San Pedro Widening CPN: 570491 Presented by: Bridgette Garrett, EI - - PowerPoint PPT Presentation

san pedro widening
SMART_READER_LITE
LIVE PREVIEW

San Pedro Widening CPN: 570491 Presented by: Bridgette Garrett, EI - - PowerPoint PPT Presentation

San Pedro Widening CPN: 570491 Presented by: Bridgette Garrett, EI PROJECT LOCATION PROJECT LOCATION EXISTING CONDITIONS Incomplete Pedestrian Facilities Sidewalk Curb Ramps Incomplete Curb & Gutter No Bicycle


slide-1
SLIDE 1

San Pedro Widening

CPN: 570491 Presented by: Bridgette Garrett, EI

slide-2
SLIDE 2

PROJECT LOCATION

slide-3
SLIDE 3

PROJECT LOCATION

slide-4
SLIDE 4

EXISTING CONDITIONS

 Incomplete Pedestrian Facilities

 Sidewalk  Curb Ramps

 Incomplete Curb & Gutter  No Bicycle Facilities  Minor Storm Drainage

Infrastructure

 Poor Lighting  Poor Pavement Condition

slide-5
SLIDE 5

EXISTING CONDITIONS

 Incomplete Pedestrian Facilities

 Sidewalk  Curb Ramps

 Incomplete Curb & Gutter  No Bicycle Facilities  Minor Storm Drainage

Infrastructure

 Poor Lighting  Poor Pavement Condition

slide-6
SLIDE 6

EXISTING CONDITIONS

 Incomplete Pedestrian Facilities

 Sidewalk  Curb Ramps

 Incomplete Curb & Gutter  No Bicycle Facilities  Minor Storm Drainage

Infrastructure

 Poor Lighting  Poor Pavement Condition

slide-7
SLIDE 7

San Pedro Dr from Alameda Blvd to Signal Ave

slide-8
SLIDE 8

San Pedro Dr from Anaheim Ave to Carmel Ave

slide-9
SLIDE 9

PROJECT SCOPE

 Design and Construction Phase Services

 DAR  Roadway Section  Pedestrian Accessibility  Storm Drainage Analysis  Right Of Way Acquisition  Street Lighting Improvements  Utility Relocations  Possible ITS Coordination  Public Involvement  Project Coordination  Typical Milestone Submittals (30%, 60%, 90%, 100%-Final)  Bid Phase Services

slide-10
SLIDE 10

PROJECT SCOPE

 Design and Construction Phase Services

 DAR  Roadway Section  Pedestrian Accessibility  Storm Drainage Analysis  Right Of Way Acquisition  Street Lighting Improvements  Utility Relocations  Possible ITS Coordination  Public Involvement  Project Coordination  Typical Milestone Submittals (30%, 60%, 90%, 100%-Final)  Bid Phase Services

slide-11
SLIDE 11

PROJECT COORDINATION

 City of Albuquerque (COA)

Traffic Engineering Storm Drainage Design Transit Capital Improvements Program (CIP) Design Review Committee (DRC)

 Albuquerque Bernalillo County Water Utility Authority (ABCWUA)  Utility Companies

slide-12
SLIDE 12

SCHEDULE

 Design Completion

 Fall 2021

 Construction Completion

 Spring 2023

 Locally Funded  Anticipated Construction Cost

 $4 million

slide-13
SLIDE 13

QUESTIONS

 Proposals due Monday, March 2, 2020 before 3:00 pm

Selection Advisory Committee Office Capital Implementation Program (CIP) Division Office One Civic Plaza 7th Floor, Room 7057 Albuquerque/Bernalillo County Government Center Albuquerque, NM 87102  No proposals will be accepted after the time specified.

 Any questions beyond this optional pre-submittal meeting must be sent in writing and

will be distributed to the listed attendees on the sign-in sheet.

 Questions or comments can be sent to Myrna Marquez at myrnamarquez@cabq.gov  Thank you and we look forward to seeing you at the upcoming SAC meeting!