An in-person construction information meeting is no longer planned - - PowerPoint PPT Presentation

an in person construction information meeting is no
SMART_READER_LITE
LIVE PREVIEW

An in-person construction information meeting is no longer planned - - PowerPoint PPT Presentation

An in-person construction information meeting is no longer planned based on guidance to limit public gatherings. Please review the information provided on the following slides. This presentation and updates during the projects duration can


slide-1
SLIDE 1

An in-person construction information meeting is no longer planned based on guidance to limit public gatherings. Please review the information provided on the following slides. This presentation and updates during the project’s duration can be found at: https://projects.511wi.gov/wis47shawano/ If you would like to be put on a weekly project update please submit your email address to one of the project contacts on the next slide. Thank you, Wisconsin Department of Transportation

slide-2
SLIDE 2

WIS 47/55

Shawano Creek to the Menominee County Line

Construction Update

June 2020

slide-3
SLIDE 3

Project Contacts

  • Tim Rank, P.E. – WisDOT Project Manager
  • tim.rank@dot.wi.gov; 920-360-2579
  • Josh Heling – Consultant Field Lead
  • joshh@jt-engineering.com; 920-680-7297
  • Prime Contractor
  • Jeff Reesman, Northeast Asphalt
slide-4
SLIDE 4

Update Topics

  • Project Contacts
  • Project Location
  • Proposed Improvements
  • Intersection Improvements
  • Traffic Impacts
  • Construction Schedule
slide-5
SLIDE 5

Project Location

slide-6
SLIDE 6

Proposed Improvements

  • Scope of work includes:
  • Resurface WIS 47/55 and pave five-foot

shoulders

  • Replace the railroad crossing and install new

signals and gates

  • Reconstruct all curb ramps to meet current ADA

requirements

  • Repair spot locations of curb and gutter
  • Replace guardrails and two drainage culverts
slide-7
SLIDE 7

Proposed Improvements

  • Scope of work, continued:
  • Install new signing, pavement marking, and centerline

rumble strips

  • Modify intersections at the following locations

to improve traffic flow, efficiency and safety:

  • Anderson Avenue
  • County H
  • Maple Avenue
  • Frailing Lane
  • Curt Black Road
  • Balsam Row Road
  • Old Keshena Road
slide-8
SLIDE 8

Intersection Improvements

County H & Maple Avenue

Elm Ave Maple Ave Old Keshena Rd

slide-9
SLIDE 9

Intersection Improvements

Frailing Lane

slide-10
SLIDE 10

Intersection Improvements

  • Curt Black Road
  • Widen for northbound right turn lane
  • Balsam Row Road
  • Widen shoulder to standard width along

the northbound by-pass lane

  • Old Keshena Road
  • Put in cul-de-sac in to provide marked

bike trail

slide-11
SLIDE 11

Traffic Impacts

  • Single lane closures with flagging conditions
  • Single lane closure for bridge work over

Shawano Creek controlled by temporary traffic signals

  • Short term closure with marked detour during

railroad crossing replacement

  • Shoulder closures in areas of intersections

improvements and guardrails

  • Local and emergency access will be

maintained

slide-12
SLIDE 12

Construction Schedule

Construction Start: June 22, 2020 Anticipated completion: end of September 2020

  • The above deadlines will be impacted based on weather and third party

coordination for railroad crossing reconstruction

Holiday Restrictions (No work/hauling allowed)

  • From noon Thursday, July 2, 2020 to 6 a.m. Monday, July 6, 2020
  • From 6 a.m. Wednesday September 2 to 6 a.m. Tuesday, September 8