I- I-405 Sepulveda Pass Widening Project 405 Sepulveda Pass - - PowerPoint PPT Presentation

i i 405 sepulveda pass widening project 405 sepulveda
SMART_READER_LITE
LIVE PREVIEW

I- I-405 Sepulveda Pass Widening Project 405 Sepulveda Pass - - PowerPoint PPT Presentation

I- I-405 Sepulveda Pass Widening Project 405 Sepulveda Pass Widening Project November 19, 2009 Project Overview 10 Mile Northbound HOV Lane Southbound Lane Standardization 20 Ramp Improvements 8 New Ramp Structures


slide-1
SLIDE 1

I- I-405 Sepulveda Pass Widening Project 405 Sepulveda Pass Widening Project

November 19, 2009

slide-2
SLIDE 2

2

Project Overview

  • 10 Mile Northbound HOV Lane
  • Southbound Lane Standardization
  • 20 Ramp Improvements
  • 8 New Ramp Structures
  • Widening of 12 Bridge Structures
  • 3 New Bridge Structures
  • 18 Miles of Retaining Wall and Sound Wall
  • $1.034 Billion
  • Project Completion 2013
  • Metro Board of Directors awarded project to Kiewit Pacific Company on April 24, 2009
  • Issued Notice to Proceed June 2, 2009
  • Project Commencement August 31, 2009
slide-3
SLIDE 3

3

Project Boundaries

Southern Boundary National Blvd., South of the Santa Monica-Rosa Parks Freeway (I-10) Northern Boundary Greenleaf St. – South of the Ventura Freeway (U.S. 101)

slide-4
SLIDE 4

4

Project Approach

slide-5
SLIDE 5

5

Design/Build Project

slide-6
SLIDE 6

6

Project Milestones

  • Bridge Replacement Mulholland
  • Shifting of Sepulveda
  • Ramp Improvements at Wilshire, Sunset and Skirball
  • Construct Retaining Walls
  • MWD 96” water line realignment
slide-7
SLIDE 7

7

Pre-Construction Activities

  • Geotechnical Investigation
  • Inspection and cleaning of storm drains and sewers
  • Survey Work
  • Mobilization
  • Construction Yard and Trailer set up
  • Conceptual Design
  • Pre-Construction Surveys
slide-8
SLIDE 8

8

Construction Schedule

Early Work Early Work (Start mid-late December 2009)

  • Construction Area Signs

– Start December 2009

  • Profile Grinding

– Start 1st week of January 2010

  • Lane Modifications/Re-striping

– Start 3rd week of December 2009

  • Barrier Rail Installation

– Start 2nd week in January 2010

  • Utility Relocations

– Start January 2010

slide-9
SLIDE 9

9

Construction Schedule Continued

Main Line Work (February/March 2010) Main Line Work (February/March 2010)

  • 17 Retaining Walls along Sepulveda Blvd.

– March 2010 to July 2012

  • Box Culvert Protection/Relocation

– TBD

  • Wilshire Blvd. Interchange

– March 2010 to October 2012

slide-10
SLIDE 10

10 10

Construction Schedule Continued

Main Work (February/March 2010 Continued) Main Work (February/March 2010 Continued)

  • Sunset Overcrossing Replacement

– March 2010 to June 2011

  • Soil Nail Walls/Excavation along Sepulveda Pass

– March 2010 to February 2011

slide-11
SLIDE 11

11 11

Upcoming Activities

  • Skirball Overcrossing Replacement

– June 2010 to August 2011

  • Mulholland Overcrossing Replacement

– September 2010 to May 2012

  • Getty Bridge Widening

– March 2011 to September 2011

  • Bel Air Crest Bridge Widening

– June 2011 to November 2011

slide-12
SLIDE 12

12 12

Construction Mitigation

  • Construction Noise

– Monitoring noise levels during construction – Source reduction – Reduction at recipient – Limiting night work – Complaint process

slide-13
SLIDE 13

13 13

Construction Mitigation Continued

  • Traffic Impacts

– Outreach with CAC – Coordination with City and Caltrans – Avoid residential neighborhoods – Minimize Construction Vehicle Impacts

  • Lighting

– Avoid Residents – Limit night work

slide-14
SLIDE 14

14

Projects Coordination

Projects in the Corridor

  • Sepulveda Reversible and Bike Lane Project

(LADOT)

  • Skirball Widening (LADOT)
  • DWP Sunset/Church Lane Sewer Project
slide-15
SLIDE 15

15 15

First Responders Coordination

Main Line (Freeway) and Local Streets Main Line (Freeway) and Local Streets

  • Increase Freeway Service Patrol
  • CHP on site as required
  • Closure submitted to LAPD weekly
  • Close coordination of construction activities with LAPD,

LASD, LAFD and CHP

  • Emergency vehicles will have access to construction zone

throughout the 10 miles

slide-16
SLIDE 16

16

Community Relations

Construction Impact Mitigation Program

  • Public Outreach
  • Stakeholder Communication
  • Construction Impact Mitigation
  • On-going Coordination with Caltrans on commuter

notifications

slide-17
SLIDE 17

17

Community Relations Continued

Resolving Issues

  • Regular hours work with Management team to address

concerns

  • After hours work with field staff to address concerns
  • On call 24/7 for emergencies
slide-18
SLIDE 18

18

The End

Metro Community Relations

Project Hotline: (213) 922-3665

I405@metro.net www.metro.net/I-405