An in-person construction information meeting is no longer planned based on guidance to limit public gatherings. Please review the information provided on the following slides. This presentation and updates during the project’s duration can be found at: https://projects.511wi.gov/wis47shawano/ If you would like to be put on a weekly project update please submit your email address to one of the project contacts on the next slide. Thank you, Wisconsin Department of Transportation
An in-person construction information meeting is no longer planned - - PowerPoint PPT Presentation
An in-person construction information meeting is no longer planned - - PowerPoint PPT Presentation
An in-person construction information meeting is no longer planned based on guidance to limit public gatherings. Please review the information provided on the following slides. This presentation and updates during the projects duration can
SLIDE 1
SLIDE 2
WIS 47/55
Shawano Creek to the Menominee County Line
Construction Update
June 2020
SLIDE 3
Project Contacts
- Tim Rank, P.E. – WisDOT Project Manager
- tim.rank@dot.wi.gov; 920-360-2579
- Josh Heling – Consultant Field Lead
- joshh@jt-engineering.com; 920-680-7297
- Prime Contractor
- Jeff Reesman, Northeast Asphalt
SLIDE 4
Update Topics
- Project Contacts
- Project Location
- Proposed Improvements
- Intersection Improvements
- Traffic Impacts
- Construction Schedule
SLIDE 5
Project Location
SLIDE 6
Proposed Improvements
- Scope of work includes:
- Resurface WIS 47/55 and pave five-foot
shoulders
- Replace the railroad crossing and install new
signals and gates
- Reconstruct all curb ramps to meet current ADA
requirements
- Repair spot locations of curb and gutter
- Replace guardrails and two drainage culverts
SLIDE 7
Proposed Improvements
- Scope of work, continued:
- Install new signing, pavement marking, and centerline
rumble strips
- Modify intersections at the following locations
to improve traffic flow, efficiency and safety:
- Anderson Avenue
- County H
- Maple Avenue
- Frailing Lane
- Curt Black Road
- Balsam Row Road
- Old Keshena Road
SLIDE 8
Intersection Improvements
County H & Maple Avenue
Elm Ave Maple Ave Old Keshena Rd
SLIDE 9
Intersection Improvements
Frailing Lane
SLIDE 10
Intersection Improvements
- Curt Black Road
- Widen for northbound right turn lane
- Balsam Row Road
- Widen shoulder to standard width along
the northbound by-pass lane
- Old Keshena Road
- Put in cul-de-sac in to provide marked
bike trail
SLIDE 11
Traffic Impacts
- Single lane closures with flagging conditions
- Single lane closure for bridge work over
Shawano Creek controlled by temporary traffic signals
- Short term closure with marked detour during
railroad crossing replacement
- Shoulder closures in areas of intersections
improvements and guardrails
- Local and emergency access will be
maintained
SLIDE 12
Construction Schedule
Construction Start: June 22, 2020 Anticipated completion: end of September 2020
- The above deadlines will be impacted based on weather and third party
coordination for railroad crossing reconstruction
Holiday Restrictions (No work/hauling allowed)
- From noon Thursday, July 2, 2020 to 6 a.m. Monday, July 6, 2020
- From 6 a.m. Wednesday September 2 to 6 a.m. Tuesday, September 8