coombs creek trail coombs creek trail
play

Coombs Creek Trail Coombs Creek Trail o BAHAMA TO MOSS PARK Public - PowerPoint PPT Presentation

C I T Y D A L L A S O F PARKS AND RECREATION DEPARTMENT Coombs Creek Trail Coombs Creek Trail o BAHAMA TO MOSS PARK Public Meeting June 30 th , 2020 Coombs Creek Trail Improvements Project Limits: 800 Block of N. Plymouth Rd. from Bahama


  1. C I T Y D A L L A S O F PARKS AND RECREATION DEPARTMENT Coombs Creek Trail Coombs Creek Trail o BAHAMA TO MOSS PARK Public Meeting June 30 th , 2020

  2. Coombs Creek Trail Improvements Project Limits: 800 Block of N. Plymouth Rd. from Bahama Dr. to the 2600 Block of Sunset Ave. at Moss Park. Scope of Work 2300 LF 10ft. wide reinforced concrete trail • 1130 LF 8ft. wide • Plymouth Rd. Between Bahama Dr. and Davis St.

  3. Existing sidewalk on west side of • Plymouth Rd. to be replaced with 10ft. wide trail. Insufficient street right-of-way width • at two locations requiring a reduced 8ft. wide trail. Holiday Hills Apartments Parking • Lot Crossing Plymouth Rd. vehicular • Bridge Add Alternate No. 1-Improvements: • Conduit and bases for future light poles along trail. Plymouth Rd. Between Bahama Dr. and Davis St.

  4. Plymouth Rd. Between Bahama Dr. and Davis St.

  5. Existing sidewalk on west side of • Plymouth Rd. to be widened to 10ft. wide trail. Curb and Gutter on the west side • of the street to be moved out into the street to accommodate wider sidewalk/trail width. Revise existing median striping to • maintain 12ft. vehicular lane width. Davis St. to Jefferson Blvd.

  6. Davis St. to Jefferson Blvd.

  7. Trail will be within the grass median • after crossing Jefferson Blvd. Jefferson Blvd. to Sunset Ave. at Moss Park

  8. Jefferson Blvd. to Sunset Ave. at Moss Park

  9. Trail Head constructed at Moss Park • Decorative concrete pavement • Seating • Landscape planting with irrigation • Moved Moss Park sign • Wildflower mix • Metal bike racks • Coombs Creek Trail Signage • Add Alternate No. 2 – Improvements” • North Oak Cliff Blvd. Trail Connection along Steven’s Golf Course – Connects to existing Coombs Creek Trail on Plymouth Rd. Moss Park Trail Head

  10. Moss Park Trail Head Concept and Amenities

  11. Moss Park Trail Head Concept and Amenities

  12. Coombs Creek Trail Funding • 2017 Bond Fund • Bond Fund Amount: $2,000,000.00 • Construction Allocation: $1,280,000.00 • Base Estimate: $1,140,000.00 • Add Alternate No. 1: $ 213,425.00 • Add Alternate No. 2: $ 95,000.00 • Schedule • August 2020 Plans Approved • October 2020 Receive Bids • December 2020 Award Construction • February 2021 Begin Construction • September 2021 Complete Construction • Funding and Schedule

  13. Grant Application • Park and Recreation Department submitted the project in • an application for the 2020 Transportation Alternatives Call for Projects through NCTCOG. If selected the City will receive Federal Grant Funds equaling $1.5 Million from the Federal Highway Administration. The grant program will be administered by the Texas Department of Transportation (TxDOT) Cost Estimate with Grant Funding: $2,000,000.00 • Add Alternate No. 1: $ 213,425.00 • Add Alternate No. 2: $ 95,000.00 • Schedule • May 2022 Plans Approved • August 2022 Receive Bids • December 2022 Award Construction • February 2023 Begin Construction • September 2024 Complete Construction • Grant Application and Schedule

  14. Questions? Questions? o Public Meeting June 30 th , 2020

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend