
Mark Twain Boulevard Avalon Park Boulevard
3.8 Miles Alafaya Trail
Anticipated BCC Approval - January 25, 2011 Anticipated Contract Execution - February 1, 2011 Anticipated Notice to Begin Construction -
Construction Duration 2-1/2 Years
County’s
Project
Procurement
Action
Mark Twain Boulevard Avalon Park Boulevard
3.8 Miles Alafaya Trail