adams road simcoe boulevard aoda ramp
play

ADAMS ROAD & SIMCOE BOULEVARD AODA RAMP TOWN OF INNISFIL P U B - PowerPoint PPT Presentation

1 ADAMS ROAD & SIMCOE BOULEVARD AODA RAMP TOWN OF INNISFIL P U B L I C I N F O R M AT I O N C E N T R E December 4, 2019 2 WELCOME THIS PUBLIC INFORMATION CENTRE WILL: PUBLIC AND STAKEHOLDERS SHOULD: establish channels of


  1. 1 ADAMS ROAD & SIMCOE BOULEVARD AODA RAMP TOWN OF INNISFIL P U B L I C I N F O R M AT I O N C E N T R E December 4, 2019

  2. 2 WELCOME THIS PUBLIC INFORMATION CENTRE WILL: PUBLIC AND STAKEHOLDERS SHOULD:  establish channels of communication with public &  sign the registry stakeholders review the presentation material  detail the work area  ask questions of the Town and/or Consultant  identify the purpose and objective  submit a comment sheet & indicate whether or not  seek input & comments for consideration in the final you want to be kept informed of the process  design

  3. 3 KEY PLAN The ramp is proposed at the location where Adams Road and Simcoe Boulevard meet

  4. 4 BACKGROUND OBJECTIVES The concrete stairs that currently provide The objectives of this project are to: access between Adams Road and Simcoe Boulevard are deficient: Improve the condition and safety level of the means of  The stairs are in poor structural condition and out of  pedestrian access between Adams Road and Simcoe level Boulevard The stairs have been identified as a safety concern  Comply with the Accessibility for Ontarians with  Disabilities Act  The stairs do not provide safe access from one road to the other for pedestrians with disabilities Comply with the Town of Innisfil’s Community  Strategic Plan which states that improving The stair dimensions are not compliant with current  accessibility within the Town of Innisfil is a strategic accessibility regulations, specifically the Accessibility priority for Ontarians with Disabilities Act

  5. 5 OPTIONS CONSIDERED Replace Stairs with Ramp Replace Stairs with New Stairs Replace Stairs with Elevator Benefits Benefits Benefits Addresses safety and condition Addresses safety and condition   Addresses safety and condition  concerns. concerns. concerns.  Addresses accessibility  Addresses AODA deficiencies with  Addresses accessibility deficiencies deficiencies and complies with the existing stairs. and complies with AODA requirements. AODA requirements. Least impactful of the options.  Complies with the Town of Innisfil’s  Complies with the Town of  Community Strategic Plan by providing Innisfil’s Community Strategic Least expensive option.  Plan by providing access for access for residents with disabilities. residents with disabilities. Concerns Concerns Concerns Does not address AODA deficiencies  with respect to wheelchair access. Still requires much of the same   More difficult to construct than infrastructure as the ramp (power, stairs alone but approximately Does not meet the intention of the  concrete retaining walls, helical piles). equivalent difficulty to elevator Town of Innisfil’s Community Strategic option. Plan. Would require stairs to be constructed  as well. Most impactful of the options  considered. Most expensive option to construct.  Flat landings at each change in  ramp alignment in accordance Potential for vandalism leading to  with the Accessibility for ongoing repair and improvement costs. Ontarians with Disabilities Act 5

  6. 6 FEATURES OF PROPOSED DESIGN The proposed ramp design has the following The proposed ramp design has the following features: features: Maximum slope of 1:15 in accordance with the A heating cable system to melt snow on contact with   Accessibility for Ontarians with Disabilities Act drainage scuppers to direct drainage away from the ramp  Flat landings at each change in ramp alignment in accordance with the Accessibility for Ontarians with Drainage swales to carry runoff water around the  Disabilities Act structure Handrails on both sides throughout and clear width of Powder coated steel pedestrian guards along all sides   900mm between handrails Provides space for snow storage at both Adams Road   Constructed using reinforced concrete supported on and Simcoe Boulevard helical piles, in order to minimize the depth of excavations and therefore reducing impacts to adjacent properties

  7. 7 RAMP LOCATION PLAN 7

  8. 8 RAMP OPTION HAS LOW IMPACTS TO ADJACENT PROPERTIES Maintains driveway access to  SNOW STORAGE SPACE adjacent homes Structure positioned to  utilizes generally unusable space Structure is kept within Town  right-of-way while maintaining clear space to adjacent properties and structures No adjustments or changes to  adjacent structures required Ease of access to existing  hydro for powering heating cables MAINTAINS CLEAR SNOW STORAGE DRIVEWAY ACCESS SPACE Minimal changes to grading  MAINTAINS CLEAR DRIVEWAY ACCESS and water flow patterns except immediately adjacent the ramp structure 8

  9. 9 IMPACTS DURING CONSTRUCTION During construction the location of the stair TEMPORARY DETOUR ROUTE MAP  crossing will be closed to through pedestrian traffic. A temporary detour route will be used during the construction period Excavations will be kept to a minimum and  will be limited to the area highlighted. Helical pile foundations are being utilized to minimize the depth of excavation The contractor will be responsible for  cleaning roadways and controlling dust during construction Work is planned for summer months when  school is out and is planned to be complete and ready for use before school is in session again in September Temporary local increase in truck traffic for  delivery of equipment and materials would be expected during construction

  10. 10 PROJECT SCHEDULE The project schedule is planned as follows: December 2019: Finalize the design, drawings, and contract documents.  January 2020: Issue the contract documents for public tender.  February 2020: Review the tender submissions and award the contract to a General Contractor.   March-May 2020: Complete tree clearing operations and relocate the gas main. Late May 2020: Construction to begin.  Late August 2020: Construction complete.  10

  11. 11 NEXT STEPS Before you leave: review/address stakeholder comments  have your questions been addressed?  complete relocation of the gas main  have you signed the registry to be informed of the  next phase of the study? finalize the contract documents and issue a tender  to procure a contractor to complete the work have you completed a comment sheet?  Following the PIC: if you have more questions, contact the Town or  Tatham Engineering. CONTACTS MICHAEL S MICHAEL SANFILIPPO ANFILIPPO, B.Sc.Eng, P , B.Sc.Eng, P. Eng. Eng. AMBER LEAL, B.Sc., C.E. AMBER LEAL, B.Sc., C.E.T. Senior Engineer, Project Manager Capital Project Manager Tatham Engineering Limited Town of Innisfil 41 King Street, Unit 4 2101 Innisfil Beach Road Barrie, ON L4N 6B5 Innisfil, ON L9S 1A1 t: (705) 733-9037 x 2074 t: (705) 436-3740 x 3246 e: msanfilippo@tathameng.com e: aleal@innisfil.ca

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend