Sanitation Fund

FY 2014/15 Budget Workshop

1

slide-2
SLIDE 2

FY 2014/15 Financial Overview

 Revenues:

Operating revenues for FY 2014/15 are projected to be approximately $53,300

  • r -0.7% lower than operating revenues budgeted in the current fiscal year.

 Expenses:

 Total Sanitation Expenses decrease by -1.5% or $107,320

 Operations: Decrease of $108,201 or -1.7%

A decrease of $150,000 in apartment and condominium reimbursements as a result of apartments no longer being eligible for reimbursement

A contractual increase of $24,138 for the curbside municipal solid waste collection contract and municipal solid waste disposal tipping fees

Sanitation Fund – FY 2014/15 Proposed Budget

2

slide-3
SLIDE 3

Sanitation Fund – FY 2014/15 Proposed Budget

FY 2014/15 Financial Overview (continued)

 Non-Operating Expenses: Remain Unchanged

$15,000 set aside in Capital Outlay to continue upgrades/repairs to landfill gas collection system.

A transfer to capital reserve of $95,000 for engineering and consulting services for preparing an application to DEEP to expand the capacity of the landfill.

3

slide-4
SLIDE 4

Sanitation Fund – FY 2014/15 Proposed Budget

Future:

 Landfill Expansion:

Construction of vertical MSE walls to expand capacity without increasing

  • verall maximum height or footprint of Landfill

Constructed as two distinct phases

Estimated Volume gain of up to 800,000 CY

$24 to $35 million in revenue

Additional Site Life 3.5 to 6.7 years

Construction cost $5.0 to $6.2 million. (both phases)

Design funds approved in FY14 budget, Preliminary design in progress

Depending on permitting process - Construction could begin in 2017 or 2018

4