CONSTRUCTION LOGISTICS PROGRAMME
Construction Logistics Improvement Group Meeting 5
CONSTRUCTION LOGISTICS PROGRAMME Construction Logistics Improvement - - PowerPoint PPT Presentation
CONSTRUCTION LOGISTICS PROGRAMME Construction Logistics Improvement Group Meeting 5 Housekeeping Ref Item Timing Lead 1 Introductions and actions from last meeting 15 GD Product launch: new Construction Logistics Plan guidance and 2 25
Construction Logistics Improvement Group Meeting 5
Housekeeping
Ref Item Timing Lead
1 Introductions and actions from last meeting 15 GD 2 Product launch: new Construction Logistics Plan guidance and training 25 Arup 3 Final report: Investigating the barriers to transporting bulk construction materials and waste by river and rail 20 SDG 4 Construction Logistics communications planning 20 GD 5 Break 15 6 Discussion: Defining consolidation, consolidation centres and consolidation activity 20 MS 7 Progress update: Investigating the construction industry’s use of HGV types 20 WSP 8 Project overview: Tideway Logistics 25 Tideway 9 Progress updates: Construction Logistics Baseline Model and Water Freight Toolkit 15 GD 10 Future meeting dates, summary and AOB 10 GD
Introductions ▪ Organisation and role
Standard method of communications
Establishing industry change initiatives
Actions from CLIG 4 – 29 March 2017
Item Action Progress Construction Logistics Plan
include the third map (Figure 3 of the exemplar) into the guidance
interested in participating in the initial CLP pilot training sessions Complete Communicating the Programme
Complete Investigating the use of HGV types
to participate in a study interview / suggest who else to involve Complete Investigating the impact of delivery inefficiencies 5 .Call to CLIG stated in the minutes - any further comments or suggestions for the study please contact AECOM Complete Summary and AOB
explore bringing the group and CLIG together Complete
A reminder of the ambition:
standardise data fields – EFFICIENT
enable accurate review – COMPARABLE
Since I last presented to you the guidance has been completed, incorporating the feedback from each of you The revised CLP Guidance is complete and can be found at:
It is accompanied by supporting documents:
courses now Accredited by the CILT
places filled so far
Practitioners!
Training is underway. Forthcoming dates:
(Arup) FOUNDATION
FOUNDATION
(Arup) FOUNDATION
(Arup) PRACTITIONER
(WSP, Holborn) PRACTITIONER
Strong focus on communication and
Developers, Contractors, Local Authority personnel, Planners, Vehicle Operators
Forthcoming dates:
FOUNDATION
FOUNDATION
(City of London) FOUNDATION
(City of London) FOUNDATION
dan.evanson@arup.co.uk
|
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 17
|
Project Context
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 18
|
Methodology
Organisation by sector % by sector TOTAL Contractor 39% 62 Developer 9% 15 Supply Chain 13% 21 Borough/Planner 11% 17 Key stakeholder 27% 43 Total 100% 160 27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 19
engagement process allowed a variety
the construction industry.
this project providing both qualitative and quantitative responses to the issues being analysed.
|
time / early morning)
(i.e. barges / trains)
industry
rail passenger movements)
Investigating the barriers to transporting bulk construction materials and waste by river and rail 20
Physical Barriers Logistical Barriers
between river / rail and the site
policies
CLPs
policy
Policy Barriers
costs
the industry – value for money
Financial Barriers
potential users.
Industry Related Barriers
Identification of Barriers…..
27/07/2017
|
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 21
Key Findings
|
Key Finding 1 - Responsibility
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 22
|
Key Finding 2 - Awareness
knowledge or access to appropriate information, decision makers are unable to make an informed decision about the likely feasibility and viability of the river and rail without expending substantial resources and costs.
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 23
|
Key Finding 3 - Improving availability of information
stakeholders found it to be an arduous process with great difficulty in identifying relevant individuals to contact
coherent and up-to-date toolkit/s for the entire industry would provide a resource for decision makers to make informed choices for both river and rail.
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 24
|
Key Finding 4 - Timing
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 25
|
Key Findings 5 & 6 - Resource demand
heads, which are consistently under threat from development.
therefore there is increasing pressure to develop on the valuable land they occupy.
very specific to that sector. There was a perception that the relevant skills across the industry were dwindling due to the lack of experienced
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 26
|
Key Finding 7 - Policy
role in encouraging river and rail use
developments are assessed lies with planners and key stakeholders, who have the power to approve, reject or amend approaches to projects through the planning process.
Logistic Plans was believed to be an effective way
process, whilst improving the awareness and knowledge of those approving planning applications is also considered to be a significant positive step forward.
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 27
|
Benefits
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 28
|
Conclusion
barriers discussed in relation to Policy and Awareness the ability for projects to use river and rail in the transportation of construction materials and waste will become easier.
measures targeted at Policy and Awareness has the ability to assist in reducing air pollution, easing congestion and simplifying the logistics
27/07/2017 Investigating the barriers to transporting bulk construction materials and waste by river and rail 29
strategic challenges currently facing London.
DISCLAIMER: This work may only be used within the context and scope of work for which Steer Davies Gleave was commissioned and may not be relied upon in part or whole by any third party or be used for any other purpose. Any person choosing to use any part of this work without the express and written permission of Steer Davies Gleave shall be deemed to confirm their agreement to indemnify Steer Davies Gleave for all loss or damage resulting therefrom.
Matthew Clark Matthew.Clark@sdgworld.net
Standard method of communications
Establishing industry change initiatives Some effect but no industry wide movement Localised action but not debated in any detail
Standard method of communications Establishing industry change initiatives
Background to successful communications Powerful industry-led change initiatives
Over 400 champions signed up Over 4000 operators accredited Over 1000 stakeholders involved
Communicating construction logistics Where do we want to be?
Communicating construction logistics How are we going to get there?
Research
industry’s use of HGV types
construction delivery inefficiencies
Rail
Royal Construction Logistics Strategy
Communicating construction logistics Discussion points
carried through all assets?
independent from the TfL dot gov domain?
does the stakeholder engagement look like?
How should programme communications be funded?
In association with
Glen Davies
In association with
In association with
measures
services
research specifications
In association with
In association with
Defining consolidation, consolidation centres and consolidation activity Mark Starosolsky
In association with
In association with
Proposal 15 d) Ensuring that all London is within a 30-minute drive of a construction consolidation centre and encouraging their use through Construction Logistics Plans and the planning process
In association with
How would we define construction consolidation? What’s in? What’s out?
In association with
What’s an appropriate maximum drive time from consolidation centre to site and how do we get more of it?
In association with
What does CLIG want to see in the next update of the directory?
In association with
In association with
Investigating the construction industry’s use of HGV types Ian Brooker WSP
49
Contents
— What's The Problem? — Mitigation — Industry Trends — Way Forward — We Still Need Your Help
50
What’s The Problem
— Articulated vehicles have a higher payload — Operating costs only slightly higher so lower cost per Tonne — But . . . .
— Safety — Access — Attitude
51
Safety Issues
— MPA Data very poor, but may be best available — HSE identified 6 fatal and 68 major accidents involving goods transport vehicles on construction sites between 2003/4 and 2007/8
Principal Circumstance of Overturn Totals 2011 Transverse slope at point of discharge 6 14 Unevenly loaded to one side Unevenly loaded (front to back) Other reason 8 2012 Transverse slope at point of discharge 4 14 Unevenly loaded to one side 4 Unevenly loaded (front to back) Other reason 6 2013 Transverse slope at point of discharge 8 22 Unevenly loaded to one side 2 Unevenly loaded (front to back) Other reason 12 50
52
Tipover Causes
— The MPA and construction companies have extensively researched the cause of tipovers on site.
