Coombs Creek Trail Coombs Creek Trail o BAHAMA TO MOSS PARK Public - - PowerPoint PPT Presentation

coombs creek trail coombs creek trail
SMART_READER_LITE
LIVE PREVIEW

Coombs Creek Trail Coombs Creek Trail o BAHAMA TO MOSS PARK Public - - PowerPoint PPT Presentation

C I T Y D A L L A S O F PARKS AND RECREATION DEPARTMENT Coombs Creek Trail Coombs Creek Trail o BAHAMA TO MOSS PARK Public Meeting June 30 th , 2020 Coombs Creek Trail Improvements Project Limits: 800 Block of N. Plymouth Rd. from Bahama


slide-1
SLIDE 1

Coombs Creek Trail Coombs Creek Trail

PARKS AND RECREATION DEPARTMENT

C I T Y

O F

D A L L A S

BAHAMA TO MOSS PARK

  • Public Meeting June 30th, 2020
slide-2
SLIDE 2

Plymouth Rd. Between Bahama Dr. and Davis St.

Coombs Creek Trail Improvements Project Limits: 800 Block of N. Plymouth Rd. from Bahama

  • Dr. to the 2600 Block of Sunset Ave. at Moss Park.

Scope of Work

  • 2300 LF 10ft. wide reinforced concrete trail
  • 1130 LF 8ft. wide
slide-3
SLIDE 3

Plymouth Rd. Between Bahama Dr. and Davis St.

  • Existing sidewalk on west side of

Plymouth Rd. to be replaced with

  • 10ft. wide trail.
  • Insufficient street right-of-way width

at two locations requiring a reduced

  • 8ft. wide trail.
  • Holiday Hills Apartments Parking

Lot

  • Crossing Plymouth Rd. vehicular

Bridge

  • Add Alternate No. 1-Improvements:

Conduit and bases for future light poles along trail.

slide-4
SLIDE 4

Plymouth Rd. Between Bahama Dr. and Davis St.

slide-5
SLIDE 5

Davis St. to Jefferson Blvd.

  • Existing sidewalk on west side of

Plymouth Rd. to be widened to 10ft. wide trail.

  • Curb and Gutter on the west side
  • f the street to be moved out into

the street to accommodate wider sidewalk/trail width.

  • Revise existing median striping to

maintain 12ft. vehicular lane width.

slide-6
SLIDE 6

Davis St. to Jefferson Blvd.

slide-7
SLIDE 7

Jefferson Blvd. to Sunset Ave. at Moss Park

  • Trail will be within the grass median

after crossing Jefferson Blvd.

slide-8
SLIDE 8

Jefferson Blvd. to Sunset Ave. at Moss Park

slide-9
SLIDE 9

Moss Park Trail Head

  • Trail Head constructed at Moss Park
  • Decorative concrete pavement
  • Seating
  • Landscape planting with irrigation
  • Moved Moss Park sign
  • Wildflower mix
  • Metal bike racks
  • Coombs Creek Trail Signage
  • Add Alternate No. 2 – Improvements”

North Oak Cliff Blvd. Trail Connection along Steven’s Golf Course – Connects to existing Coombs Creek Trail on Plymouth Rd.

slide-10
SLIDE 10

Moss Park Trail Head Concept and Amenities

slide-11
SLIDE 11

Moss Park Trail Head Concept and Amenities

slide-12
SLIDE 12

Funding and Schedule

  • Coombs Creek Trail Funding
  • 2017 Bond Fund
  • Bond Fund Amount:

$2,000,000.00

  • Construction Allocation:

$1,280,000.00

  • Base Estimate:

$1,140,000.00

  • Add Alternate No. 1:

$ 213,425.00

  • Add Alternate No. 2:

$ 95,000.00

  • Schedule
  • August 2020

Plans Approved

  • October 2020

Receive Bids

  • December 2020

Award Construction

  • February 2021

Begin Construction

  • September 2021

Complete Construction

slide-13
SLIDE 13

Grant Application and Schedule

  • Grant Application
  • Park and Recreation Department submitted the project in

an application for the 2020 Transportation Alternatives Call for Projects through NCTCOG. If selected the City will receive Federal Grant Funds equaling $1.5 Million from the Federal Highway Administration. The grant program will be administered by the Texas Department of Transportation (TxDOT)

  • Cost Estimate with Grant Funding:

$2,000,000.00

  • Add Alternate No. 1:

$ 213,425.00

  • Add Alternate No. 2:

$ 95,000.00

  • Schedule
  • May 2022

Plans Approved

  • August 2022

Receive Bids

  • December 2022

Award Construction

  • February 2023

Begin Construction

  • September 2024

Complete Construction

slide-14
SLIDE 14

Questions? Questions?

  • Public Meeting June 30th, 2020