Prince William County Government Citizen Information Meeting Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) March 23, 2016 Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way) 1 Route 1 Widening to 6 Lanes (Featherstone


slide-1
SLIDE 1

Prince William County Government

Citizen Information Meeting

Route 1 Widening to 6 Lanes

(Featherstone Rd. to Marys Way) March 23, 2016

slide-2
SLIDE 2

1

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

slide-3
SLIDE 3

2

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Project Overview

Project is funded by a combination of State, Federal, and Local funds through the Northern Virginia Transportation Authority (NVTA). Current project estimate is $86 million.

Administered by the Prince William County Department of Transportation.

Widening of Route 1 from a 4-Lane Undivided Roadway to a 6-Lane Divided Roadway.

Project Length approximately 1.3 miles.

Safety, Drainage, Signals, Pedestrian Improvements.

Undergrounding of Utilities.

slide-4
SLIDE 4

3

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Typical Section

slide-5
SLIDE 5

4

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Additional Design Features & Considerations

  • Design Speed of 45 mph; Posted Speed 35 mph.
  • Re-Alignment of Bel Air Rd. and Village Dr.
  • Stormwater Management Ponds (4 ponds).
  • Traffic Signals at Featherstone Rd., Rosedale Ct., Bel Air

Rd./Village Dr., Prince William Pkwy./E. Longview Dr., and Marys Way/Mt. Pleasant Dr.

  • Pedestrian and Bicycle Facilities.
  • Wide Outside Lanes for bicycles (15’).
  • 10’ Shared Use Path (West side of Route 1).
  • 5’ Sidewalk (East side of Route 1).
  • Utility Relocation and Undergrounding.
slide-6
SLIDE 6

5

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Environmental

  • NEPA Document – Environmental Assessment (EA).
  • Preliminary (Phase 1) Environmental Site Assessment (ESA)

completed.

  • Detailed (Phase 2) Environmental Site Assessments (ESA) to be

performed after Citizen’s Information Meeting.

  • Noise and Air Quality reports ongoing.
  • Environmental studies will be available for Public Hearing in

Summer 2016.

  • No Wetland/Stream impacts anticipated.
  • No anticipated effect on cultural resources.
slide-7
SLIDE 7

6

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Right of Way Acquisition

  • Right of Way and easements (permanent and temporary) will be required for

project construction.

  • 17 significant parcel impacts with approx. 73 overall impacted parcels.
  • Affected property owners will be contacted during land acquisition process

initiation.

  • Structures identified as impacted to be demolished immediately following R/W

Acquisition.

  • For additional information related to right of way acquisition, please contact

Prince William County Right of Way Manager, Mr. Scott Hatten or Mr. Tim Witter:

  • Mr. Scott Hatten

Prince William County Department of Transportation 5 County Complex Court, Suite 290 Prince William, VA 22192 Email: Shatten@pwcgov.org Telephone: 703-792-6825

  • Mr. Tim Witter

Prince William County Department of Transportation 5 County Complex Court, Suite 290 Prince William, VA 22192 Email: Twitter@pwcgov.org Telephone: 703-792-6825

slide-8
SLIDE 8

7

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Project Schedule

  • Summer 2016 – Public Hearing.
  • Fall 2016 – Finalize Design.
  • Fall 2016 – Initiate Right-of-Way (Total Acquisitions).
  • Spring 2017 – Initiate Right-of-Way (Partial Acquisitions).
  • Winter 2017-2018 – Utility Relocations Begin.
  • Fall 2018 – Advertise For Construction.
  • Summer 2021 – Project Complete.
slide-9
SLIDE 9

8

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Current Project Estimate

Right of Way and Utilities $56M Preliminary Engineering $4M Construction: $26M Project Total: $86M

  • Project is funded by a combination of State, Federal, and Local

funds through the Northern Virginia Transportation Authority (NVTA).

slide-10
SLIDE 10

9

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Upcoming Activities

  • Utility Test Pits will begin in April.
  • Geotechnical Borings will begin at the end of March.
  • Detailed (Phase 2) Environmental Site Assessments will begin

in April.

slide-11
SLIDE 11

10

Route 1 Widening to 6 Lanes (Featherstone Rd. to Marys Way)

Questions & Comments

  • Staff from Prince William County Department of Transportation and

its consultants, Rinker Design Associates, P.C. and JMT are available to discuss the project and answer questions.

  • Written comments can be submitted to Prince William County’s

Project Manager, Ms. Sherry Djouharian:

  • By email at: SDjouharian@PWCgov.org
  • Or by mail at:
  • Ms. Sherry Djouharian

Prince William County Department of Transportation 5 County Complex Court, Suite 290 Prince William, VA 22192