BHS 100 Building Update & Timeline Extension C a p ita l Pro - - PowerPoint PPT Presentation

bhs 100 building update timeline extension
SMART_READER_LITE
LIVE PREVIEW

BHS 100 Building Update & Timeline Extension C a p ita l Pro - - PowerPoint PPT Presentation

BHS 100 Bldg Update & Timeline Extension BHS 100 Building Update & Timeline Extension C a p ita l Pro je c ts Re p o rt 072717 BHS 100 BHS 100 Building Update & T ime line E xte nsion Bldg Update & Timeline


slide-1
SLIDE 1

C a p ita l Pro je c ts Re p o rt

07∙27∙17

BHS 100 Bldg Update & Timeline Extension

  • BHS 100 Building Update

& Timeline Extension

slide-2
SLIDE 2

C a p ita l Pro je c ts Re p o rt

07∙27∙17

BHS 100 Bldg Update & Timeline Extension

∴ BHS 100 Building Steering Committee Update ∴ 2016 Capital Projects Budget Overview ∴ Timelines ∴ Next Steps

BHS 100 Building Update & T ime line E xte nsion Age nda

slide-3
SLIDE 3

C a p ita l Pro je c ts Re p o rt

07∙27∙17

BHS 100 Bldg Update & Timeline Extension

January ∴ Committee works with Mahlum to explore master planning and community partnerships ∴ Parents, teachers, administrators and Steering Committee representatives meet to discuss Special Education March ∴ Mahlum and staff meet with BARN to explore partnerships with CTE April ∴ Mahlum shares concept plans for CTE and Performing Arts campus with committee May ∴ SPED program location, CTE partnerships and identification of underutilized space discussion

BHS 100 Building Update & T ime line E xte nsion Ste e r ing Committe e Update

slide-4
SLIDE 4

C a p ita l Pro je c ts Re p o rt

07∙27∙17

BHS 100 Bldg Update & Timeline Extension

June ∴ Preliminary concept plans with considerations of space utilization, adjacencies, access, parking, site, flexibility, site massing, management and administration are reviewed by committee July ∴ Committee reviews project goals and prioritization ∴ Theater consultants interviewed by Mahlum ∴ Market conditions and cost escalation factors impacting projects ∴ Project schedule

BHS 100 Building Update & T ime line E xte nsion Ste e r ing Committe e Update

slide-5
SLIDE 5

C a p ita l Pro je c ts Re p o rt

07∙27∙17

BHS 100 Bldg Update & Timeline Extension

Campus Maste r Plan Ope ning

PLANNING AND DESIGN CONSTRUCTION PROCESS

E d Spe c Sc he matic De sign De sign De ve lop. Constr uc tion Doc ume nts Bid Constr uc tion L and Use Re vie w Bldg. Pe r mit

BHS 100 Bldg Update & T ime line E xte nsion Sc he dule - Cur r e nt

slide-6
SLIDE 6

C a p ita l Pro je c ts Re p o rt

07∙27∙17

BHS 100 Bldg Update & Timeline Extension

Blakely

July 2017

Pre-planning Renovation | Ed Specs | Design | Construction

100 Bldg CTE & Performing Arts Campus Planning

Campus Plan Ed Specs | Design | Construction Program Analysis & Direction

Options

BHS 100 Bldg Update & T ime line E xte nsion Sc he dule – Pr

  • po se d E

xte nsio n

100 Bldg CTE & Performing Arts

Program Analysis Space Utilization Preliminary Ed Spec Site Massing

2020/2021

Opens July 2021 Opens July 2020 Renovation | Ed Specs | Design | Construction

slide-7
SLIDE 7

C a p ita l Pro je c ts Re p o rt

07∙27∙17

BHS 100 Bldg Update & Timeline Extension

Blakely Options Program Analysis Campus Master Plan BHS 100 Bldg - Pause ∴ Timelines ∴ Prioritization ∴ Strategic phasing ∴ Risk management ∴ Market conditions ∴ CoBI impact ∴ Staff capacity | experience

Ne xt Ste ps

slide-8
SLIDE 8

C a p ita l Pro je c ts Re p o rt

07∙27∙17

BHS 100 Bldg Update & Timeline Extension

Que stions