— Tipping on an incline or uneven ground — Tipping on soft ground that cause the trailer to sink and lean — Not tipping with the tractor and trailer in line — Load sticking in body, on one side of the body, uneven
— Moving forward causing instability whilst load at height — Raising body too quickly with excessive product retained inside — Load freezing / sticking to body floor — Poor maintenance of the chassis and suspension — Strong cross winds
53
Tipover Causes
54
Access
— Several concerns about access:
— Turning circle — Single powered axle on artics — General issues of site conditions favouring off road vehicles
55
Attitude / Status Quo
— Perception that articulated vehicles need specially designed sites — Construction sites constantly changing — The assumption is that rigids will be used — Some contractors insist on rigids — Hauliers invest in the vehicles which they can get most use from — Mismatch of costs (who makes the effort) and benefits (from the lower cost and external benefits)
56
But . . . .
— Incidence of accidents still not clear — Artics and rigids both meet the same standard (7 degrees) — Arguably artic turning circle is no worse than rigid — Artics access most construction sites – to deliver steel, windows, etc. — Some developers and contractors take a close interest in payloads – particularly major infrastructure projects
57
Mitigation
— Industry Standards and Best Practice — Vehicle Design — Inclinometers — Liners — Tipping Frames — Moving Floors
58
Industry Standards: CLOCS Site Conditions
— However, the site assessment
characteristics:
— Ground condition 1: Approach angle. — Ground condition 2: Material type. — Ground condition 3: Rutting and bumps. — Ground condition 4: Water.
— The ground condition ratings are not intended to and cannot be used to assess the availability of a safe unloading area for tippers.
59
Industry Standards: MPA
60
Mitigation and Prevention
— Vehicle Design
— Trailer rigidity — Real axle steering
— Inclinometers — Cameras — Tipping Frames — Moving Floors / Ejectors
61
Industry Trends
— A definite move towards more use of artics, particularly moving floors — Focussed initially on:
— “Internal” movements controlled by aggregate cos — Major infrastructure projects — Longer distance movements
— Case studies of suppliers working closely with developers and contractors to demonstrate the benefits of articulated vehicles — Slow process — When will this become viable for smaller hauliers?
62
The Way Forward
— Use of articulated vehicles should be the norm, not the exception — CLPs should require evidence of why articulated vehicles cannot be used — Developers need to become more involved – lower costs and reduced impact on the community — Dissemination of best practice — More research into tipover incidence
63
We Still Need Your Help
— We particularly need to speak to:
— Developers — Dealers — Drivers — International case studies
wsp.com
In association with
Tideway logistics Gordon Battye
66
Project Background
67
Project background
Current Situation
68
Project background
Current situation
69
Project background
70
Project background
Intercepting the CSOs
71
The project
72
What are we building?
73
Delivery Model
2014
formed to deliver the project.
West - BMB Central - FLO East - CVB System Integrator
74
Tideway Sites
75
The tunnel route and worksites
76
Typical CSO Connection / Intervention shaft
77
Physical legacy
Blackfriars: After
78
Timetable for Construction
Main works preliminary construction begins
Tunnelling begins
Tunnelling ends
Project completion
Main Works contracts awarded
79
Materials need to build it.
Material Estimated quantity Excavated material 4,612,000 Tonnes Demolition material 137,000 Tonnes Ready mixed concrete 635,000 Tonnes Bulk fill material 651,000 Tonnes Precast concrete shaft and tunnel linings 613,000 Tonnes Bulk aggregates for onsite production of concrete and grout 425,000 Tonnes Site consumables (formwork / pipe / track etc.) 313,000 Tonnes Plant and equipment 164,000 Tonnes Cement and bentonite 122,000 Tonnes Steel reinforcement for concrete structures 97,000 Tonnes Office supplies 40,000 Tonnes TOTAL: 7,809,000 Tonnes
80
Road Transport
81
Tideway HGV Numbers (Including More by River)
All by Road DCO Contract More By River East 172,760 93,940 77,820 61,100 Central 232,240 94,210 51,640 45,740 West 101,600 50,970 37,980 33,280 100,000 200,000 300,000 400,000 500,000 600,000
HGV numbers - All worksites
West Central East 53% reduction 67% reduction 72% reduction
82
HGV Numbers
the peak month.
construction period.
construction period.
Residual HGV Numbers
83
Tideway Strategy for VRUs
performance in infrastructure projects within the UK.
comprehensively raise standards above existing industry norms.
“The RightwaY “
84
Tideway Strategy for VRUs
the environment; as well as driving best practice driving forward”
construction logistics plans.
What are we doing?
85
Vehicle Movement Planning & Management
ensure:
All vehicles checked at gate for:
Tideway Strategy for VRUs
86
Checks on proposed operators / transport providers
type of vehicle(s) and business they operate
Tideway Strategy for VRUs
87
Vehicle checks
excavators and volumetric mixers
based
Tideway Strategy for VRUs
88
Driver training requirements
site) of any vehicle, including vans
an alternative)
Tideway Strategy for VRUs
89
River Transport
90
Key Commitments to River Transport
Strategy(APP207.02)
reducing estimated total number of HGVs from approximately 506,000 to 239,000
including in MWC tenders and the More by River initiatives.
140,000.
91
River Transport Strategy
approve elements of the works affecting the River Thames, and the local and strategic highway network.
The Strategy will be secured through the project wide requirement PW15 in the Draft DCO which provides: “The authorised development shall be carried out in accordance with Section 4 and Schedules 1 to 7 of the River Transport Strategy (document reference APP180), or such updated version of the River Transport Strategy which is the result of any approval given or other decision taken further to the terms of the River Transport Strategy.”
Overview and Principles
92
Key Commitments to River Transport
DCO committed ‘Specified’ materials for river transport:
Additional materials for river transport now includes:
93
Marine Logistics - Implementation
compared to the DCO estimate of 11,000 movements.
reduced due to change in barge sizes.
indicated by PLA.
the barge size, key example is change from 800t to 1,500t barges.
eliminating need to tranship to take to other locations such Wallasea
94
Tideway predicted vessel movements per day
2 4 6 8 10 12 Jan-16 Mar-16 May-16 Jul-16 Sep-16 Nov-16 Jan-17 Mar-17 May-17 Jul-17 Sep-17 Nov-17 Jan-18 Mar-18 May-18 Jul-18 Sep-18 Nov-18 Jan-19 Mar-19 May-19 Jul-19 Sep-19 Nov-19 Jan-20 Mar-20 May-20 Jul-20 Sep-20 Nov-20 Jan-21 Mar-21 May-21 Includes: Excavated materials Cofferdam fill Segments Secondary lining More by River Excludes: Other site servicing activities Sum of Total - TTT East Sum of Total - TTT West Sum of Total - TTT Central
95
Marine Logistics - Implementation
movements/day, mainly day time.
existing freight traffic on the River.
include passenger services and leisure vessels.
96
Marine Logistics - Implementation
experienced existing river transport providers.
97
Marine Logistics - Implementation
least 3 staff/tug.
98
Marine Logistics - Implementation
Enhancing Marine Safety and Training
Thames Skills Academy
personnel.
members.
99
Marine Logistics - Implementation
Marine Training Programme:
validation.
Safety Management:
increased safety standards.
100
Vessel movements
Deemed Marine Licence, and Schedule 16 PLA Protective Provisions, River Regulators (4WLA))
River Movement Planning and Monitoring System
101
Lessons Learned?
102
What has been learned?
In association with
Upcoming technical research projects
In association with
Water Freight toolkit - Commissioned
tool that maps suitable wharves and also unloading and loading areas on the Grand Union Canal (Mainline and Paddington)
In association with
Baseline model - Tender out
quantifies construction logistics operations by mode, load and vehicle type in London
destination and also the impacts generated by construction logistic activity in London in 2017
In association with
Any other business and future meeting dates
In association with
In association with
Friday 20 October 2017
Arup 13 Fitzroy Street W1T 4BQ
Wednesday 28 February 2018
City of London Guildhall EC2P 2EJ
In association with
enquiries@constructionlogistics.org.uk