5245 02 02 72 73 wis 23 wis 11 mineral point county shop
play

5245-02-02,72/73 WIS 23 WIS 11 Mineral Point County Shop Road to - PowerPoint PPT Presentation

5245-02-02,72/73 WIS 23 WIS 11 Mineral Point County Shop Road to Minerva Street Lafayette County Public Involvement Meeting May 3, 2016 5:30 p.m. to 7:30 p.m. Agenda Introductions Project Location Purpose and Need Scope of


  1. 5245-02-02,72/73 WIS 23 WIS 11– Mineral Point County Shop Road to Minerva Street Lafayette County Public Involvement Meeting May 3, 2016 5:30 p.m. to 7:30 p.m.

  2. Agenda  Introductions  Project Location  Purpose and Need  Scope of Work  Project Schedule  Open House 2

  3. Introductions  WisDOT Project Development Supervisor  Bill Strobel, PE  WisDOT Project Manager  Matt Dapp, PE  Design Team  James Rinzel  Brad Groh, PE  Dylan Douglas, PE 3

  4. Project Location End Project Begin Project 4

  5. Project Location 5

  6. Existing Facility  1.5-mile corridor  Arterial Highway  Two-lane urban sections  66’ wide right-of-way (typical), some segments differ 6

  7. Project Need  Pavement Deterioration  Roadway Geometry  Bridge B-33-007 over the Pecatonica River  Intersection Improvements  Other Design Factors 7

  8. Pavement Deterioration  Original concrete still in place from Center Hill Road to the Pecatonica River (built 1966)  Potholes  Block/fatigue cracking 8

  9. Roadway Geometry  Horizontal curvature  Pavement cross slope  Bicycle lane and sidewalk layout 9

  10. Proposed Typical Sections Reconstruction Section 10

  11. Finished Retaining Wall (approx. 3’ high) Finished Short Retaining Wall (approx. 2’ high) 11

  12. Proposed Typical Sections Pavement Replacement Sections 12

  13. Roadway Geometry Existing Centerline Proposed Centerline 13

  14. Roadway Geometry Existing Centerline Proposed Centerline 14

  15. Intersection Improvements  Harriet St. Intersection  Washington St. Intersection  WIS 81 Intersection  Difficult turn movements for large trucks March 2016 (looking southwest) March 2016 (looking west) 15

  16. Intersection Improvements  Harriet Street Intersection  Proposed NB Left Turn Movement WIS 23 / Harriet Street WIS 23 16

  17. Intersection Improvements  Harriet Street Intersection  Proposed SB Right Turn Movement WIS 23 / Harriet Street WIS 23 17

  18. Intersection Improvements  Washington Street Intersection  Proposed NB Right Turn Movement Washington Street WIS 23 / WIS 23 / Harriet Street 18

  19. Intersection Improvements  Washington Street Intersection  Proposed SB Left Turn Movement Washington Street WIS 23 / WIS 23 / Harriet Street 19

  20. Intersection Improvements  WIS 81 Intersection  WB Left Turn Movement WIS 81 WIS 23 20

  21. Intersection Improvements  WIS 81 Intersection  WB Right Turn Movement WIS 23 WIS 81 21

  22. Intersection Improvements  WIS 81 Intersection  NB Right Turn Movement WIS 81 WIS 23 22

  23. Intersection Improvements  WIS 81 Intersection  SB Left Turn Movement WIS 81 WIS 23 23

  24. Other Design Factors  Cul-de-sac Huntington Ct. (south intersection)  Utility (sanitary/water) improvements and upgrades Existing utilities Proposed cul-de-sac location 24

  25. Other Design Factors  Lighting Existing median lighting Existing median lighting (looking (looking south near Alice St.) between Ann St. and Louisa St.) 25

  26. Other Design Factors  Lighting Existing median lighting (looking Existing median lighting (looking between Ann St. and Louisa St.) between Ann St. and Louisa St.) 26

  27. Other Design Factors  Stairs  Encroachments 27

  28. Other Design Factors  Curb ramp upgrades (ADA 1974)  Median parking – safety concerns 28

  29. Traffic  Average Daily Traffic (2013 Count)  2,700 – 10,000 vehicles per day  2041 Forecast (AADT)  3,150 – 11,400 vehicles per day 29

  30. Scope of Work  Agency Coordination  Public Involvement  Environmental Report  Real Estate Plats/Acquisition  Preliminary/Final Design 30

  31. Project Schedule  Public Involvement Meeting #1 May 2016  Archeological Survey May 2016  Historical Survey May 2016  Hydrology Study May 2016  Soil Testing Summer 2016  Environmental Report Submittal February 2017  Public Involvement Meeting #2 February 2017  Survey, Plat Spring 2017  Agency Scoping/Coordination Ongoing  Final Plans May 2020  Public Involvement Meeting #3 Spring/Summer 2021  Construction Summer 2021 31

  32. Input ‘Dot’ Exercise STEP 1 – Place number on the map. STEP 2 – Write number and comment on form. 12 32

  33. 33

  34. WIS 23 Improvement Project Matt Dapp, P.E. – WisDOT Project Manager WisDOT – SW Region 2101 Wright Street Madison, WI 53704 608-246-5353 matthew.dapp@dot.wi.gov 34

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend