citizen information meeting
play

Citizen Information Meeting Route 1 Widening to 6 Lanes - PowerPoint PPT Presentation

Prince William County Government Citizen Information Meeting Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) March 23, 2016 Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) 1 Route 1 Widening to 6 Lanes (Featherstone


  1. Prince William County Government Citizen Information Meeting Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) March 23, 2016

  2. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) 1

  3. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Project Overview  Project is funded by a combination of State, Federal, and Local funds through the Northern Virginia Transportation Authority (NVTA). Current project estimate is $86 million.  Administered by the Prince William County Department of Transportation.  Widening of Route 1 from a 4-Lane Undivided Roadway to a 6-Lane Divided Roadway.  Project Length approximately 1.3 miles.  Safety, Drainage, Signals, Pedestrian Improvements.  Undergrounding of Utilities. 2

  4. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Typical Section 3

  5. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Additional Design Features & Considerations  Design Speed of 45 mph; Posted Speed 35 mph.  Re-Alignment of Bel Air Rd. and Village Dr.  Stormwater Management Ponds (4 ponds).  Traffic Signals at Featherstone Rd., Rosedale Ct., Bel Air Rd./Village Dr., Prince William Pkwy./E. Longview Dr., and Marys Way/Mt. Pleasant Dr.  Pedestrian and Bicycle Facilities. • Wide Outside Lanes for bicycles (15’). • 10’ Shared Use Path (West side of Route 1). • 5’ Sidewalk (East side of Route 1).  Utility Relocation and Undergrounding. 4

  6. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Environmental NEPA Document – Environmental Assessment (EA).  • Preliminary (Phase 1) Environmental Site Assessment (ESA) completed. • Detailed (Phase 2) Environmental Site Assessments (ESA) to be performed after Citizen’s Information Meeting. • Noise and Air Quality reports ongoing. • Environmental studies will be available for Public Hearing in Summer 2016.  No Wetland/Stream impacts anticipated.  No anticipated effect on cultural resources. 5

  7. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Right of Way Acquisition  Right of Way and easements (permanent and temporary) will be required for project construction.  17 significant parcel impacts with approx. 73 overall impacted parcels.  Affected property owners will be contacted during land acquisition process initiation.  Structures identified as impacted to be demolished immediately following R/W Acquisition.  For additional information related to right of way acquisition, please contact Prince William County Right of Way Manager, Mr. Scott Hatten or Mr. Tim Witter: Mr. Scott Hatten Mr. Tim Witter Prince William County Department of Transportation Prince William County Department of Transportation 5 County Complex Court, Suite 290 5 County Complex Court, Suite 290 Prince William, VA 22192 Prince William, VA 22192 Email: Shatten@pwcgov.org Email: Twitter@pwcgov.org Telephone: 703-792-6825 Telephone: 703-792-6825 6

  8. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Project Schedule Summer 2016 – Public Hearing.  Fall 2016 – Finalize Design.  Fall 2016 – Initiate Right-of-Way (Total Acquisitions).  Spring 2017 – Initiate Right-of-Way (Partial Acquisitions).  Winter 2017-2018 – Utility Relocations Begin.  Fall 2018 – Advertise For Construction.  Summer 2021 – Project Complete.  7

  9. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Current Project Estimate Right of Way and Utilities $56M Preliminary Engineering $4M Construction: $26M Project Total: $86M  Project is funded by a combination of State, Federal, and Local funds through the Northern Virginia Transportation Authority (NVTA). 8

  10. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Upcoming Activities  Utility Test Pits will begin in April.  Geotechnical Borings will begin at the end of March.  Detailed (Phase 2) Environmental Site Assessments will begin in April. 9

  11. Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) Questions & Comments  Staff from Prince William County Department of Transportation and its consultants, Rinker Design Associates, P.C. and JMT are available to discuss the project and answer questions.  Written comments can be submitted to Prince William County’s Project Manager, Ms. Sherry Djouharian:  By email at: SDjouharian@PWCgov.org  Or by mail at: Ms. Sherry Djouharian Prince William County Department of Transportation 5 County Complex Court, Suite 290 Prince William, VA 22192 10

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend