i i 405 sepulveda pass widening project 405 sepulveda
play

I- I-405 Sepulveda Pass Widening Project 405 Sepulveda Pass - PowerPoint PPT Presentation

I- I-405 Sepulveda Pass Widening Project 405 Sepulveda Pass Widening Project November 19, 2009 Project Overview 10 Mile Northbound HOV Lane Southbound Lane Standardization 20 Ramp Improvements 8 New Ramp Structures


  1. I- I-405 Sepulveda Pass Widening Project 405 Sepulveda Pass Widening Project November 19, 2009

  2. Project Overview • 10 Mile Northbound HOV Lane • Southbound Lane Standardization • 20 Ramp Improvements • 8 New Ramp Structures • Widening of 12 Bridge Structures • 3 New Bridge Structures • 18 Miles of Retaining Wall and Sound Wall • $1.034 Billion • Project Completion 2013 • Metro Board of Directors awarded project to Kiewit Pacific Company on April 24, 2009 • Issued Notice to Proceed June 2, 2009 • Project Commencement August 31, 2009 2

  3. Project Boundaries Southern Boundary National Blvd., South of the Santa Monica-Rosa Parks Freeway (I-10) Northern Boundary Greenleaf St. – South of the Ventura Freeway (U.S. 101) 3

  4. Project Approach 4

  5. Design/Build Project 5

  6. Project Milestones • Bridge Replacement Mulholland • Shifting of Sepulveda • Ramp Improvements at Wilshire, Sunset and Skirball • Construct Retaining Walls • MWD 96” water line realignment 6

  7. Pre-Construction Activities • Geotechnical Investigation • Inspection and cleaning of storm drains and sewers • Survey Work • Mobilization • Construction Yard and Trailer set up • Conceptual Design • Pre-Construction Surveys 7

  8. Construction Schedule Early Work Early Work (Start mid-late December 2009) • Construction Area Signs – Start December 2009 • Profile Grinding – Start 1st week of January 2010 • Lane Modifications/Re-striping – Start 3 rd week of December 2009 • Barrier Rail Installation – Start 2 nd week in January 2010 • Utility Relocations – Start January 2010 8

  9. Construction Schedule Continued Main Line Work (February/March 2010) Main Line Work (February/March 2010) • 17 Retaining Walls along Sepulveda Blvd. – March 2010 to July 2012 • Box Culvert Protection/Relocation – TBD • Wilshire Blvd. Interchange – March 2010 to October 2012 9

  10. Construction Schedule Continued Main Work (February/March 2010 Continued) Main Work (February/March 2010 Continued) • Sunset Overcrossing Replacement – March 2010 to June 2011 • Soil Nail Walls/Excavation along Sepulveda Pass – March 2010 to February 2011 10 10

  11. Upcoming Activities • Skirball Overcrossing Replacement – June 2010 to August 2011 • Mulholland Overcrossing Replacement – September 2010 to May 2012 • Getty Bridge Widening – March 2011 to September 2011 • Bel Air Crest Bridge Widening – June 2011 to November 2011 11 11

  12. Construction Mitigation • Construction Noise – Monitoring noise levels during construction – Source reduction – Reduction at recipient – Limiting night work – Complaint process 12 12

  13. Construction Mitigation Continued • Traffic Impacts – Outreach with CAC – Coordination with City and Caltrans – Avoid residential neighborhoods – Minimize Construction Vehicle Impacts • Lighting – Avoid Residents – Limit night work 13 13

  14. Projects Coordination Projects in the Corridor • Sepulveda Reversible and Bike Lane Project (LADOT) • Skirball Widening (LADOT) • DWP Sunset/Church Lane Sewer Project 14

  15. First Responders Coordination Main Line (Freeway) and Local Streets Main Line (Freeway) and Local Streets • Increase Freeway Service Patrol • CHP on site as required • Closure submitted to LAPD weekly • Close coordination of construction activities with LAPD, LASD, LAFD and CHP • Emergency vehicles will have access to construction zone throughout the 10 miles 15 15

  16. Community Relations Construction Impact Mitigation Program • Public Outreach • Stakeholder Communication • Construction Impact Mitigation • On-going Coordination with Caltrans on commuter notifications 16

  17. Community Relations Continued Resolving Issues • Regular hours work with Management team to address concerns • After hours work with field staff to address concerns • On call 24/7 for emergencies 17

  18. The End Metro Community Relations Project Hotline: (213) 922-3665 I405@metro.net www.metro.net/I-405 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend