SLIDE 1
San Pedro Waterfront Berths 74-84 Promenade and Town Square
June 19, 2019
SLIDE 2 Agenda A. Overview B. Project Scope
- Demolition
- Promenade
- Town Square
C. San Pedro Public Market D. Phasing E. Pedestrian Access/Parking F. Coordination G. Schedule H. Accomplishments and Next Steps
SLIDE 3 Project Scope (Overview)
- Hardscape/Landscape/Irrigation
- Site Furnishings
- Site Removals
- Water/Fire Protection
- Lighting/Power/Security
- Museum Landing and
Overlook
- Floating Dock
- 7th Street Ramps
- Grading
- Drainage
- Intersection Modifications
- Street/Parking Lot
- Striping
- Signage
SLIDE 4 Project Scope (Demolition)
B76 - POC Restaurant B83 Acapulco Site B79 Asian Village B78 Soil Remediation
POC VILLAGE MARINA RESTAURANT BLUE BUILDING
SLIDE 5
Town Square Renderings
SLIDE 6
Town Square Renderings
SLIDE 7
Town Square Renderings
SLIDE 8
Town Square Renderings
SLIDE 9
Town Square Renderings
SLIDE 10
Town Square Renderings
SLIDE 11
Project Scope (Town Square)
SLIDE 12
San Pedro Public Market
SLIDE 13
San Pedro Public Market
SLIDE 14
San Pedro Public Market
SLIDE 15
San Pedro Public Market
SLIDE 16
San Pedro Public Market
SLIDE 17 Coordination
- Additional Contractors
- San Pedro Public Market
- Harbor Blvd Extension
- Town Square Restroom
- Jankovich
- Utility Companies
- DWP Water
- DWP Power
- Oil
- Existing Tenants – access must be
maintained
- San Pedro Fish Market
- Café International
- Crusty Crab
- LA Harbor Sport Fishing
- Los Angeles Maritime Institute (LAMI)
- Utro’s
- SP Slip
- Downtown Harbor
- Future Tenants – San Pedro Public Market
SLIDE 18
Project Schedule
Advertised: Construction (18 months) January 29, 2019 September 30, 2019 – March 30, 2021 San Pedro Public Market NTP Phase I March 2020 (12 months) Harbor Blvd Extension NTP March 2020 (9-12 months) Town Square Restroom NTP Spring 2020 (6 months) Promenade Phase II (depends on completion of SPPM Phase I area) NTP April 2021 (18 months)
SLIDE 19 Accomplishments and Next Steps
ACCOMPLISHMENTS
- Ports O’ Call Building Demolition
- Chevron Remediation
- Advertised Promenade and Town Square
- Accepted Bids Promenade and Town Square
NEXT STEPS
- Addendum (March)
- Contract Award (August)
- Lease Amendment (August)
- SPPM NTP (March 2020)
- Town Square Restroom (in design)
- Promenade – Phase II Project (continue design later this year)
SLIDE 20
Questions
Questions?