Public Involvement Meeting WIS 118 US 63 WIS 112 Ashland and Bayfield Counties March 24, 2020 Introductions Jeff Olson, WisDOT Project Supervisor Jeff Saxby, WisDOT Consultant Project Manager Jim Wendels, QUEST Civil Engineers


slide-1
SLIDE 1

WIS 118 US 63 – WIS 112 Ashland and Bayfield Counties

March 24, 2020

Public Involvement Meeting

slide-2
SLIDE 2

Introductions

  • Jeff Olson, WisDOT Project Supervisor
  • Jeff Saxby, WisDOT Consultant Project Manager
  • Jim Wendels, QUEST Civil Engineers
  • Adam Osypowski, QUEST Civil Engineers
slide-3
SLIDE 3

Purpose of Meeting

  • Review purpose and need for project
  • Describe proposed improvements
  • Discuss anticipated impacts
  • Review project schedule
  • Receive public input
slide-4
SLIDE 4

Project Location Map

Project ID: 8725-02-00 Benoit-WIS 112 USH 63 to WIS 112 STH 118, Bayfield and Ashland Counties

Bayfield County Ashland County

slide-5
SLIDE 5

Need for Project

  • Roadway surface on WIS 118 is deteriorating.
  • Some sections of the WIS 118 pavement have settled.
  • Several culvert pipes need maintenance.
slide-6
SLIDE 6

Proposed Improvements

  • Deep mill and overlay WIS 118.
  • Conduct additional underlying pavement repairs in settled areas after

milling.

  • Replacing one culvert and rehabilitating several other culverts.
  • Paving side road approaches.
  • Refreshing gravel shoulders and emergency turnouts.
slide-7
SLIDE 7

Property Impacts

  • Project expected to be constructed within existing right of way.
  • No real estate is anticipated to be acquired.
  • Temporary driveway closures will be necessary during parts of the

construction process.

  • Will coordinate with property owners during these periods.
slide-8
SLIDE 8

Traffic Management During Construction

  • Construction currently is scheduled for summer of 2021.
  • WIS 118 will be closed to through traffic and detoured.
  • WIS 118 will be open to local traffic.
  • Motorists can expect to encounter lane closures and flagging operations.
  • WIS 118 may be closed in both directions for culvert construction.
  • These closures are anticipated to last 2-3 days each.
slide-9
SLIDE 9

WIS 118 Project Limits

Bayfield County Ashland County

WIS 118 DETOUR US 63- US 2 – WIS 112

WIS 118 Detour Route

slide-10
SLIDE 10

Current Project Schedule

  • Public Involvement Meeting

March 24, 2020

  • Environmental document

May 2020

  • Final design

July 2020 – November 2020

  • Construction

Summer 2021

slide-11
SLIDE 11

Project Contacts

Jeff Saxby WisDOT Consultant Project Manager (920) 380-2805 jsaxby@sehinc.com Jim Wendels, P.E. Consultant Project Manager (715) 423-3525 jim.wendels@questllc.biz

slide-12
SLIDE 12

Questions?

Your attendance, comments and input are keys to project success!