ACEC OC February 22, 2017 I-405 Freeway 1958 I-405 Freeway Today Measure R Highway Projects Study Area Highway Program Project Status Summary (Measure R Funded) # Current Phase Estimated Cost of Phase Project Current Phase ($mil.)
Study Area
Measure R Highway Projects
Highway Program Project Status Summary (Measure R Funded)
# Project Current Phase Estimated Cost of Current Phase ($mil.) Phase Completion 11 I-5 North HOV Project SR 14 to Parker Road PS&E $31.0 Dec 2018 12 I-605/I-5 Interchange Improvements PAED $20.84 Mar 2019 13 I-605/SR 60 Interchange Improvements PAED $30.0 Feb 2020 14 I-605/SR 91 Interchange Improvements PAED $7.8 May 2019 15 I-710/SR 91 Interchange Improvement PSR/PDS $2.6 June 2017 16 I-405 Crenshaw Blvd On and Off Ramps Improvements PS&E $10.3 Aug 2016 17 I-405 and I-110 Aux Lane from SR 91 to Torrance Blvd. PS&E $9.0 Jul 2017 18 SR 138, I-5 to SR 14 PAED $25.0 Apr 2017 19 I-710 South PAED $91.0 Sep 2018 20 I-710 South Early Action Projects - Soundwall Projects (3 locations) PS&E $12.7 Feb 2018 Subtotal Measure R Highway Projects $2,982.45
Highway Program Project Status Summary (Non-Measure R Funded)
# Project Current Phase Estimated Cost
- f Current
Phase ($mil.) Phase Completion
21 I-10 HOV from Citrus Avenue to SR 57 Construction $264.4 Nov 2021 22 I-10 HOV from Puente Avenue to Citrus Avenue Construction $195.6 Apr 2019 23 SR 57 and SR 60 Mixed Flow Interchange ** (Eastbound and Westbound flyover off-ramp to Grand Ave, Eastbound on-ramp SR-60) PS&E $13.0* Sep 2020 24 SR 71: I-10 to Mission Blvd ** PS&E and ROW $16.0 Dec 2019 25 SR 71: Mission Blvd to Rio Rancho Road ** PS&E and ROW $40.0 Dec 2019 Subtotal Non-Measure R Funded Highway Projects $529 Total Active Highway Projects $3,511.45
* Initial Budget Estimate is through completion of Design ** These are projects with completed PAED and in Approved 2009 LRTP and 2014 SRTP
Contracting Opportunities
- I-5 HOV and Truck Lanes (SR-14 to Parker Rd.)
Construction
- I-710 Early Action Projects (Soundwalls)
Construction
- High Desert Corridor
PS&E/ROW
- SR-138 Northwest
PS&E
- I-710 Early Action Projects
PS&E
- I-605/I-5 IC Improvements
PS&E
- I-605/60 IC Improvements
PS&E
- I-605/SR-91 Improvements
PS&E
- Arterials/Intersections
PAED/PS&E
- I-605/South Street Aux. Lane
PAED/PS&E
- I-605/Beverly Blvd. IC Improvements
PAED/PS&E
- I-710/SR-91 IC Improvements
PAED/PS&E
- SR-710 Corridor Improvements
PAED/PS&E
I-605 “Hot Spots”
- 2012 Feasibility Study
- Identified congestion hot spots along I-5, SR-91,
I-605, and I-405
- Freeway widening/additional lanes, ramp
reconfigurations, arterial intersection enhancements, signage, and safety features
- PIDs and PAEDs in progress for various projects
- Estimated total cost of projects in the corridor:
$4+ billion Project Summary Study Area
- Various early action projects upcoming and in
progress Status Update
91 60 5 405 91
6 4 7 5
1. Valley Blvd. IC Imp. 2. SR-60 Aux. Lane (WB) 3. Peck Rd. IC Imp. (NB) 4. Peck Rd. to Rose Hills, Add GP Lane (SB) 5. Beverly Blvd. IC Imp. (SB) 6. Whittier Blvd. IC Imp. (SB) 7. SR-91 to South Street Aux. Lane (SB)
Interchange Studies In Progress Early Action Projects TBI Early Action Projects Identified
1 3 N
“HOT Spots” & Early Action Freeway Projects
1 2
I-710 (South)
- In PAED phase
- 18 miles between the Ports of Long Beach and
Los Angeles and the SR-60
- Alternatives being pursued:
- 5C: One lane + upgrading
- 7: 5C + 4-lane freight corridor
- Estimated Cost: $4-$8 billion
- Project funded through PAED phase
- Includes “Early Action” Projects
Study Area
- Final EIR/EIS: Summer 2018
- Early Action projects starting in
2019 and after Project Summary Status Update
2 1 3 4 6 7 8 5 1. Florence Avenue 2. Firestone Blvd. 3. Imperial Highway 4. Alondra Blvd./91 5. Long Beach Blvd. 6. Del Amo Blvd. 7. Willow Street 8. Anaheim St./PCH 9. Shoemaker Bridge
N
9
Early Action Freeway Projects
High Desert Corridor
- In PAED phase
- 63 miles - Highway, Expressway, Tollway, High Speed Rail, Bikeway, and energy
production/transmission corridor
- Connecting North Los Angeles County and San Bernardino County (Victorville)
- Transit connection between the CHSR and the XpressWest
- Secured Funds-$33 Million (Measure R)
- Estimated cost: $8.9 bil.
- In Measure M for ROW and Engineering
Status Update Project Summary
- Final EIR/EIS completed in 2016
Northwest SR-138
- In PAED phase
- 36 miles from I-5 to SR-14
- Freeway/Expressway/conventional
highway
- $25 mil. Measure R through PAED
- Funding for subsequent phases needs
to be determined
- Estimated Project Cost: $700+ mil.
Status Update Project Summary
- Draft ED in circulation
- Final EIR/EIS approval in 2017
- Safety Projects construction
contracts through Caltrans
State Route 710 (North)
- $780M in Measure R funds
- In PAED phase
- Preliminary Cost Estimate: $130 mil-$6
billion
- 5 Alternatives Under Study:
- No Build Alternative
- Transportation System
Management/Transportation Demand Management (TSM/TDM)
- Bus Rapid Transit
- Freeway Tunnel
- Light Rail Transit Alternative
Project Summary Study Area Status Update
- Final EIR/EIS Approval in 2018
- $130 mil. allocated by the GCCOG – more $ in Measure M
from SGVCOG
- 10 locations studied under various contracts
- More locations to be evaluated under the interchange
improvement PAEDs
- Metro or local agencies will advance the projects
- All local project construction by local agencies
- Construction projects by cities on-going. Schedule and city
contacts posted on Metro Highway Program website
I-605 Corridor Arterial Improvements
- Insert the latest list
Local Projects to Construction
Funding and Resource Needs
- I-5 HOV/HOT Lanes between SR-14 and
Parker Road (C)
- I-110 Southbound Auxiliary Lane near the I-
405 Interchange (C)
- SR-138 Widening from I-5 to SR-14 (D/C)
- SR-138/SR-14 Local Interchanges (C)
- I-405, Crenshaw Blvd. Ramp Improvements
(C)
- I-605/I-5 Interchange Improvements (D/C)
- I-605/SR-60 Interchange Improvements
(D/C)
- I-605/SR-91 Interchange Improvements (C)
- I-605 Corridor Arterial Intersection
Improvements (D/C)
- I-710 South Early Action Projects -
Soundwalls (D/C)
- I-710 South Early Action Projects - Local
Interchanges (P/E/D/C)
- I-710/SR-91 Interchange Improvements
(P/E/D/C)
- SR-60/SR-57 Interchange (D/C)
- SR-71 Widening: Mission to I-10 (C)
- SR-71 Widening: Mission to SR-60 (C)
- US-101 Northbound Auxiliary Lane between
SR-110 and Echo Park/Glendale Blvd. Off- Ramp (D/C)
- US-101/I-405 Interchange Improvements
(D/C)
- SR-138 Improvements from SR-14 to San
Bernardino County Line (various segments) (P/E/D/C)
- I-605/I-10 Interchange Improvements
(P/E/D/C)
Measure R Projects Non-Measure R Projects
- High Desert Corridor
ROW
- I-5 N. HOV/Truck Lanes
- Other Freeway Projects
- LVM Subregional
Improvements
- Sepulveda Pass Corridor
Phase 1
- I-105 Express Lanes
- I-710 Early Action Projects
- I-605 Interchanges
- SR-71
- SR-57/SR-60 Interchange
Measure M
Measures M Projects
- I-405 SB Curve Impr.
- I-405/I-110 Interchange
- I-110 Express Lanes
Extension to the I-405 Interchange
- I-605 between I-105 and
I-10
- I-5, Paramount Blvd. to I-710
- I-710 Corridor & Early Action
Projects
Measure M
Measures M Projects
Measure M Major Projects
Measure M Subregional Projects
+ Subregional Projects
Measures R & M Project Delivery Schedule
- I-405 Early Action projects in South Bay
- Early Action projects in other subregions
- Obtain subregional concurrence on the list and
priority of projects
- Assist in accelerated delivery of local projects
- Extensive coordination and collaboration with
Caltrans and other agencies for accelerated project delivery
- Professional Services On-Call Contracts Awards in