Preconstruction Community Meeting Larry Mathena Project Manager - - PowerPoint PPT Presentation

preconstruction community meeting larry mathena project
SMART_READER_LITE
LIVE PREVIEW

Preconstruction Community Meeting Larry Mathena Project Manager - - PowerPoint PPT Presentation

SHIPLEYS CHOICE DAM REHABILITATION PROJECT Preconstruction Community Meeting Larry Mathena Project Manager Anne Arundel County Dept. of Public Works Shipleys Choice Elementary School September 13, 2018 DPWandYOU.com | Making a


slide-1
SLIDE 1

DPWandYOU.com | Making a difference, together

SHIPLEY’S CHOICE DAM REHABILITATION PROJECT

Shipley’s Choice Elementary School September 13, 2018

Larry Mathena – Project Manager

Anne Arundel County Dept. of Public Works

Preconstruction Community Meeting

slide-2
SLIDE 2

DPWandYOU.com | Making a difference, together

Agenda

2

  • 1. Project Background
  • 2. Preconstruction Activities
  • 3. Construction Phases & Features
  • 4. Road Closure
  • 5. Planting Plan
  • 6. Construction Schedule
  • 7. Project Updates
  • 8. Questions

* Please sign in & grab a handout

slide-3
SLIDE 3

DPWandYOU.com | Making a difference, together

Project Background – Shipley’s Dam

3

  • Dam built in 1981
  • Seepage & Settlement

Issues

  • MDE deemed dam unsafe

& directs County to remove

  • County worked w/ JMT to

complete design for Dam Removal

  • Construction Contract

awarded to Paydirt

slide-4
SLIDE 4

DPWandYOU.com | Making a difference, together

Preconstruction Activities – Overhead Line Relocation

  • n West Benfield Road

4

  • Temp. Relocate OH Line around New Culvert
  • Street light relocated (Pole to be removed)
  • BGE, Comcast, Verizon to relocate lines
  • OH lines replaced

after Culvert construction

slide-5
SLIDE 5

DPWandYOU.com | Making a difference, together

Construction Phases

5

Phase 1 Culvert Replacement Phase 2 Shipley’s Dam Removal

  • Construction

in 2 Phases

  • Zoning
  • R2
  • OS
slide-6
SLIDE 6

DPWandYOU.com | Making a difference, together

Phase 1 – Stream Diversion + Erosion & Sediment Control

  • Place ESC

Features

  • Install

stream diversion

slide-7
SLIDE 7

DPWandYOU.com | Making a difference, together

Phase 1 – Public Utility Relocations Gas, Water, Force Main, Sanitary/Storm Sewers

  • Utility Bypasses
  • No interruption

in service

  • Existing/New

Culverts in Red

slide-8
SLIDE 8

DPWandYOU.com | Making a difference, together

Phase 1 – Remove Ex. Culvert + Install New Culvert

New 7’x10’ Concrete Box Culvert

slide-9
SLIDE 9

DPWandYOU.com | Making a difference, together

Phase 1 – New Culvert Profile

slide-10
SLIDE 10

DPWandYOU.com | Making a difference, together

Pile Driving & Preconstruction Home Surveys

10

  • Home surveys conducted by County’s contractor Seismic Surveys
  • Preconstruction survey of homes and other structures – Document existing conditions
  • Post-construction survey also conducted
  • Need pre/post surveys to help determine if damage occurred during construction

Pile Driving for Culvert

  • Required due to soft subsoil
  • 78 Concrete Piles to be used
  • Daytime work only
  • Vibration levels will be monitored
slide-11
SLIDE 11

DPWandYOU.com | Making a difference, together

Phase 1 – In Stream Work + Grading

slide-12
SLIDE 12

DPWandYOU.com | Making a difference, together

12

Road Closed between Pixie Dr & Severnside Dr

Phase 1 Road Closure Detour Plan

  • W Benfield Road closed

6+ months

  • Sign posted 2 weeks

before closing

  • Paydirt proposing change

to Precast Culvert – Could save time

  • County Traffic Engineer

will consider signal changes (will monitor traffic during construction)

slide-13
SLIDE 13

DPWandYOU.com | Making a difference, together

  • Install Filter Logs + Silt

Fence

  • Install Haul Road

down to stream

  • Begin removal of dam

embankment

Phase 2 Dam Removal

Oak Stump Dr Cul-de-Sac Shipley’s Choice Dam

slide-14
SLIDE 14

DPWandYOU.com | Making a difference, together

Phase 2 Dam Removal

  • Earth fill from Dam

placed along east hillside

  • Drain along slope to

intercept runoff

  • Bear Branch channel

reestablished after outlet pipe removal

slide-15
SLIDE 15

DPWandYOU.com | Making a difference, together

Phase 1 & 2 – Planting Plan

  • Seed & Plant

disturbed areas

  • 141 Trees
  • 493 Shrubs
  • 1676 Live

Stakes

slide-16
SLIDE 16

DPWandYOU.com | Making a difference, together

Tentative Construction Schedule

16

  • Oct 2018

Ph 1 Construction begins w/ Erosion & Sediment Control Utility Relocations/Road Closure

  • Winter

Ph 1 Culvert Installation

  • Spring 2019

Ph 1 Culvert completed/Road Opened

  • Summer

Ph 2 Dam removal begins

  • Late Fall 2019

Ph 2 Construction complete

* Paydirt will provide Construction Schedule by late Sep

slide-17
SLIDE 17

DPWandYOU.com | Making a difference, together

Project Updates

17

  • Monthly Updates on the Shipley’s Dam Project are emailed to the

following HOAs & Organizations:

  • Shipley’s Choice HOA & Community Assoc, Greater Severna Park Council, Point

Field Landing Community Assoc, Crain West, Ben Oaks/Severn River Assoc

  • Monthly Project Update will include:
  • Updated construction schedule, latest activities, road closure updates
  • Project Updates may also be found on the County’s Website
  • For web address, see Handout
slide-18
SLIDE 18

DPWandYOU.com | Making a difference, together

Contact Info (on Handout)

Larry Mathena

Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva Road, MS 7217 Annapolis, MD 21401 (410) 222-7908 pwmath00@aacounty.org

Alternate POC:

Greg LeBlanc Same Address (410) 222-0043 pwlebl89@aacounty.org

slide-19
SLIDE 19

DPWandYOU.com | Making a difference, together

Questions or Comments?

19

slide-20
SLIDE 20

DPWandYOU.com | Making a difference, together

Bureau of Utility Operations

24-Hour Emergency Water Services: (410) 222-8400 Billing Inquiries: (410) 222-1144

Bureau of Waste Management Services

Bulk Trash Service/Curbside Collections: (410) 222-6100

Bureau of Highways

Northern District: (410) 222-6120 Central District: (410) 222-7940 Southern District: (410) 222-1933 Traffic Lights/Signs: (410) 222-1940

Bureau of Engineering

General Inquiries: (410) 222-7500