US 60 Widening Project Public Meeting May 23, 2012 Discussion Items Purpose of Tonights Meeting US 60 Widening Project Team Project Purpose and Need Alternatives Project Schedule Why we are here To share


slide-1
SLIDE 1

US 60 Widening Project

Public Meeting May 23, 2012

slide-2
SLIDE 2

Discussion Items

  • Purpose of Tonight’s Meeting
  • US 60 Widening Project Team
  • Project Purpose and Need
  • Alternatives
  • Project Schedule
slide-3
SLIDE 3

Why we are here

  • To share information about the US 60 Widening

Project

  • To discuss improvement alternatives that are

under consideration

  • Most importantly, to obtain your comments and

concerns through the comment forms

We need your input!

slide-4
SLIDE 4

The US 60 Project Team

  • KYTC District 9
  • Stantec Consulting Services

– Design Consultant

slide-5
SLIDE 5
  • From I-64 to KY 180
  • Just over 3.8 miles in length
  • In Phase I / Preliminary Design phase
  • Will explore needed improvements to the KY 180 intersection

Project Information

slide-6
SLIDE 6

Project Purpose

The purpose of the US 60 widening project is to relieve congestion, improve safety, and provide system connectivity for motorists accessing downtown Ashland from the I-64 corridor.

slide-7
SLIDE 7

Traffic Forecasts

  • Existing (2011/2012)

– 10,500 to 13,500 vehicles per day (VPD)

  • Design Year (2030)

– 3 Lane: 14,400 to 15,600 VPD – 5 Lane: 17,400 to 18,800 VPD

  • The 5 Lane option diverts traffic from KY 180
slide-8
SLIDE 8

Crash History

  • 106 Crashes from

2009-2011

  • Rear end and angle

crashes make up 50%

  • f all collisions
  • Below average crash

rate overall

slide-9
SLIDE 9

We need your input!

  • The Project Team needs your help in determining

what the future roadway should look like

  • Would you prefer to widen US 60 to 3 lanes or 5

lanes?

  • Which typical section do you prefer?
  • How should we accommodate bicycles and

pedestrians?

  • Please fill out your questionnaire and leave it at

the sign-in table.

slide-10
SLIDE 10

Proposed Typical Sections

Three-lane options

Three lane Urban Typical with curb and gutter Three lane Rural Typical with shoulders

Five-lane options

Five lane Urban Typical with curb and gutter Five lane Rural Typical with shoulders

slide-11
SLIDE 11

Bicycle and Pedestrian Accommodations

Single sidewalk on the north / west side Bicycle Lanes on both sides of the roadway

slide-12
SLIDE 12

Alternatives Considered

slide-13
SLIDE 13

Potential Alignment Changes

slide-14
SLIDE 14

Segment 3

slide-15
SLIDE 15

KY 180 Intersection

slide-16
SLIDE 16

KY 180 Intersection Existing

slide-17
SLIDE 17

KY 180 Intersection Improved

slide-18
SLIDE 18

Project Schedule

Phase I (Preliminary Design) Complete Late Summer 2012 Phase II (Final Design) Complete 2013 Right-of-Way 2013-2014 Utilities 2014 Construction 2015-2016

slide-19
SLIDE 19

Contact Information

Rachel Catchings, P.E. Darrin Eldridge, P.E.