Public participation

A RE YENG LINE 2C

19 March 2020

slide-2
SLIDE 2

A Re Yeng alignment

Soshanguve (Kopanong) Rainbow Junction Pretoria Central Business District Hatfield Menlyn Denneboom (Mamelodi) Akasia

v

Line 2A (7 km) Dec 14 Line 2B (10 km) 2020 Line 2C (11 km) 2020 Line 1C (13 km) 2021

Mahube Valley (Mamelodi)

Line 2D (9 km) 2020 Line 1B (10 km) 2021 Line 1A (9 km) 2016

LEGEND

  • Line 1
  • Line 2

Pretoria Station

slide-3
SLIDE 3

Route

January Masilela Drive Lynnwood Road Simon Vermooten Road Denneboom Link

Line 2C route

slide-4
SLIDE 4

Proposed station positions

L P Bambo Drive Shabangu Avenue

Line 2C and 2D

slide-5
SLIDE 5

History of Line 2C

The engagement commenced on 10 November 2014. Public meetings were held on the following dates:

  • 15 March 2016
  • 19 March 2017

The environmental studies were completed in 2015. A traffic impact assessment was completed in 2017. The promulgation of Simon Vermooten Road and the Mamelodi section of Line 2C was completed in June 2016.

slide-6
SLIDE 6

Environmental impact assessment specialist studies

Wetland delineation: Exigo3 Geo-hydrological investigations: Exigo3 Socio-economic impact assessment: Demacon Air quality studies: Rayten Engineering Solutions Noise impact: Enviro Acoustic Research Heritage assessment: Nzumbululo Heritage

slide-7
SLIDE 7

Summary of findings The diversion to alternative lower-order roads is already taking place.

  • Lane acquisition
  • This results in a large unserved demand along January

Masilela Drive and Lynnwood Road that cannot practically be accommodated on alternative routes.

  • There is gross oversaturation at several key intersections

along diversion routes on alternative routes.

  • Lane acquisition is not feasible and, therefore, is not

recommended.

  • Lane addition is recommended.
  • Minor road network upgrades are recommended.

Traffic impact assessment

slide-8
SLIDE 8

Line 2C traffic impact assessment – Intersection improvements

  • The following intersections are to be upgraded:
  • January Masilela Drive and Atterbury Road
  • January Masilela Drive and Glenwood Road
  • January Masilela Drive and Twig Street
  • January Masilela Drive and Lynnwood Road
  • Lynnwood Road and Lizann Avenue
  • Lynnwood Road and Jacobson Drive
  • Lynnwood Road and Rubida Street
slide-9
SLIDE 9

January Masilela Drive

  • Existing lane configuration maintained

There are two mixed traffic lanes in each direction.

  • Add two bus rapid transit lanes

There will be one bus rapid transit lane in each direction.

  • Non-motorised transport

There is a two-metre sidewalk and a two-metre cycle lane.

slide-10
SLIDE 10

January Masilela Drive

  • One station at Glenwood Road
  • One water course crossing
  • Two properties affected (parking areas)
  • Bus or taxi bays remain
  • No accesses affected
  • One additional traffic signal
slide-11
SLIDE 11

January Masilela Drive

slide-12
SLIDE 12

January Masilela Drive

slide-13
SLIDE 13

Lynnwood Road

  • Existing lane configuration

There are two general traffic lanes in each direction.

  • Future lane configuration

There will be two general traffic lanes in each direction. The median is wide enough to accommodate the construction

  • f one new bus rapid transit lane in each direction.
  • Non-motorised transport

There is a two-metre sidewalk and a two-metre cycle lane.

slide-14
SLIDE 14

Lynnwood Road

Station positions

  • Ascott Street – Jacobson Drive
  • Botterklapper Street
  • Simon Vermooten Road
slide-15
SLIDE 15

Line 2C Overview Lynnwood Road

slide-16
SLIDE 16

Line 2C Overview Lynnwood Road

slide-17
SLIDE 17

Line 2C Overview Lynnwood Road

slide-18
SLIDE 18

Line 2C Overview Lynnwood Road

slide-19
SLIDE 19

Line 2C Overview Lynnwood Road

slide-20
SLIDE 20

Line 2C Overview Lynnwood Road

slide-21
SLIDE 21

Line 2C Overview Lynnwood Road

slide-22
SLIDE 22

Simon Vermooten Road

Lane configuration

  • This road has recently been upgraded and the upgrade

has accommodated the future bus rapid transit lanes.

  • It has two general traffic lanes in each direction and one

bus rapid transit lane in each direction.

slide-23
SLIDE 23

Simon Vermooten Road

Station positions

  • Simon Vermooten Road and Griffiths Street
  • Simon Vermooten Road and

Bronkhorstspruit Road

  • Simon Vermooten Road and Alwyn Street
slide-24
SLIDE 24

Simon Vermooten Road

slide-25
SLIDE 25

Simon Vermooten Road

slide-26
SLIDE 26

Denneboom Link

  • Existing lane configuration

There is one general traffic lane in each direction.

  • Future lane configuration

There will be one general traffic lane in each direction and the construction of one new bus rapid transit lane in each direction.

  • Non-motorised transport

There is a two-metre sidewalk and a two-metre cycle lane.

slide-27
SLIDE 27

Line 2C Overview Denneboom Link

slide-28
SLIDE 28

Denneboom Intermodal Facility

Mamelodi to CBD 45 Buses/hr.

slide-29
SLIDE 29

Promulgation process

Notice of intent – Mid April 2020 Comment period – 21 days Closing date for comments – May 2020 Report to Council for final decision Promulgation in Provincial Gazette