Agenda Item #11-B I-64/I-264 Ramp Improvements and I-264/Witchduck Road Interchange & Ramp Extension 1 I-64/I-264 Ramp Improvements and I-264/Witchduck Road Interchange & Ramp Extension Project Features Widen WB I-64 to EB I-264


slide-1
SLIDE 1

I-64/I-264 Ramp Improvements and I-264/Witchduck Road Interchange & Ramp Extension

1

Agenda Item #11-B

slide-2
SLIDE 2

I-64/I-264 Ramp Improvements and I-264/Witchduck Road Interchange & Ramp Extension

Project Features

  • Widen WB I-64 to EB I-264 exit ramp
  • New flyover ramp from WB I-64 to EB I-264
  • New two-lane EB I-264 C-D Road
  • Widen EB I-264
  • Newtown Road Interchange
  • Witchduck Road Interchange

2

slide-3
SLIDE 3

I-64/I-264 Ramp Improvements and I-264/Witchduck Road Interchange & Ramp Extension

Two Construction Advertisements

  • I-264/Witchduck – January 2017
  • Maintains original schedule
  • I-64/I-264 – Spring 2016
  • Accelerated schedule
  • RW acquisition
  • Utility relocations

3

slide-4
SLIDE 4

I-64/I-264 Ramp Improvements and I-264/Witchduck Road Interchange & Ramp Extension

Next Steps

  • HRTAC to execute the Interim Project Agreements

(PE & RW)

  • Properly document PE & RW funding in the SYIP
  • Begin Total Take RW acquisition process
  • Begin Partial Take RW acquisition process
  • HRTAC to execute the Standard Project Agreements

(CN)