5245-02-02, 72 WIS 23 WIS 11– Mineral Point County Shop Road to Minerva Street Lafayette County Public Involvement Meeting #3 October 11, 2018 5:30 p.m. to 7:30 p.m.
5245-02-02, 72 WIS 23 WIS 11 Mineral Point County Shop Road to - - PowerPoint PPT Presentation
5245-02-02, 72 WIS 23 WIS 11 Mineral Point County Shop Road to - - PowerPoint PPT Presentation
5245-02-02, 72 WIS 23 WIS 11 Mineral Point County Shop Road to Minerva Street Lafayette County Public Involvement Meeting #3 October 11, 2018 5:30 p.m. to 7:30 p.m. Project Team WisDOT Project Development Supervisor Bill Strobel,
2
Project Team
WisDOT Project Development Supervisor
- Bill Strobel, PE
WisDOT Project Manager
- Matt Dapp, PE
WisDOT Design Team
- James Rinzel
WisDOT Real Estate Team
- Teresa Klein
- Kema Williams
3
Project Team
Structure Design
- Michael Baker International
Plat Development and Survey
- JT Engineering
Municipal Design
- Delta 3 Engineering
- Vierbicher
- KL Engineering
4
Overview
Project Location Existing Facility Project Needs Project Improvements Project Impacts Project Schedule Open House
5 County Shop Rd Minerva Street
Project Location
6
Existing Facility
1.49-mile roadway section Two-lane urban roadway
- Residential area south of the bridge
Concrete replaced in 1966 Asphalt replaced in 1984 6,900 vehicles per day
- Business area north of the bridge
Asphalt replaced in 1989 2,700 – 10,000 vehicles per day
- Parking lanes
Variable Land Terrain 66 foot right-of-way width
(typical)
7
Project Needs
Pavement Deterioration Structure Deterioration Substandard Roadway Features
- Intersection Geometry
- ADA Concerns
- Crosswalk Locations
Utility Replacements
- Water
- Sanitary
- Lighting
- Storm Sewer
8
Project Improvements
Roadway Sections Superstructure Replacement Intersection Improvements
- OSOW Accommodations
ADA Upgrades Utility Replacements
9
Roadway Sections
Proposed Section County Shop Road to Center Hill Road
10
Roadway Sections
Proposed Section Center Hill Road to Pecatonica River Bridge
11
Retaining Walls
Modular Block Retaining Wall
12
Roadway Sections
Proposed Section Pecatonica River Bridge to Cornelia Street
13
Roadway Sections
Proposed Section Cornelia Street to Harriet Street
14
Roadway Sections
Proposed Section Harriet Street to Mary Street
15
Roadway Sections
Proposed Section Mary Street to Lucy Street
16
Roadway Sections
Proposed Section Lucy Street to Minerva Street
17
Superstructure Replacement
Replace Bridge Deck
- Built 1968, Concrete Overlay 1993
Install Concrete Parapet with Metal Railing Repair Substructure Include 6 ft Sidewalk Lighting on Structure
Center Hill Road/Union Grove Lane Re-alignment
- Improved intersection angle with WIS 23
- Improved vehicle visibility
18
Intersection Improvements
Proposed Location Proposed Location
Huntington Court Re-alignments (Minor)
- Improved intersection angle with WIS 23
- Pedestrian accommodations
19
Intersection Improvements
Proposed Location Proposed Location
Harriet Street Intersection Widenings
- Improved truck turning movements
- Wider paved shoulders and corners
20
Intersection Improvements
Proposed Widening Proposed Widening
Washington Street Cul-de-Sac at Lucy Street
- Improve intersection layout
21
Intersection Improvements
Cul-de-Sac Location
22
ADA Upgrades
ADA Curb Ramps
23
Crosswalk Locations
ADA Curb Ramps Crosswalks Crosswalks
24
Utility Replacement
Water Utilities
- Replace watermain and services from Center Hill Road to
Lucy Street
Sanitary Utilities
- Replace sanitary main sections south of Alice Street and
from Harriet Street to Lucy Street
- Install sanitary main connections at Huntington Court,
Ravine Street and County F
- Replace services from Center Hill Road to River Street and
from Harriet Street to Lucy Street
Lighting
- Replace lighting from bridge to Harriet Street
25
Utility Replacement
Storm Sewer Utilities
- Replace storm sewer main and laterals from Center Hill
Road to Lucy Street
- Install check valves at structure for flooding
26
Project Impacts
Detours Access over Pecatonica River Roadway Shift Real Estate
27
Detour
WIS 23 Detour (30.3 miles)
WIS 81 – 10.3 miles WIS 126 – 5.7 miles US 151 – 14.3 miles
28
Detour
WIS 81 Detour (25.9 miles)
WIS 23 – 6.1 miles WIS 11 – 6.0 miles WIS 78 – 13.8 miles
Access maintained for emergency services and
local residents/businesses
One lane open over bridge during construction
29
Access over Pecatonica River
Temporary Signals
Access maintained for emergency services and
local residents/businesses
One lane open over bridge during construction
30
Access over Pecatonica River
Temporary Signals
31
Roadway Shift
Existing Land Terrain
- Steep west of WIS 23
- Flat east of WIS 23
Proposed Centerline Existing Centerline
32
Real Estate
WisDOT Representatives
- Teresa Klein
- Kema Williams
Real Estate Acquisitions
- 85 Total Properties
- FEE (permanent acquisitions)
- TLE (temporary limited easements)
- Appraisal Staking – Fall 2018
Potential Property Impacts
- Carriage Walk Removal
- Tree Removal
- Access Removal
Real Estate Acquisition
- 2019 - 2020
33
Project Schedule
Public Involvement Meeting #1
May 2016
Archeological Survey
May 2016
Historical Survey
May 2016
Hydrology Study
May 2016
Soil Testing
Summer 2016
Public Involvement Meeting #2
November 2016
Project Plat
July 2018
Environmental Report Submittal
January 2018
Public Involvement Meeting #3
October 11, 2018
Real Estate Acquisitions
2019 – 2020
Utility Coordination
January 2019
Public Involvement Meeting #4
TBD – Prior to Construction
Agency Coordination (DNR, etc.)
Ongoing
Final Plans Due
May 2020
Construction
Spring – Fall 2021
34
Input ‘Dot’ Exercise
STEP 1 – Place number on the map. STEP 2 – Write number and comment
- n form and submit in
comment box.
12
35