public involvement meeting wis 106 improvements
play

Public Involvement Meeting WIS 106 Improvements Town of Sumner Town - PowerPoint PPT Presentation

Public Involvement Meeting WIS 106 Improvements Town of Sumner Town Hall October 8, 2019 Project Team WisDOT Southwest Region Karla Knorr,PE, Project Supervisor Brad Schultz, PE, Project Manager MSA Professional Services, Inc.


  1. Public Involvement Meeting WIS 106 Improvements Town of Sumner Town Hall October 8, 2019

  2. Project Team • WisDOT Southwest Region  Karla Knorr,PE, Project Supervisor  Brad Schultz, PE, Project Manager • MSA Professional Services, Inc.  Ben Wilkinson, PE, Project Supervisor  Chase Kieler, PE, Project Manager  Nathan Cook, PE, Project Engineer

  3. Meeting Agenda • Project history • Design considerations • Proposed improvements • Proposed schedule

  4. WIS 106 Project History • WIS 106 Roadway:  1954: Roadway reconstruction  1954 -1996: Mill & overlays; most recent 1996 B-28-0107  2001: Pulverize & overlay • Structures:  B-28-0107: concrete flat slab bridge, constructed 2001  B-28-0108: two span concrete slab bridge, constructed in B-28-0108 2001  C-28-0011: 12-ft x 8-ft box culvert, widened in 1954 C-28-0011

  5. WIS 106 Project History  Current Roadway Issues: • Existing pavement is deteriorated with cracking and rutting • Structure C-28-0011 does not have guardrail to protect the blunt ends of concrete parapets

  6. WIS 106 Project History  Safety Screening Analysis conducted by WisDOT • No crash patterns attributed to the existing roadway geometry • Crashes are attributed to vehicle failure, driver impairment, and weather-related crashes • There were some run off the road crashes at the east end along the river

  7. WIS 106 Design Considerations  Design Alternatives Considered • Do Nothing – Roadway will continue to deteriorate • Full Reconstruction – Complete replacement of the roadway structure  Extensive right of way impacts • Right of way acquisition needed for ditch widening, culvert extensions  Extensive environmental impacts • Wetland impacts, tree clearing  High project cost • Excessive costs given that the existing roadway base materials and lower layers of pavement can still be used. • Mill and Overlay (Preferred Alternative) – Remove and replace top pavement layers  Minimal impacts  Cost Effective method that addresses the roadway issues efficiently

  8. WIS 106 Proposed Improvements  Pavement Improvements – Mill & Overlay (Preferred Alternative) • Mill 2 ½ to 3 ½ inches of the top of the existing asphalt pavement. Then add 2 ½ to 3 ½ inches of new asphaltic pavement. • Existing shoulder widths (4 to 10 feet) to be maintained • Increased paved shoulder widths in some areas (add 1 to 2 feet) • Some added base aggregate to reshape gravel shoulders Existing Proposed

  9. WIS 106 Proposed Improvements  Safety Improvements – Mill & Overlay (Preferred Alternative) • Guardrail improvements  Added guardrail at east end of project along the river  Added guardrail at structure C-28-0011  Evaluating possible improvements to existing guardrail at B-28-0107 and B- 28-0108

  10. WIS 106 Proposed Improvements  Safety Improvements– Mill & Overlay (Preferred Alternative) • Centerline Rumble Strips • Reduces head-on and run-off-road to left crashes

  11. WIS 106 Proposed Improvements  Structures Improvements • Concrete Deck Overlays were evaluated at bridges B-28-0107 and B-28-0108  Infrared scans revealed that the decks are in good shape – overlays are not needed at this time • Improvements to box culvert C-28-0011  Replace displaced wingwalls • Cross Culvert Replacement  Culvert inspections performed by Dane County and Jefferson County.  One culvert in need of replacement (west of Kruetz Road intersection)

  12. Proposed Schedule & Traffic Impacts • The project is expected to be constructed during the summer of 2022 • It is anticipated that the project will be staged  One lane constructed at a time  Flagging will be utilized to maintain one lane of traffic. Source: Wayne State University College of Engineering

  13. Design & Public Outreach Schedule • Public Involvement Meeting – October 2019 • Environmental Document – February 2020 • Preliminary Plans – April 2020 • Final Plans – May 2021 • Construction – Summer 2022

  14. Thank you! Please move about the room to examine the various exhibits on display. Project staff is available to gather input and discuss any questions you may have. Feel free to contact project team at any time during the ongoing design process!

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend